Monday, 5 September 2022
With the steel structure now erected, all foundations and underground infrastructure also installed; the Clyde Campbell Solar Carpark is beginning to make it's mark in our community.
Throughout August, 90% of the asphalt works have also been completed, including flood damaged area.
The solar panels have arrived at site ready for installation, with the project remaining on schedule to be completed for late October.
Council have also been consulting with Advisory Groups to ensure our community interests are considered for this project, including provision for additional accessible parking spaces and public art. Updates will be posted to this page as these works progress.
This project is now complete.