Flood Restoration - Roads & Bridges Update (Jan 2024)
Share Flood Restoration - Roads & Bridges Update (Jan 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Jan 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Jan 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Jan 2024) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Geotechnical Investigations
During the month our contractors closed single lanes for works on Orion Street, Skyline Road South, Tuntable Creek Road, and Zouch Road to perform geotechnical investigations. This involved using a drilling rig to understand subsurface conditions. We would like to thank residents for your patience and resilience during this time. All landslip geotechnical investigations have now been completed with the bridge investigations underway and expected to also be completed by the middle of February.
Eltham Road
Recently, funding was secured to install guardrail on Eltham Road. These works were completed late January with a road closure in place around the site. There was a road closure between Houghlahans and Humpty Back roads and we thank the community for their patience during the road closure.Quilty Road
Works were recently completed on Quilty Road to repair pavement damage and replace a culvert to return the road to pre-existing conditions. Thank you to the residents for their patience and support during the works.
Tuntable Creek Road
As the safety threshold had been exceeded, a road closure was triggered for Tuntable Creek Road on Wednesday 17 January 2024 at the landslip site, between Rose Road and Beardow Road. The shut down was to ensure the safety of motorists and to allow for further monitoring. Geotechnical experts were on site the next day to inspect the site and determined it could be reopened. The road reopened Thursday morning 18 January 2024. The new signs installed in October 2023 assisted to reduce detour times allowing Council to notify residents of the closure before reaching the closed site.
CURRENT WORKSNimbin Road
Works are continuing for Site 4km on Nimbin Road, after the successful completion and opening of Site 1Km. Recently work crews completed implementation and maintenance of the erosion control following the heavy rainfall. Placement of approximately 70% of the GWS (No Fines Concrete Blocks) on top of the pile cap and approximately 60m of drainage layer and selected fill behind the retaining wall were also recently completed.
Guardrails Project
During the past month our guardrails project has been underway, replacing or installing new guardrails. This is multisite works to repair traffic barriers at road sections damaged during the 2022 natural disaster. Generally, the sites are at road sections over creek crossings. Each work site will require traffic control and the repair will generally be completed within 2 days. Recently, the work crew worked on Eltham and Boatharbour Road. Other road closures will be updated as scheduled work on Live Traffic.
Terania Creek – Bridge Updates
The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings completed for bridge 3. Commencement on bridge 2 is scheduled for early February.
FUTURE WORKSDorroughby Road
The road closure for Dorroughby Road was unfortunately delayed until 12 February with expected competition approximately 26 February, subject to change pending weather conditions. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing conditions. Road closure will be required around the works zone with the section located approximately 500 meters from the Dorroughby Road/Corndale Road intersection, between 791 Corndale Road and 65 Dorroughby Road. Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated. Please adhere to all road closed signs and directions from any traffic controllers.
Rogerson Road
A culvert replacement is planned for late February 2024. These works will require a road closure for up to 10 weeks subject to weather and resources availability. The existing culvert was damaged in the February 2022 natural disaster and has funding approved for a replacement structure with concrete pipes.
Newton Drive
A number of minor up slope landslips and a single pipe culvert are scheduled to be repaired during February. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Rosebank Road
Rosebank road slip will have restoration works completed during February. The works involve reinstating the property access track and restoring the batter and table drain along the road edge. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Johnston Road
Minor works on a damaged drainage culvert along Johnston Road will be completed in February. This will involve reinstating a rock blanket that was washed away in the February 22 Flood Event. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Leycester Road
Council wishes to advise funding has now been secured to reinstate the road to a suitable standard to ensure the community are able to travel safely along this road. The works are schedule to occur July 2024, notwithstanding another disaster event and subject to weather conditions, resources, and contractor availability. During works traffic will be impacted as the works will be carried out under Traffic Control stop/go arrangement and a reduced speed limit. At times traffic users may experience long delays to allow construction of the new pavement. Access to property driveways may be impacted or restricted at times however will ensure property owners are notified prior to this occurring. Motorists will be notified of the upcoming roadworks with VMS boards and updated through www.livetraffic.com closer to construction commencement. Emergency services vehicles will be accommodated if required. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.
Eureka Road, Graham Road & Haywood Lane
The design plans have changed for Eureka Road, Graham Road, and Haywood Lane. These sites were originally scheduled for culvert replacement; however, funding has been successfully acquired to upgrade these locations from box culverts to bridges. Currently, design for the project works is in final stages with the bridges due to be delivered to Council late February. The works are to be scheduled after delivery, this is subject to change pending weather conditions, resources, and contractor availability. We apologise in advance for any disruptions you may experience while we carry out this essential work. These works will involve removing the existing infrastructure at each site and preparing the area for bridge construction. To minimise impact to residents and traffic flow during the construction work a temporary track will be established as a side road. The works will take approximately 6 weeks at each site. -
Eltham Road - Road Closure (Jan 2024)
Share Eltham Road - Road Closure (Jan 2024) on Facebook Share Eltham Road - Road Closure (Jan 2024) on Twitter Share Eltham Road - Road Closure (Jan 2024) on Linkedin Email Eltham Road - Road Closure (Jan 2024) linkPlease note: Due to the current weather situation, these works have extended until the 31st of January at 5pm.
