Category Paterson Road   Show all

  • Flood Restoration - Roads & Bridges Update (May 2024)

    Share Flood Restoration - Roads & Bridges Update (May 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (May 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (May 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (May 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.

    Environmental Rescue at Rogerson Road
    What happens when a handful of bats put a major flood restoration project on hold? When it came time to replace three large steel storm water drainage pipes with reinforced concrete pipes ones on Rogerson Road, McKees Hill, project coordinators discovered at least half a dozen micro bats had made a hole in one pipe, their home.

    Myotis Macropus: One of Australia’s most fascinating species because they’re the only bats in Australia to capture fish for food. They have large feet which they use to trawl for food near the water’s surface. Work crews had to play a waiting game until two juvenile bats were old enough to fly. But then the challenge was - how to catch the youngsters and offer them an alternative roosting venue. Eventually patience and thermal imaging cameras confirmed the two young bats took to the skies for the first time, just after sunset on 1st May.

    That night the hole was sealed, and a timber bat box installed as an alternative roost. Four bats settled into their new home but the remaining two had to be caught and housed in the box. Once the culvert work is complete it’s hoped all the bats, and their box will be relocated into the new concrete pipes.

    COMPLETED WORKS
    Crofton Road
    Road pavement restoration works on Crofton Road are on track to be completed by the end of May. Until then the road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.


    Gungas Road
    Works commenced at the end of April on Gungas Road to desilt the creek crossing at Black Sheep. This involved the removal of debris to allow the creek to flow across the full width and reduce the chance of overtopping the crossing in the future.


    Nimbin Road
    Wet weather continued to cause delays to the completion of works on Nimbin Road at the site near Shipway Road. By mid-May the road was open to two-way traffic with the final clean up completed by 24 May 2024. During the past month, works were completed for the construction drainage along the retaining wall and placement of road base layers along the full width of the road. The road has now been sealed with asphalt and guardrails installed.

    Oakey Creek Road
    In May, temporary works were completed at a landslip site along Oakey Creek Road that was identified as a safety hazard.


    CURRENT WORKS
    Multiple Road Works
    The works involve grading over 120km on 53 unsealed gravel roads which have been significantly damaged as a result of declared natural disaster events in December 2023 and April 2024. Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first. Council is deploying six separate works crews and efforts have been made to cluster the works geographically to optimise efficiency and resource allocation. Motorists will be notified of road changes via roadside signage. We apologise in advance for any disruptions you may experience while we carry out this essential work. For further information visit https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/upcoming-works-grading-for-multiple-unsealed-gravel-roads

    Blue Knob Road
    Works began in late May to rectify the first of two landslip sites on Blue Knob Road. These works will occur for approximately 12 months which will include an additional two sites along Blue Knob Road. The road will remain open under stop go traffic control to have minimal impact on residents.

    Eureka Road, Graham Road & Haywood Lane
    Works have commenced to replace culverts with bridges and all side tracks are in place with existing culverts removed. Future piling work is scheduled to commence in mid-June.

    Newton Drive
    Works on several minor upslope landslips and a single pipe culvert were heavily impacted this month due to weather conditions. Crews are hoping for favourable weather in June to progress the pending works which will to be completed under traffic control and will have minimal impact on the residents in this area.

    Rogerson Road
    Through successful collaboration with environmental professionals the juvenile micro bats were temporary relocated during April. This will allow works to commence replacing the steel drainage pipes with cement ones. Thank you to the community for your understanding and patience while the works continue.

    Stony Chute Road
    Following the February 2022 natural disaster, Stony Chute Road suffered extensive damage. With funding secured restoration works are now underway. The works will continue for approximately three to four weeks from 15May 2024, subject to weather conditions.


    Terania Creek Road – Bridge Updates
    Concrete approaches, scour protection, and guard rail installation are complete for Bridge 3. Final work is due to be complete late May. For Bridges 1 and 2 side track installation is nearing completion with work to recommence in June.

