Share July 6 2022 on Facebook
Share July 6 2022 on Linkedin
Email July 6 2022 link
Dunoon Road works at Boomerang Creek were completed on June 28th. Additional pothole repair works for Dunoon Road will be completed over the coming weeks.
Share 28th June 2022 - Project Wrap Up on Facebook
Share 28th June 2022 - Project Wrap Up on Linkedin
Email 28th June 2022 - Project Wrap Up link
During the 28 February natural disaster, Boomerang Creek at Dunoon Road over-topped the embankment causing significant damage on the downstream side.
Restoration of this section of the road was prioritised with emergency funding after the initial assessments by geotechnical engineers deemed the remaining embankment unsafe.
Transport for NSW works crew, under Council supervision, carefully reconstructed the embankment by using rock. It was a difficult project to manage due to environmental restraints, extended periods of wet weather and associated delays due to saturated pavement material.
We would like to thank the community for its patience with a long detour in place for the majority of the works.
Share 17th June 2022 on Facebook
Share 17th June 2022 on Linkedin
Email 17th June 2022 link
Dunoon Road is open, with caution to traffic.
Pavement has been placed, with the final stages being the seal to go ahead this week (weather permitting).
Please drive with care, and thank you to the community for their ongoing patience.
Share 9 June 2022 on Facebook
Share 9 June 2022 on Linkedin
Email 9 June 2022 link
Seal and continued works of Dunoon Road are scheduled for Tuesday 14th. Pavement material will require replacing due to heavy rain and the shady nature of the site.
Motorists are advised to use caution. We apologise for any inconvenience.
Funding has been approved to heavy patch and stabilise damaged sections of Duncan Road to Corndale Road. Works are scheduled for the end of the June.
Share 3 June 2022 on Facebook
Share 3 June 2022 on Linkedin
Email 3 June 2022 link
Unfortunately the road seal planned for Monday 6th, has been postponed. It is not possible to carry out this work with wet subgrade.
Road will be open from tonight under traffic control devices. Works will recommence 14th Jun.
Thank you for your ongoing patience.
Share 31 May 2022 on Facebook
Share 31 May 2022 on Linkedin
Email 31 May 2022 link
With improved weather, works are finally continuing to finalise the works on Dunoon Road.
At this stage, spray seal is scheduled for Monday 6th June. Shall this work proceed, the road will reopen by the afternoon.
Thank you for your ongoing patience, and we are glad to be sharing with you this news.
Share May 16th 2022 on Facebook
Share May 16th 2022 on Linkedin
Email May 16th 2022 link
Dunoon Road will remain closed until further notice. Works have been completed, however the road cannot be sealed due to ongoing wet weather.
If you are affected by this ongoing road closure, please reach out to rebecca.sproule@lismore.com.au
We will use your feedback to create a local access plan, and work with you until the road can be re-opened.
We apologise for the inconvenience and thank the community for their ongoing patience.
Share May 3rd 2022 on Facebook
Share May 3rd 2022 on Linkedin
Email May 3rd 2022 link
Due to ongoing rain, the expected completion date of road works on Dunoon Road between Dorroughby and Repentance Creek roads has been extended until 15 May. Signage at the detour points will be updated to notify road users of the road closure.
Material from the quarry used to complete the works is too wet, resulting in slower transport. To ensure work continues effectively, our teams are completing other Dunoon Road surfacing works in the meantime.
The full works include the excavation of existing road surface down to access base of the embankment, reconstruction of the embankment using rock and select fill and reconstruction of the pavement and sealed pavement.
We apologise for the delay and thank the community for their patience at this time.
Share April 4th 2022 on Facebook
Share April 4th 2022 on Linkedin
Email April 4th 2022 link
Works are due to begin today. Residents and community members are encouraged utilise the Q&A on this page for any concerns and questions.
A letter drop has been completed, with local residents of the affected roads notified. Updates will available on this page as this project progresses.
Weather is a current concern, that may add delays to part of the works completed, affecting the completion timeline. Please be advised updates will be posted, with additional letter drops for any major changes.
We thank the community for their patience and understanding.