Council wishes to advise schedule works on Eltham Road require a temporary road change. The works will involve closing of the road for approximately 2 days, from 7am to 5pm, on January 29 and 30, subject to change pending weather conditions. The road closure will be required around the works zone with the section located in the figure below.
Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated. Please adhere to all road closed signs and directions from any traffic controllers.
What are the works?
Following the February 2022 natural disaster, Eltham Road suffered extensive damage. Funding has now been secured to install guardrail at the site identified below.
Live Traffic Information
https://www.livetraffic.com/incident-details/181754
Further Information
We apologise in advance for any disruptions you may experience while we carry out this essential work. Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Eltham Road – Jan 2024 Update.’ -
Flood Recovery Heavy Patching Program
Share Flood Recovery Heavy Patching Program on Facebook Share Flood Recovery Heavy Patching Program on Twitter Share Flood Recovery Heavy Patching Program on Linkedin Email Flood Recovery Heavy Patching Program linkFlood Recovery Heavy Patching Program –
Restoration of road surface, possible change in road level.
Segments of the following have been identified for heavy patching works to repair flood damage to road surface.
Precinct 1
Graham Road
Gundarimba Road
River Bank Road
Rous Road
Skyline Road
Tregeagle Road
Tuckurimba Road
Tucki Road
Wybelena Road
Precinct 2
Bagotville Road
Broadwater Road
Kilgin Road
Mathieson Lane
Precinct 3
Tatham Road
Precinct 4
Nimoola Road
Pelican Creek Road
Precinct 6
Back Creek Road
Precinct 7
Axford Road
Martin Road
McGuinness Road
Rock Valley Road
Precinct 8
Boggumbil Road
Davis Road
Jacobson Road
Jiggi Road
Potessu Road
Rosehill Road
Precinct 9
Anderson Road
Basil Road
Cecil Street
Crofton Road
Gungas Road
Lillian Rock Road
Moffitt Road
Sibley Street
Symonds Road
Thorburn Street
Precinct 10
Booerie Creek Road
Boyle Road
Keerrong Road
Precinct 11
Koonorigan Road
Pinchin Road
Terania Creek Road
The Channon Road
Tuntable Creek Road
Precinct 12
Dorroughby Road
Duncan Road
James Street (Dunoon)
Middleton Way
Nightcap Range Road
Rocky Creek Dam Road
Precinct 13
Corndale Road
Hunters Hill Road
Grace Road
James Gibson Road
Precinct 14
Boatharbour Road
Eltham Road
Humpty Back Road
Regional Roads
Blue Knob Road
Coraki Road
Dunoon Road
Nimbin Road
Wyrallah Road
Bridge Street (Wyrallah)
Kyogle Road
These works are subject to change to due weather conditions, availability of contractors and funding. Updates will be posted on this article.
Shall you wish to be kept up to date directly, you can register your details via the Your Say ‘Submissions’ tab HERE. Alternately, please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details. Please reference ‘Flood Recovery Heavy Patching Program’.
How will the works affect traffic?
Roads will be open to residential access only during the time of works. Traffic controls will be in place, which will cause minor delays and disruptions. Please note roadside signage, updates on myroadinfo and updates in the online Your Say article for communication about temporary disruptions to your property access during this period.
What do the works involve?
These roads need to be fixed to improve the structural integrity and driving conditions for road users. Works include cleaning drains and culverts, cutting off high road shoulders, digging out and replacing soft spots with rock. The gravel overlay is placed where required, before stabilising with the addition of slag lime. This is then compacted, trimmed, and sealed. Followed by line marking edge line.
The road surface may receive a final wearing seal several months after the initial bitumen seal has cured.
This pavement overlay may potentially change road levels between 0mm to +150mm and resurfacing of the existing road width due to additional layers of new road base material.
All driveways that intersect the road will match any changes to the road profile. If there are any changes, you will be contacted should your driveway/access need modification. We will also do maintenance to roadside drainage as needed.
What happens now?
If you wish to make comment on the works, we ask that you do this by 4pm Monday, 15th August 2022 referring to ‘Flood Recovery Heavy Patching Program’. Feedback can be received via any of the following:
- Via the ‘Submissions’ tab of this article HERE.
- Email to council@lismore.nsw.gov.au
- Call to Council (02) 6625 0500
- In writing to Lismore City Council, PO Box 23A, Lismore 2480