Category Henson Bridge Show all
-
Current Road Project Updates 5 August 2022
Share Current Road Project Updates 5 August 2022 on Facebook Share Current Road Project Updates 5 August 2022 on Twitter Share Current Road Project Updates 5 August 2022 on Linkedin Email Current Road Project Updates 5 August 2022 linkGravel Roads (Flood Repair Works) – approximately 50% of LCC Gravel Roads have been repaired now since the Feb/March 2022 events.
Caniaba Road – Drainage and shoulder widening works progressing well. Project is currently running to plan with minimal delays.
Richmond Hill Road – the landslip has been repaired and pavement rehabilitation works are progressing.
Nimbin Road near Goolmangar School – urgent maintenance works were carried out last week, the damaged sealed pavement was returned to gravel. This section of road will be overlaid with new gravel and stabilised this month
Keerrong Road Bridge – the new concrete bridge is now complete and earthworks progressing on the approaches
Henson Bridge – Piling is now complete, works progressing well on preparing the bridge abutments (form/reo/poor)
Keerong Road – Landslip and drainage remediation works are commencing, leading to a road closure from August 10th - adjacent to 1265 Kerrong Road. Motorists are advised via roadside signage. Pavement strengthening works are also progressing on approximately a 1km section. Further pavement works are scheduled.
Bruxner Highway at Northcott Road – pavement rehabilitation works are progressing which have included stabilisation of the existing material and overlay with new gravel.
Gungas Road – shoulder widening and pavement works are progressing.
Cowlong Road – pavement strengthening works are progressing south of McKenzie Road.
Jiggi Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.
Pinchin Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.
One section of Jiggi Road, preconstruction on 04/08/22
Wyrallah Road - Geotechnical drilling to determine scope of works.
Drilling at Wyrallah Road 27/07/22
Dunoon Road (near the Macadamia Factory) - Temporary patching on a section of road adjacent Macadamia factory on Dunoon Road. This section of road is due for full pavement reconstruction in October this year.
a section of Dunoon Road before temporary patching 02/08/22