Project Update Thursday 6 October
The project to reinstate a permanent solution has commenced. However, the detailed survey required has been pushed back one month due to the complexity of the site, among other factors.
However, the design is still anticipated to be complete by end of September. Procurement for materials and contractors is underway, and construction is still forecasted to commence October this year.
Environmental consultants have been engaged to conduct a Review of Environmental Factors (REF). Geotechnical engineers are also investigating the locales of the creek crossings for understanding the possibility to under bore pipe at future bridge sites.
Share Project Update Thursday 6 October on Facebook
Share Project Update Thursday 6 October on Twitter
Share Project Update Thursday 6 October on Linkedin
Email Project Update Thursday 6 October link
This project was completed May 2024