    Upper Tuntable Falls Road
    Landslip remediation works will be complete at the Upper Tuntable Falls slip site this week. Some minor grading and drainage works will continue into June on Upper Tuntable Falls Road, with completion expected mid June.


    FUTURE WORKS
    Gwynne Road
    The design for 1.2 kilometres of new pavement is nearing completion and once finalised the work will be put out to tender with works predicted to begin in approximately 6 weeks.

  • Multiple Unsealed Gravel Roads - Grading Works (May 2024)

    Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Facebook Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Twitter Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Linkedin Email Multiple Unsealed Gravel Roads - Grading Works (May 2024) link

    Council wishes to advise of upcoming works on the listed roads below. The works involve grading over 120km of unsealed gravel roads which have been significantly damaged as a result of declared natural disaster events AGRN1101 (December 2023) and AGRN1119 (April 2024).

    What are the works?

    Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first. Council is deploying six separate works crews and efforts have been made to cluster the works geographically to optimise efficiency and resource allocation.

    The works will begin to commence this week, though will not all begin simultaneously due to contractor availability. These works will take approximately three months to complete, weather permitting.

    We understand the importance of these roads to our daily commutes, emergency services, and local economy, and we are committed to restoring them to their optimal condition quickly. Motorists will be notified of road changes via roadside signage. We apologise in advance for any disruptions you may experience while we carry out this essential work.

    Crew 1

    Crew 2

    Priority

    Road Name

    Priority

    Road Name

    1

    Davis Road

    1

    Gungas Road

    2

    Boggumbil Road

    2

    Shipway Road

    3

    Stead Road

    3

    Bishops Creek Road

    4

    Unnamed Lane West off Mountain Top (Georgica)

    4

    Parmenter Road

    5

    Clark Road

    5

    Keerrong Road

    6

    Unnamed Lane West off Clark

    6

    Quilty Road

    7

    Warby Road

    7

    Mulvena Road

    8

    Bertoli Road

    9

    Lodge Road

    10

    Stanger Road

    11

    Blade Road (West)

    12

    Cullen Road

    13

    Suffolk Road

    14

    Blade Road

    Crew 3

    Crew 4

    Priority

    Road Name

    Priority

    Road Name

    1

    Terania Creek Road

    1

    Upper Coopers Creek Road

    2

    Lawler Road

    2

    Minyon Falls Road

    3

    Rankin Road

    3

    Fox Road

    4

    Greengate Road

    4

    Nightcap Range Road

    5

    Unara Road

    5

    Lychee Drive

    6

    Walmsley Road

    6

    Armstrong Road

    7

    Virtue Road

    8

    Behan Access

    9

    Lavis Road

    10

    McKinnon Road

    Crew 5

    Crew 6

    Priority

    Road Name

    Priority

    Road Name

    1

    McInnes Road

    1

    Wallace Road

    2

    Monaltrie Road

    2

    Rose Road

    3

    Bice Road

    3

    Pinchin Road

    4

    Yeager Road

    4

    Izzard Road

    5

    Eastment Lane

    5

    Paterson Road

    6

    McMahon Road

    6

    Arkinstall Road

    7

    Muldoon Road

    8

    Norton Road

    9

    Lavis Road

    10

    McKinnon Road

    We are in the process of assessing various additional roads to be included in the scope of these recovery works. Our goal is to ensure comprehensive restoration and long-term resilience of our unsealed gravel road network. The funding for this engagement is granted by Transport for NSW (TfNSW) under the Disaster Recovery Funding Arrangements (DRFA) guidelines to reconstruct eligible assets to pre-disaster function.


    Works Criteria

    The works have been carefully distributed and prioritised based on the following criteria:

    • Scale of Damage: Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first.
    • Contractor Availability: We have coordinated with available contractors to expedite the commencement of these essential repairs.
    • Group Locality: Efforts have been made to cluster the works geographically to optimise efficiency and resource allocation.


    Further Information
    This notification will be posted on our Your Say dedicated Flood Recovery – Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges.

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Unsealed Gravel Roads – May 2024 Update.’