Latest News: 31 July 2019

Residents may be wondering why there has been minimal activity on site at the Beardow Street landslip over the last few days. This is because we are awaiting survey results to confirm that all is as it should be before we move on to the next stage of the process. This is an essential part of the quality control process. Once we have confirmation, we will start to haul what's called 'general fill' to the site, in order to fill the embankment.

We said in an earlier update that pavement re-instatement would commence in early August. We are slightly behind, mainly due to the weather and this part of the process is more likely to commence at the end of August.