Community Update: 10 June 2021
Work is progressing as planned on the Johnston Road repairs.
Pre-construction activities such as compound set up, clearing works, drainage culvert construction and erosion and sediment controls are currently being undertaken. The majority of the works are currently focused on completing the drainage aspect of the project to allow road reconstruction works to commence. Drainage works are estimated to take 1-2 weeks.
The current program suggests an approximate 10-week construction time frame. Our schedule is on track and, at this stage, we have experienced no unforeseen delays.
Share Community Update: 10 June 2021 on Facebook
Share Community Update: 10 June 2021 on Twitter
Share Community Update: 10 June 2021 on Linkedin
Email Community Update: 10 June 2021 link
These works are complete.