Category Lismore Transit Centre Show all
-
Buildings and Facilities Update - November 2022
Share Buildings and Facilities Update - November 2022 on Facebook Share Buildings and Facilities Update - November 2022 on Twitter Share Buildings and Facilities Update - November 2022 on Linkedin Email Buildings and Facilities Update - November 2022 linkAlbert Park Baseball – Restoration works continue across the baseball fields and clubhouse & amenities. Validation report identified further areas of detailed cleaning required within the clubhouse which is being actioned to obtain certificate of validation. Batting cage replacement is currently being quoted.
Arthur Park Archery Club – Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Brunswick Street Depot – Sign shop, Fab shop and Workshop are operational. Temporary offices are in place until restoration works are complete. Contractor has been engaged for demountable office restoration. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Caniaba Street Reserve - Soccer Clubhouse – Hygienist certificate of validation received. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.
Clyde Campbell Carpark – Patching across the carpark has been completed. A scope of works and estimation of costs for severely damaged area behind Mary G’s has been submitted to Public Works Advisory for approval.
Croquet Club, Spinks Park - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
CWA Building, Spinks Park – Decontamination works continuing – planned to be completed Mid-November. Repairs to damaged heritage tile roof are scheduled. A scope of works is developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Family Support Network (Old Scout Hall – 41 Wilston St, South Lismore) – Structural assessment complete. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.
Harold Fredricks Carpark Lights – Replacement solar lights for this carpark have been procured. Awaiting arrival for installation.
Humbley Oval Hockey Club Kiosk – Site isolated via temporary fencing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
John Crowther Carpark – After being utilised as a temporary waste transfer station this carpark has now had resurfacing works and is available again for public use.
Laurie Allen Centre – Geotechnical Drilling contractor engaged to get samples to assist in the structural assessment of this building.
Lismore Airport Terminal - Hygienist certificate of validation received. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Lismore Basketball Association – Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Lismore Centra Tourist Park – Park is operational. Final restoration works on new office building is being complete.
Lismore Cattle Sale Yards – Replacement sales office designed and Development Application submitted. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Lismore City Hall - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Lismore Library - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation. Structural Drying still on-going to maintain moisture levels. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Lismore Memorial Baths – Aquatic Engineer site visit complete and awaiting on final report on water treatment system. Scope of works developed and estimation of costs of restoration works has been developed. Following outcome of Aquatic engineers assessment of water treatment system a submission for Community Recreation & Cultural Asset works required will be submitted to Public Works Advisory for approval.
Lismore Park Elaine Blanche Tennis Courts (Lismore Tennis Courts) Clubhouse – Hygienist validation sampling complete, awaiting results of reporting. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.
Lismore Regional Gallery - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Lismore SES Headquarters – Council has been working closely with SES to minimise any disruption during the replacement of floor coverings that were inundated in the February 2022 flood. This work is ongoing and is scheduled to be finished by end of November.
Lismore Transit Centre – The Transit Centre re-opened to the public on Monday 17/10/22 as a Recovery Centre and Assistance point. Minor restoration works continue throughout November as materials/supplies become available.
Marie Mackney Netball Clubhouse (Lismore Netball Courts) – Hazardous building materials have been removed. Structural drying is ongoing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Mortimer Oval (Brick Building) - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Mortimer Oval (Container Building) – Tender for the replacement of the roof structure has closed with successful tenderer selected. Scope of works developed for remaining works and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.
Municipal Building - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.
Richmond River Historical Society contents safely relocated to a flood free location whilst restoration works on the municipal building are complete.
Oakes Oval (Gordan Pavilion) - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Old Helicopter Building – Electrical, Data and Fire systems restoration has commenced. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Richards Oval Clubhouse (Lismore Workers Clubhouse) - Hazardous building materials have been removed. Structural drying is ongoing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Stock Pot Kitchen (Old Art Gallery) – Stock Pot Kitchen is open to the public. Please see their social media for details on opening hours. The Old Art Gallery’s site restoration is ongoing. A scope of works is developed, and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
Visitor Information Centre - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works is developed, and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.
-
Buildings and Facilities Update - October 2022
Share Buildings and Facilities Update - October 2022 on Facebook Share Buildings and Facilities Update - October 2022 on Twitter Share Buildings and Facilities Update - October 2022 on Linkedin Email Buildings and Facilities Update - October 2022 linkEmergency works on Council’s flood affected buildings has largely focused on removal of flood affected materials, decontamination and structural drying for all buildings to obtain validation certificates.
