29 July: Works due for completion mid-September

Roadworks are progressing well on repairs at Blue Knob Road, Nimbin, with work expected to be complete by mid-September.

Council is close to finishing several major components of the project with works such as tree removal and the bulk of drainage now complete. Around half of the major earthworks to prepare for the new road material are also finished.

The final and more visible stages of the project will take shape over the next six weeks. This includes the final kerb and gutter as well as placing the new base material on the road, adjusting the height of the road, road sealing, signage and line marking.

There have been minimal wet weather delays during this project (touch wood!) and we would like to thank residents for your patience as these essential roadworks continue.

If you have any questions regarding the project you can contact Project Manager Luke Wakefield directly on 1300 87 83 87 or email luke.wakefield@lismore.nsw.gov.au.


Share 29 July: Works due for completion mid-September on Facebook Share 29 July: Works due for completion mid-September on Twitter Share 29 July: Works due for completion mid-September on Linkedin Email 29 July: Works due for completion mid-September link

This project is now complete. Thank you for your interest and patience while these essential roadworks took place.