    We are continuing to update the community on the extensive repair work Council is undertaking across our road network and any updates on our planned projects.


    Among many other roads, our crews are working on two projects at the Clyde Campbell Carpark.


    Construction of the Clyde Campbell Solar Carpark and EV Charging Station officially commenced in early July. Electrical work for the 75kW DC fast Electric Vehicle (EV) charger, capable of charging two cars at one, has been installed.


    Today crews resurfaced the area of the Solar Carpark with asphalt and prepared the landscaping sections.


    The next phase of this project will be constructing a 100kW solar array, which doubles as a shade structure – Engineered to withstand floods.


    At the same time today, the carpark was repaired in sections from damage due to the 28 February natural disaster. Crews prepared the surface of the carpark and resurfaced it with asphalt.


    We will keep our community up to date on the solar project and repair work of the carpark.


    For the latest updates on our road works, please visit the dedicated Maintaining our Roads update page on Your Say website at https://yoursay.lismore.nsw.gov.au/maintaining-our-roads..., where you can ask questions about this road closure or any other current road works occurring in the Q+A section of the page.