Lismore Employment Lands May 2023 Update
Works have progressed well over the past few months with many elements now completed:
- new Hepburn Park public Carpark - 100% complete
- kerb works at the North end of Oliver Avenue - 100% complete
- Oliver Avenue/Holland Street round-a-bout - 100% complete
- modifications/upgrades to the Bruxner Highway/Holland Street round-a-bout - 30% complete
- Oliver Avenue road extension - 90% complete
Council will continue to keep the community up to date with changes to traffic via our Your Say website and Facebook page with the project expected to be completed in June 2023.
Oliver Avenue/Holland Street round-a-bout
Hepburn Park carpark
Hepburn Park carpark
Oliver Avenue extension
Retaining Walls 100% Complete - koala fence still to be completed