Share Tuntable Creek Road - Drainage & Pavement Works (Sept 2024) on Facebook Share Tuntable Creek Road - Drainage & Pavement Works (Sept 2024) on Twitter Share Tuntable Creek Road - Drainage & Pavement Works (Sept 2024) on Linkedin Email Tuntable Creek Road - Drainage & Pavement Works (Sept 2024) linkCouncil wishes to advise of upcoming works on Tuntable Creek Road. The works will occur for approximately 5 weeks, from 30 September to 4 November 2024, subject to weather conditions.
The road will remain open with works completed under stop/go traffic control to have minimal impact on residents, delays are expected. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.
We apologise in advance for any disruptions you may experience while we carry out this essential work.
What are the works?
Following the February 2022 natural disaster, Tuntable Creek Road suffered extensive damage. Funding has been secured for minor clearing, drainage works, storm water replacement and pavement rehabilitation approximately 200m long identified on the map below.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Tuntable Creek Road – Sept 2024 Update.’ -
Tuntable Creek Road - Reopened (9am 15 August 2024)
Share Tuntable Creek Road - Reopened (9am 15 August 2024) on Facebook Share Tuntable Creek Road - Reopened (9am 15 August 2024) on Twitter Share Tuntable Creek Road - Reopened (9am 15 August 2024) on Linkedin Email Tuntable Creek Road - Reopened (9am 15 August 2024) linkTuntable Creek Road – Road Open (15 August 2024)
Tuntable Creek Road has reopened at 9am today, 15 August, after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.
As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.
In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.
Please contact frp@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.
To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form. -
Tuntable Creek Road - Road Closure (12 August 2024)
Share Tuntable Creek Road - Road Closure (12 August 2024) on Facebook Share Tuntable Creek Road - Road Closure (12 August 2024) on Twitter Share Tuntable Creek Road - Road Closure (12 August 2024) on Linkedin Email Tuntable Creek Road - Road Closure (12 August 2024) linkTuntable Creek Road - Road Closure (12 August 2024)
Tuntable Creek Road between Rose Road and Beardow Road will be closed at 8am today until further notice due to significant rainfall.
We apologise for the short notice and thank the community for their understanding.
Live Traffic Information
https://www.livetraffic.com/incident-details/174116 -
Tuntable Creek Road - Reopened (3 July 2024)
Share Tuntable Creek Road - Reopened (3 July 2024) on Facebook Share Tuntable Creek Road - Reopened (3 July 2024) on Twitter Share Tuntable Creek Road - Reopened (3 July 2024) on Linkedin Email Tuntable Creek Road - Reopened (3 July 2024) linkTuntable Creek Road – Road Open (3 July 2024)
Tuntable Creek Road has reopened at 1:30pm today, 3 July, after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.
As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.
In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.
Please contact frp@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.
To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form. -
Tuntable Creek Road - Road Closure (2 July 2024)
Share Tuntable Creek Road - Road Closure (2 July 2024) on Facebook Share Tuntable Creek Road - Road Closure (2 July 2024) on Twitter Share Tuntable Creek Road - Road Closure (2 July 2024) on Linkedin Email Tuntable Creek Road - Road Closure (2 July 2024) linkTuntable Creek Road - Road Closure (2 July 2024)
Tuntable Creek Road between Rose Road and Beardow Road will be closed at 10 am today until further notice due to significant rainfall.
We apologise for the short notice and thank the community for their understanding.
Live Traffic Information
https://www.livetraffic.com/incident-details/174116 -
Tuntable Creek Road - Reopened (23 April 2024)
Share Tuntable Creek Road - Reopened (23 April 2024) on Facebook Share Tuntable Creek Road - Reopened (23 April 2024) on Twitter Share Tuntable Creek Road - Reopened (23 April 2024) on Linkedin Email Tuntable Creek Road - Reopened (23 April 2024) linkTuntable Creek Road – Road Open (3:30pm, 23 April 2024)
Tuntable Creek Road has reopened after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.
As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.
In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.
Please contact frp@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.
To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form. -
Tuntable Creek Road - Road Closure (21 April 2024)
Share Tuntable Creek Road - Road Closure (21 April 2024) on Facebook Share Tuntable Creek Road - Road Closure (21 April 2024) on Twitter Share Tuntable Creek Road - Road Closure (21 April 2024) on Linkedin Email Tuntable Creek Road - Road Closure (21 April 2024) linkTuntable Creek Road - Road Closure (21 April 2024)
Tuntable Creek Road between Rose Road and Beardow Road will be closed at 3pm today until further notice due to significant rainfall.
We apologise for the short notice and thank the community for their understanding.
Live Traffic Information
https://www.livetraffic.com/incident-details/174116 -
Tuntable Creek Road - Reopened (5 April 2024)
Share Tuntable Creek Road - Reopened (5 April 2024) on Facebook Share Tuntable Creek Road - Reopened (5 April 2024) on Twitter Share Tuntable Creek Road - Reopened (5 April 2024) on Linkedin Email Tuntable Creek Road - Reopened (5 April 2024) linkTuntable Creek Road – Road Open (5 April 2024)
Tuntable Creek Road has reopened, 2pm 5 April 2024, after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.
