Project Update - November 2023

Council in conjunction with contracting partner NTS Group, are continuing works on the Nimbin Pipeline Replacement Project. Expected completion is March 2024, subject to weather and unforeseen delays.

Works will continue to be conducted from 7am to 5pm, Monday to Friday. No water outages are expected, however any works that may result in a drop of water pressure will be completed outside of peak times.

Shall you wish to receive alerts for potential outages, please register below.

Nimbin Water Customer Contact Details

Project Update

Construction has commenced at the Sheathers Bridge end for the new 200mm diameter pipeline, extending to Nimbin weir along Gungas Road. Following all preliminary works being successfully completed, 140m of the pipeline has been replaced.

Due to the nature of works and required equipment, residents and motorists travelling on Gungas Road should anticipate traffic delays until the project completion.

The construction activities may lead to elevated noise levels and increased dust. We are aware that these changes could impact nearby residents. We sincerely apologize for any inconvenience this may cause and want to assure you that measures will be implemented to minimize these disturbances.

Will this project cause water restrictions?

The most recent water restrictions for Nimbin and current boiled water alerts for Nimbin Rural Line are the result of decreased water flow in Mulgum Creek. The restrictions were in place to manage water supply with forecasted dry weather. Further information on restrictions, will be shared via Council’s communication channels.

Where can I find further information?

Further information and updates will be available via Your Say, Nimbin Water Supply – Pipeline Replacement Project: https://yoursay.lismore.nsw.gov.au/nimbin-water-supply

Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500. Please reference ‘Nimbin Pipeline Replacement AF22/2514’ in your correspondence.

Council appreciates the patience and resilience of this community as we continue to finalise these works.

Share Project Update - November 2023 on Facebook Share Project Update - November 2023 on Twitter Share Project Update - November 2023 on Linkedin Email Project Update - November 2023 link

This project was completed May 2024