26 April 2021: Project Update
Joe Lokic, the Project Manager for this project has confirmed that there are no road closures planned for this week and that access will be as normal (with the exception of one business that is being dealt with directly). He has also provided the following information:
- This week storm water drainage and earthworks will be complete
- 50% of the E2 kerb works will be complete
- 50% of the gutter works will be complete
- Sub base works will commence late in the week
Share 26 April 2021: Project Update on Facebook
Share 26 April 2021: Project Update on Twitter
Share 26 April 2021: Project Update on Linkedin
Email 26 April 2021: Project Update link
Consultation has concluded