The Lismore City Hall to the River Pedestrian Spine is one of four projects funded through the “Revitalisation of the Lismore CBD” project funded by the NSW Government.
The project is the construction of a 2.5m wide concrete footpath connecting Lismore City Hall to the existing path at Riverside Park, through the centre of Heritage Park. The path will provide improved connectivity and accessibility for pedestrians travelling from Lismore City Hall through to the Wilsons River and vice versa, whilst also enhancing user experience for visitors of Heritage Park.
The works include a concrete footpath from Molesworth Street to Victoria Street with a raised deck surrounding the fig tree in the centre of the park. It will also include lighting. Access to the Visitor Information Centre and toilets from Heritage Park will also be improved.
See photos for the concept plans.
This page has been archived, please visit the Your Say home page or Lismore City Council website for the most up to date information.
The Lismore City Hall to the River Pedestrian Spine is one of four projects funded through the “Revitalisation of the Lismore CBD” project funded by the NSW Government.
The project is the construction of a 2.5m wide concrete footpath connecting Lismore City Hall to the existing path at Riverside Park, through the centre of Heritage Park. The path will provide improved connectivity and accessibility for pedestrians travelling from Lismore City Hall through to the Wilsons River and vice versa, whilst also enhancing user experience for visitors of Heritage Park.
The works include a concrete footpath from Molesworth Street to Victoria Street with a raised deck surrounding the fig tree in the centre of the park. It will also include lighting. Access to the Visitor Information Centre and toilets from Heritage Park will also be improved.
Share April 2023 Update on FacebookShare April 2023 Update on X (formerly Twitter)Share April 2023 Update on LinkedinEmail April 2023 Update link
The deck under the fig tree at the centre of Heritage Park is now complete and open as well as the majority of concrete footpaths through the park.
The final pathway works are scheduled for completion in late April with works continuing through the school holidays, but will have only a minor impact on the use of the park - the access from Victoria street (near the waterplay) will be closed. The main access from the Molesworth Street carpark will be open.
The new paths will provide much needed accessibility and connection through the park, from Molesworth Street through to Riverside Park, as well as lighting and seating.
The miniature railway and water play area will be operating as normal, including daily through the school holidays.
The competed deck surrounding the fig tree
New seating through the park
New footpaths throughout the park
The deck under the fig tree at the centre of Heritage Park is now complete and open as well as the majority of concrete footpaths through the park.
The final pathway works are scheduled for completion in late April with works continuing through the school holidays, but will have only a minor impact on the use of the park - the access from Victoria street (near the waterplay) will be closed. The main access from the Molesworth Street carpark will be open.
The new paths will provide much needed accessibility and connection through the park, from Molesworth Street through to Riverside Park, as well as lighting and seating.
The miniature railway and water play area will be operating as normal, including daily through the school holidays.
Share February 2023 Update on FacebookShare February 2023 Update on X (formerly Twitter)Share February 2023 Update on LinkedinEmail February 2023 Update link
Works on the deck in Heritage Park are nearing completion. This includes a section of the main walkway in the centre of the park, as well as a deck and seating around the fig tree.
Concreting and lighting works throughout the park will commence from February and be completed in sections to enable the park to remain open.
The Heritage Park Railway will continue to operate as normal during works (Thursdays, Saturdays and Sundays).
The project is due for completion in April 2023 subject to weather.
The deck beginning to take shape around the fig tree
Works around the fig tree in heritage park
Works on the deck in Heritage Park are nearing completion. This includes a section of the main walkway in the centre of the park, as well as a deck and seating around the fig tree.
Concreting and lighting works throughout the park will commence from February and be completed in sections to enable the park to remain open.
The Heritage Park Railway will continue to operate as normal during works (Thursdays, Saturdays and Sundays).
The project is due for completion in April 2023 subject to weather.
The deck beginning to take shape around the fig tree
Share November Update on FacebookShare November Update on X (formerly Twitter)Share November Update on LinkedinEmail November Update link
Works on the deck in the park are commencing this week. This area will be fenced off and the rest of the park will still be operational. Works on the deck will be underway between now and Christmas.
Works on the rest of the pathway will stop over Christmas but will commence again from mid-January.
Works on the deck in the park are commencing this week. This area will be fenced off and the rest of the park will still be operational. Works on the deck will be underway between now and Christmas.
Works on the rest of the pathway will stop over Christmas but will commence again from mid-January.
Share September 2022 Update on FacebookShare September 2022 Update on X (formerly Twitter)Share September 2022 Update on LinkedinEmail September 2022 Update link
Share August Update on FacebookShare August Update on X (formerly Twitter)Share August Update on LinkedinEmail August Update link
Council is pleased to advise the community that works on Heritage Park will commence on Monday 24h October (weather permitting).
During the works Heritage Park will experience partial closures and some disruptions to access. The works include the construction of a 2.5m wide footpath through Heritage Park to improve connectivity and accessibility for pedestrians travelling between City Hall and Wilsons River and park users. It also includes lighting and a central deck.
Council is pleased to advise the community that works on Heritage Park will commence on Monday 24h October (weather permitting).
During the works Heritage Park will experience partial closures and some disruptions to access. The works include the construction of a 2.5m wide footpath through Heritage Park to improve connectivity and accessibility for pedestrians travelling between City Hall and Wilsons River and park users. It also includes lighting and a central deck.
Share Commencement of Works - March 2022 on FacebookShare Commencement of Works - March 2022 on X (formerly Twitter)Share Commencement of Works - March 2022 on LinkedinEmail Commencement of Works - March 2022 link
Works on the Pedestrian Spine pathway (through Heritage Park) are scheduled to commence in the week beginning 7th March 2022.
The park will remain open during the works, however due to concrete works at the main entry, access will only be via the Victoria Street entry. Works are expected to take between 6-8 weeks.
Works on the Pedestrian Spine pathway (through Heritage Park) are scheduled to commence in the week beginning 7th March 2022.
The park will remain open during the works, however due to concrete works at the main entry, access will only be via the Victoria Street entry. Works are expected to take between 6-8 weeks.