Lismore Employment Lands August Update

The great weather has continued over the past month which has allowed for works on Oliver Avenue to progress.

The key works occurring in the coming month include continuing of the following:

  • Earthworks in the main alignment on the Oliver Ave Road extension
  • The construction of the Hepburn Park new Carpark
  • The construction of the new roundabout at Oliver Avenue and Holland Street
  • Fill for the new industrial lots adjacent to new Oliver Avenue connection
  • Stage two of the noise abatement works
  • Installation of new NBN conduits
  • Bridge construction for the new bridge over Tucki Tucki Creek
  • Finalisation of footpath construction on the northern side of Oliver Avenue.

Noise abatement on identified houses has also progressed with stage one houses now complete.

Council will continue to keep the community up to date with changes to traffic via our Your Say website and Facebook page.