Bungabbee Bridge replacement update: June 2021
Work is progressing well on the bridge replacement. We've included some photos to the right hand side to show the works, for those that are interested.
Pre-construction activities such as compound set up, vegetation works, piling pad construction, temporary track construction and erosion and sediment controls are currently being undertaken.
Following this work, a piling contractor will undertake pile installation. We are expecting this activity to take 1 week, weather dependent.
The existing bridge will remain open until commissioning of the new bridge. The temporary track is for construction traffic plant/machinery only.
The current program suggests an approximate 16-week construction time frame starting from early June. Commencement of work was delayed due to weather, contractor availability and conflicting project priorities.
Below is a summary of the different activities that will take place on this project, in sequential order:
• Preconstruction;
• Earthworks & piling;
• Abutment construction;
• Beam/ girder installation;
• Deck construction;
• Earthworks/ backfilling & drainage;
• Removal of existing structure;
• Road furniture; &
• Demobilisation.