Johnston Road - 25 August 2022 Update
Johnston Road will remain closed over the weekend. Installation of the inclinometers (used to measure the movement of the landslip) could not be completed as scheduled. Therefore, the truck mounted rig will need to sit in position over the weekend, which significantly impacts road usage.
On-road drilling remains on track to be completed by Friday 26 August. Stop/go traffic control will be onsite for Monday to allow motorist through Johnston Road until the geotechnical works are completed.
We appreciate your patience.