What’s structural drying and why is it so important?
Structural drying is the process undertaken after the removal of flood damaged porous building materials. Allowing the underlying structural building materials to dry out with the assistance of dehumidifiers, fans and sometimes gas heated blowers. This reduces the moisture levels present in the building to an acceptable level.
After this process has occurred validation assessments are done to assess the moisture levels within the building, as well as the presence of bacteria and other foreign spores to ensure the building is ready for remediation works. Ensuring mould and other bacteria do not regrow.
All of Council’s buildings have to go through this testing and receive post-remediation verification reports for the buildings moisture, microbial and hazardous material presence.
Council has been receiving these post-remediation verification reports across its built assets, including large buildings such as Lismore City Hall, Lismore Airport Terminal, Lismore Municipal Building, Lismore Library, Lismore Regional Gallery, Lismore Transit Centre and Visitor Information Centre. Some verification certificates have been received others are still awaiting the results of samples sent for testing.
October Feature Project Update - Lismore Transit Centre
The Lismore Transit Centre’s restoration works following the February natural disaster are almost complete!
On Monday 17/10/22 the Recovery Centre and Assistance Point including Service NSW, John Lyng Group, Council and Legal Aid moved into the Transit Centre. Whilst some restorative works remain, the vast majority have been complete.
Public Toilets and Showers are available at the Transit Centre (Please note this is only during the Recovery Centre operational hours).
Below are photos inside some of Council's major buildings, comparing the condition after the February 2022 natural disaster to now.
Lismore City Hall - Fountain Room
Lismore Library
Lismore Municipal Building
Lismore Regional Gallery
Lismore Airport Terminal
Lismore Memorial Baths
February 2022 and July 2022
-
Buildings and Facilities Update - September 2022
Share Buildings and Facilities Update - September 2022 on Facebook Share Buildings and Facilities Update - September 2022 on Twitter Share Buildings and Facilities Update - September 2022 on Linkedin Email Buildings and Facilities Update - September 2022 linkIt's been a busy month as restoration works continue across Council’s buildings, parks and facilities. Below you will find updates on the progress being made at Council’s Buildings, as well as some quick updates on Parks and Public toilets that required restorative works.
Albert Park Baseball - Strip out and clean of clubhouse and amenities has been completed. Electricity due to be reconnected during September.
Arthur Park Archery Club - Assessment report has been completed, with scope of works currently under review.
Gundurimba Building – Carpentry work is underway to restore this building. Heritage Consultants were engaged prior to the commencement of restoration works.
Brunswick Street Depot – Electrical restoration works to be completed throughout September.
Caniaba Street Reserve - Soccer Clubhouse – Awaiting final assessment report from hygienist before restoration works commence.
Cedar Log Shed - Scope of works is currently being assessed for this building.
Central Tourist Park – Construction of new office building to replace existing flood damaged building commenced. Minor concreting works complete.
City Hall - First floor strip out of flood damaged building materials and electrical components is underway. Followed by cleaning and assessment for scope of works. Grand piano is currently undergoing mould remediation and storage with local specialised contractor.
Croquet Club – Electrical restoration works have commenced. Heritage Consultants have been engaged to contribute to the scope of works required to this building.
CWA Building - Decontamination contractor (to prevent mould) will commence mid-September. Heritage Consultants have been engaged to contribute to the scope of works required to this building.
ELGAS - ELGAS Station still operational. Offices and stores buildings are being replaced, with design for new buildings determined in collaboration with the tenant. Fencing has been repaired and/or replaced.
Gordon Pavilion (Oakes Oval) – Oakes/Crozier Sports Hub upgrades are progressing. Gordon Pavilion cleaning and decontamination works have been finalised. The grounds of Oakes/Crozier Oval are open.
Laurie Allen Centre - Building is currently closed to the public. Removal of flood damaged building material and electrical components has been completed. Building requires specialist structural assessment before commencing restoration works.
Lismore Basketball Association - Design works are currently underway in collaboration with Lismore Basketball Association for replacement of flooring.
