Side Track Access - 22 July 2022

The side-track access for Fernside Bridge is on schedule to be open for vehicles by 29th July (pending weather). This will allow vehicles over 3.5tonne (GMV) access to and from Fernside Road, while restoration works are considered for Fernside Bridge.

Additional pipes for higher creek flow have been installed as an added precaution. To finalise the works, shotcrete, sealing and tidy up will be carried out this week.

We appreciate the ongoing patience of the community while this side-track access for heavy vehicles was installed.