Bungabbee Bridge Update: 16 July
We are making progress on the Bungabbee Bridge replacement. We have had to install temporary working platforms and a creek crossing for the piling rig to install the reinforced concrete piles. These concrete piles have now been installed and Council’s bridge construction team is currently onsite cutting the piles to size (see photo on the right hand side of this page.) This is in preparation for the next stage of construction which will see the forming up of both abutments A & B. Work is currently scheduled to be completed by the end of September, however this is subject to no further issues with supply of reinforcing steel and COVID-19 restrictions affecting overseas suppliers.