Project Update Thursday 6 October

The project to reinstate a permanent solution has commenced. However, the detailed survey required has been pushed back one month due to the complexity of the site, among other factors.

However, the design is still anticipated to be complete by end of September. Procurement for materials and contractors is underway, and construction is still forecasted to commence October this year.

Environmental consultants have been engaged to conduct a Review of Environmental Factors (REF). Geotechnical engineers are also investigating the locales of the creek crossings for understanding the possibility to under bore pipe at future bridge sites.