Latest News: 2 July 2019

The weather has not been on our side in the last week so we were unable to remove all the contaminated material from the Beardow Street site by the end of June, despite the best efforts of all concerned.

However, by end of the financial year, we had removed 98% of contaminated material and this week we will continue to remove the last of it.

From that point on, we will be focusing on rebuilding the embankment and will be returning back to ‘normal’ operating hours:

Monday to Fridays: 7am to 6pm

Saturdays: 8am to 1pm

Sundays: No work scheduled.

We are still on track to commence roadworks in early August to re-instate the pavement in Beardow St.

Who to contact with any concerns:

  1. Rick Neale, Contract Manager – 0414 576 588

    Rick is your first point of contact and is the Project Engineer contracted from Civil Consult

  2. Your second point of contact is Steven Bennetts, Lismore City Council’s Capital Works Engineer – 0427 568 221

  3. If you need to call out of office hours: 1300 87 83 87