  • Cosy Camp Road - Culvert Works (Oct 2024)

    Share Cosy Camp Road - Culvert Works (Oct 2024) on Facebook Share Cosy Camp Road - Culvert Works (Oct 2024) on Twitter Share Cosy Camp Road - Culvert Works (Oct 2024) on Linkedin Email Cosy Camp Road - Culvert Works (Oct 2024) link

    Restoration works are scheduled for Cosy Camp Road, Corndale, for approximately 3-weeks from Monday 11 November 24 to Monday 2 December 24 (between 7am and 5pm) subject to weather conditions.

    The road will remain open to traffic via single lane, with works to be completed under stop/go signalling from traffic controllers. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Motorists are asked to please adhere to all road signs, speed limits and directions from the traffic controller and ensure extra care is taken around workers and moving machinery.

    What are the works?

    Cosy Camp Road suffered significant damage in the 2024 natural disaster. Funding is now secured for remediation and reconstruction works including of a damaged culvert. Works will include minor earthworks and stripping of topsoil, rebuilding road verge, headwall replacement, clearing and regrading table drain, guardrail installation and road signage installation.

    If you'd like to join our mailing list receive specific updates on this project, please email frp@lismore.nsw.gov.au and include in the title ‘Cosy Camp Road – November 2024 Update.’

    The Flood Restoration Portfolio team thanks you for your patience and cooperation as we complete these essential road restoration works.

  • Flood Restoration - Roads & Bridges Update (Sept 2023)

    Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Sept 2023) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Bungabbee Road

    Recently the Bungabbee Road bridge approaches works were completed to repair damages from the 2022 natural disaster. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Dudgeon Road Bridge

    Works were scheduled and completed last month to repair the flood damaged Bungabbee Road bridge approaches. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Major Flood Recovery Works Map

    Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater along with Flood Restoration Building projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.


    CURRENT WORKS

    Nimbin Road

    Works are continuing for the Nimbin Road landslips. Site Km1, located 1 Km from Nimbin has all the concrete works and piling complete with the installation of block wall in progress. This site is on schedule for the road to be fully open before Christmas. Site Km4, located 4 Km’s from Nimbin is currently undergoing construction of gabion walls, these are used for scour protection, which prevents soil from being washed away and helps strengthen the road. The site also has piling in progress with approximately 30% completed.


    Keerrong Road

    Works have commenced on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works are scheduled for approximately 3 weeks, subject to weather, contractor, and material availability. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com. Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.


    Geotechnical Investigations

    The Lismore City Council (LCC), Flood Recovery – Roads and Bridges team recently secured interim funding for additional geotechnical investigations and survey to commence on several flood affected roads. Initial investigations took place in 2022 to inform the designers about the geological conditions and failure mechanism. This information was used to apply for funding to repair. Additional investigations are now required to inform the final design.

    Geotechnical drilling is a type of drilling that is performed as part of the construction process to assist with better understanding a site. Investigations involve collecting rock and soil samples to obtain data regarding surface and subsurface examination. These samples provide valuable insights into the physical properties of the site, enabling engineers to design and construct remediation works to deliver roads that are safer and more durable.

    Roads approved for investigations include Bice Road, Bishops Creek Road, Black Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Cross Road, Gungas Road, Johnston Road, Koonorigan Road, Lillian Rock, Martin Road, Mountain Top Road, Oakey Creek Road, Orion Street, Rock Valley Road, Skyline Road, Stanger Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Upper Tuntable Falls Road, Wallace Road, Whian Whian Road, Yeager Road and Zouch Road.


    Cawongla Road

    Significant changes to the traffic control measures at the Cawongla Road Landslide site, near Martin Road, were recently implemented. It was identified that the site was deemed unsafe due to technical issues with the traffic lights, including repeated battery charge depletion, and concerns about safety. Therefore, the traffic lights previously regulating traffic flow have been replaced with a “Give Way” sign and a “Stop” sign. This decision was prompted by multiple incidents of road users running the red lights, posing a serious safety hazard. The new signage system aims to simplify traffic management while mitigating potential hazards. All signage has been installed as per the amended traffic guidance scheme, and a comprehensive risk assessment was conducted before implementing these changes to ensure the safety of all individuals travelling through the site.

  • Geotechnical Investigations & Survey (Aug 2023)

    Share Geotechnical Investigations & Survey (Aug 2023) on Facebook Share Geotechnical Investigations & Survey (Aug 2023) on Twitter Share Geotechnical Investigations & Survey (Aug 2023) on Linkedin Email Geotechnical Investigations & Survey (Aug 2023) link

    Interim funding has been approved for geotechnical investigations and survey to commence on the roads identified below. This process will be taking place over the next 4 months.


    Commencing - 4th of September
    Bice Road, Black Road, Cawongla Road, Gungas Road, Koonorigan Road, Martin Road, Mountain Top Road, Orion Street and Yeager Road.


    Commencing - 18th of September

    Bishops Creek Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Lillian Rock, Mountain Top Road, Oakey Creek Road, Rock Valley Road, Skyline Road, Stanger Road, Tuntable Creek Road, Upper Tuntable Falls Road and Zouch Road.


    Commencing - 16th of October

    Blue Knob Road, Cross Road, Johnston Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Wallace Road and Whian Whian Road


    There will be some implications on traffic during this process, please adhere to all road signs and directions from any traffic controller. We apologise for any inconvenience. Further details will be provided once available.


    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Geotechnical Investigations & Survey.’