Lismore Airport Terminal – BOM weather station has been restored. Aeronautical instrumentation replacement is progressing. Specialist contractor has removed flood damaged airport security screening equipment. Restoration works on terminal to progress once Scope of Works required is finalised.
Lismore Cattle Sale Yards – Structural assessment has been completed. Final design of office building being reviewed in collaboration with tenants.
Lismore Lake Buildings - Restoration works have commenced with the removal of flood damaged structures.
Lismore Library – Structural drying is currently underway. Components to repair elevator have been ordered. Heritage Consultants have been engaged to contribute to the scope of works required to this building.
Lismore Memorial Baths – Clean and decontamination works have been finalised. Heritage Consultants have been engaged to contribute to the scope of works required to this facility and assessment of the pool’s pumps for restoration, replacement or elevating for future flood proofing is being considered to form part of the works required at this facility.
Lismore Park Elaine Blanche Tennis Courts (Lismore Tennis Courts) – Tennis courts are open. Clubhouse is awaiting final validation of moisture levels before restoration works can commence. Temporary toilets are available at this facility for users.
Lismore Pipe Band Building – Flood damage assessment has been completed. Clean and decontamination contractors to be engaged for this building.
Lismore Preschool – Lismore Preschool is completing restoration works directly. Please refer to their social media for further updates.
Lismore Regional Gallery -. Final detailed clean is underway, with reporting for validation of building to be done once complete. Scope of works required for the building restoration is being developed.
Lismore SES Headquarters - Open and operational.
Lismore Transit Centre – Restoration of the roof structure has been completed, with solar hot water system to be installed shortly. Full restoration works are currently underway for replacement of kitchen, public toilets, and amenities including disabled toilets and showers.
Marie Mackney Netball Clubhouse (Lismore Netball Courts) - Specialist subcontractor has been engaged to assist with removal of hazardous building materials from this building. Temporary toilets are available at this facility for users.
Mortimer Oval New Building - Validation sampling of building complete with report forthcoming. The design of a new roof structure is being finalised.
Mortimer Oval Old Building – Building currently structurally drying. Restoration works to follow.
Municipal Building, Old Council Chambers – Heritage Consultants have been engaged to contribute to the scope of works required to this building. Clean and decontamination works for prevention of mould is ongoing.
Old Helicopter Building - Electrical, data and fire system contractors have commenced restoration works.
Radio Controlled Car Building - Nesbitt Park - Works to remove flood damaged building materials and cleaning is underway. Replacement of RC Tracks boundary fencing is progressing with procurement process started.
Riverview Park Clubhouse and Canteen – Restoration of the boundary fencing of Riverview Park underway. Clubhouse and Canteen are completing drying before validation can be obtained.
Richards Oval - Workers Soccer Clubhouse – Removal of flood damaged building and electoral components complete. Structural drying underway to be followed by validation report.
Terania Building – Restoration works for electrical and plumbing have commenced, with electricity being reconnected. ACE Community Colleges are re-locating from the Terania building on Magellan St to Suite 4, Level 1 29 Molesworth Street from October 2022. Please follow their social media for further updates on exact opening dates.
Visitor Information Centre - Closed to public until restoration works are complete, structural drying has been completed. Toilets are operational and open to the public. May require intermittent closure to complete necessary works, temporary services will be available.
-
Buildings and Facilities Update - August 2022
Share Buildings and Facilities Update - August 2022 on Facebook Share Buildings and Facilities Update - August 2022 on Twitter Share Buildings and Facilities Update - August 2022 on Linkedin Email Buildings and Facilities Update - August 2022 linkThere are a number of Flood Restoration works being completed. Please see below updates on some of the projects shared for this month. Council asks members of the community to exercise caution around any of these sites and abide by temporary exclusion fences/barriers.
Updates on specific projects can be found by selecting 'Projects By Name' as found on the right side of the main article (Desktop) or scrolling to the bottom of the article page (Mobile).
If there is a project you would like particular updates on, please utilise the Q+A function of the main article.
Terania Building - Structural drying to be completed, followed by restoration works.
Albert Park Baseball - Strip out and clean of Clubhouse and Amenities commenced mid-July, expected to take two weeks. Pathway cleaning, plus removal of flood damaged storage sheds has been completed. The fencing has been removed and stored for re-use.
Arthur Park Archery Club - Scope of works to be determined, pending Assessment Report.