As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.
In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.
Please contact frp@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.
To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form. -
Tuntable Creek Road - Road Closure (4 April 2024)
Share Tuntable Creek Road - Road Closure (4 April 2024) on Facebook Share Tuntable Creek Road - Road Closure (4 April 2024) on Twitter Share Tuntable Creek Road - Road Closure (4 April 2024) on Linkedin Email Tuntable Creek Road - Road Closure (4 April 2024) linkTuntable Creek Road - Road Closure (4 April 2024)
Tuntable Creek Road between Rose Road and Beardow Road will be closed at 11:00am today until further notice due to significant rainfall.
We apologise for the short notice and thank the community for their understanding.
Live Traffic Information
https://www.livetraffic.com/incident-details/174116 -
Flood Restoration - Roads & Bridges Update (Mar 2024)
Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Mar 2024) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Black Road
Temporary repair works were completed on Black Road to restore access to properties for residents. This involved importing some additional rock, stabilising the current structure with no fines concrete, and adding some additional surface material to ensure the crossing remains trafficable while the design for a new structure is under way.
Dorroughby Road
The Dorroughby Road landslip restoration project is now completed with motorists excitingly driving the stretch over road in mid-March. The works involved stabilising the landslip embankment, installing drainage, and constructing a new road pavement. We would like to thank the community for their patience during the construction and the positive feedback we have received from road users who are enjoying this new section of the road.
Industry Drive
During March work crews constructed a gabion wall to improve drainage prevent future erosion on Industry Drive. The works were completed under the watchful eye of nearby preschool children, who demonstrated great anticipation at the fence each day as they watched eagerly what the machinery would do next. A highlight for our crews as they witnessed the children’s smiling faces observing the works. Thank you to the local community for your support during these works.
Johnston Road
Works are now complete on a storm water outlet on Johnston Road. These works included reinstating the rock erosion protection and the concrete around the top of the precast headwall.
Road Maintenance Works - Gwynne Road, Stony Chute Road & Tuntable Falls Road
A busy month for our maintenance crews with staff inspecting and providing maintenance on many roads throughout the region. After listening to community concerns Gwynne Road, Stony Chute Road and Tuntable Falls Road were added as priority maintenance works. To improve road conditions, crews provided pothole repairs on Stony Chute Road and Tuntable Falls Road along with light grading and filling potholes for the sealed section of Gwynne Road.
CURRENT WORKS
Crofton Road
Road pavement restoration works have commenced on Crofton Road for the locations identified below. The works will occur for approximately two to three months, subject to weather conditions. The road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.
Newton Drive
Works have commenced on several minor upslope landslips and a single pipe culvert. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Nimbin Road
Works are progressing on Nimbin Road at the site near Shipway Road. During the past month, on the southbound lane, work crews have removed the asphalt and base material along with reshaping and installing drainage. The road pavement was also constructed, compacted, and rolled along the full width of the road. Following this, the steel barriers on top of the retaining wall were installed, allowing the traffic to shift back to the northbound lane. Next month, works are scheduled to construction drainage along the retaining wall and complete placement of the road base layers along the full width of the road. This will be followed by sealing and asphalting along the full width of the road, installing guardrails and construction of the gabion basket wall extension ready for the anticipated opening on the road in May.
Milgate Road
Works have commenced on Milgate Road involving road surface and drainage repairs.
Rogerson Road
The team are continuing to implement the appropriate protocols to ensure the safety of juvenile micro bats. Through successful collaboration with environmental professionals this protected species will be temporary relocated. This will allow the pups to complete their growth cycle during the breeding season and reduce their risk in maturing. We will provide further update when available. Thank you to the community for your patience and understanding.
Rosebank Road
Landslip restorations are underway at Rosebank Road. The works involve reinstating the property access track and restoring the batter and table drain along the road edge.
Terania Creek – Bridge Updates
The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings are completed for bridge 1. During early March, work crews will commence final concrete works and installation of lateral restrain brackets for bridge 3.
Tuntable Creek Road
During March, maintenance works were completed on Tuntable Creek Road from Young Road heading back down the hill approximately 500m. These works involved reshaping of table drains, slashing and minor landslip remediation.
Upper Tuntable Falls Road
Works are underway on two landslip sites on Upper Tuntable Falls Road located near the Tuntable Falls Primary School. During the past month, a site office was established and works commenced to reinstate the existing open drains. Temporary ramps were also constructed to allow trucks entry to the slip area. The works are expected to take 6-8 weeks weather permitting.
Zouch Road
Priority works have commenced for Zouch Road. This will involve with a light grade and repairs to the road surface.
FUTURE WORKS
Gwynne Road
Gwynne Road is currently out to design; the design will take approximately one month. After this, the project will go to tender with work will be starting on the road in approximately 8 weeks.
Magellan Street
New guardrails will be installed on Magellan Street in the location identified on the map below during April. The road will remain open with works completed under single lane traffic control to have minimal impact on road users.