Community Update: 23 August

Works are still progressing well and the majority of the road pavement has now been widened. Critical activities underway at the moment are an 80m x 3m retaining wall and drainage installation.

We would like to thank the community for their patience with the detour. Without the road closure, this project could not be constructed safely - half the existing pavement required removal adjacent to the retaining wall.

Work is approximately 50% complete.

Share Community Update: 23 August on Facebook Share Community Update: 23 August on Twitter Share Community Update: 23 August on Linkedin Email Community Update: 23 August link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>