July 12 2022

Bridge construction works are now well underway. Landing bridge beams were installed yesterday at Keerrong Bridge.

Due to the February 28 disaster and March flooding events, the collapsed culvert structure located north of the intersection with Dudgeon Road is being replaced with a new 7.2m wide by 16.1m long InQuik bridge.

Works on the bridge are expected to be finalised by the end of August 2022, pending weather conditions.

Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

Keerrong Road is also scheduled to undergo pavement repairs on some sections of severely damaged areas from Wednesday July 13th. Initially the works will start with drainage remediation to allow water to drain from the pavement. Following these works there will be a pavement stabilisation crew mobilising to site to stabilise the existing pavement. As well as adding an additional 150mm of new road base material to improve the pavements strength.

This work is a large roads maintenance activity and will take approximately 4 weeks to complete (weather permitting).

A single lane traffic closure will allow traffic to travel through the worksite. Signage will be in place to notify road users, and updates available on northernrivers.myroadinfo

We thank the community for their patience as we complete these works.