Flood Restoration - Buildings, Parks and Facilities

Share Flood Restoration - Buildings, Parks and Facilities on Facebook Share Flood Restoration - