Program Update - July 2023
Town Bridge, Terania Creek Works
Piling works are well underway with the installation of the four x 1.2m diameter x 13.5m deep bored concrete piles.
Following completion of the piling activities, works will commence on forming up the abutments. The steel bridge structure has also recently been dispatched from France and is currently on route and is expected in the Port of Brisbane in approximately 45 days.
The innovative steel structure has been constructed in France and will be launched into place in one piece. Unique for the area, this type of structure will be the first in the region. A planned completion date is scheduled for September 2023, subject to weather, contractor, and material availability.