Gundurimba Building - Cleaning and structural drying completed. Painting has commenced, carpentry work expected to commence mid-August.
Brunswick Street Depot - Workshop and Fabrication shop are operational. Temporary offices are in place until restoration works are completed.
Caniaba Street Reserve - Soccer Clubhouse - Strip out, removal of flood damaged building material and electrical components, plus cleaning and structural drying have been completed. Restoration works to following pending validation report.
Cedar Log Shed - Scope of works is currently being assessed.
Central Tourist Park - Essential services have been restored. Restoration works of specific buildings are ongoing.
City Hall - Removal of flood damaged building material and electrical components completed on the Ground Floor. Clean, decontamination (to prevent mould) and structural drying has commenced. First Floor strip out has commenced.
Croquet Club - Building assessed. Building restoration works to commence pending current contractor procurement.
CWA Building - Decontamination (to prevent mould) expected to commence mid September, with restoration works to follow. Temporary structural bracing has been installed.
ELGAS - ELGAS Station still operational. Removal of flood damaged building material and electrical components of the office and parts store have been completed. Restoration works are currently being scoped.
Gordon Pavilion (Oakes Oval) - Facility upgrades have recommenced. Cleaning has been completed and restoration works are underway. The grounds of Oakes/Crozier Oval are open.
Laurie Allen Centre - Building is currently closed to the public. Removal of flood damaged building material and electrical components has been completed. Building requires specialist structural assessment before commencing restoration works.
Lismore Basketball Association - Design works are currently underway for replacement of flooring.
Lismore Airport Terminal - Structural drying of the building has been completed, restoration works to follow.
Lismore Cattle Sale Yards - Initial assessment completed on sale yards, further structural assessment required on octagonal sales ring and office. Restoration works to follow on finalisation of structural assessment.
Lismore Lake Buildings - Removal of flood damaged building material and electrical components on the pump shed will begin in August. Restoration works to follow.
Lismore Library - Following paint strip out, a final detailed clean will be completed by end of August. Once completed, structural drying will take place over a four week period.
Lismore Memorial Baths - Removal of flood damaged building material and electrical components, plus cleaning of office buildings completed and change rooms are ongoing. Pool has been de-sludged, pool surrounds and equipment approaching completion. New security fence has been erected, with further restoration works to follow.
Elaine Blanch Tennis Courts (Lismore Tennis Courts) - Cleaning of the courts is completed. Clubhouse undergoing structural drying, before commencing restoration works.
Lismore Pipe Band Building - Damage assessment and repair scoping underway.
Lismore Preschool - Damage assessment and repair scoping underway.
Lismore Regional Gallery - Strip out, removal of flood damaged building material and electrical components is complete. A final detail and clean is underway. Up to 4 weeks structural drying required prior to restoration commencing.
Lismore SES Headquarters - Open and operational. Minor restoration works and final cleaning to be completed.
Lismore Transit Centre - Structural drying scheduled to be completed in August. Restoration works to follow to repair building for public use.
Marie Mackney Netball Clubhouse (Lismore Netball Courts) - Removal of flood damaged building material and electrical components is ongoing. Specialist subcontractor has been engaged to assist with these works.
Mortimer Oval New Building - Strip out of damaged flooring and detailed cleaning complete. Validation report and roof design underway.
Mortimer Oval Old Building - Removal of flood damaged building material nearing completion. Restoration works to commence.
Municipal Building, Old Council Chambers - Building closed to public, museum staff removing and cleaning artefacts with the assistance of the Contractor onsite. Ground Floor flood damaged material removal commenced by specialist subcontractor. Clean and decontamination (to prevent mould) of First Floor to be completed by September.
Old Helicopter Building - Structural drying complete, with restoration to follow pending validation reporting. Electrical, data and fire system contractors have been engaged to commence restoration works.
Radio Controlled Car Building - Nesbitt Park - Works to remove building materials and cleaning is underway.
Riverview Park Clubhouse and Canteen - Initial cleaning has been completed. Structural drying is now underway.
Richards Oval - Workers Soccer Clubhouse - Strip out, removal of flood damaged building material underway pending specialist contractor.
Visitor Information Centre - Closed to public until restoration works are complete, structural drying has been completed. Toilets are operational and open to the public. May require intermittent closure to complete necessary works, temporary services will be available.