Lismore Employment Lands May 2023 Update

Works have progressed well over the past few months with many elements now completed:

  • new Hepburn Park public Carpark - 100% complete
  • kerb works at the North end of Oliver Avenue - 100% complete
  • Oliver Avenue/Holland Street round-a-bout - 100% complete
  • modifications/upgrades to the Bruxner Highway/Holland Street round-a-bout - 30% complete
  • Oliver Avenue road extension - 90% complete

Council will continue to keep the community up to date with changes to traffic via our Your Say website and Facebook page with the project expected to be completed in June 2023.

Oliver Avenue/Holland Street round-a-boutHepburn Park carpark Hepburn Park carpark Oliver Avenue extensionRetaining Walls 100% Complete - koala fence still to be completed

Share Lismore Employment Lands May 2023 Update on Facebook Share Lismore Employment Lands May 2023 Update on Twitter Share Lismore Employment Lands May 2023 Update on Linkedin Email Lismore Employment Lands May 2023 Update link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>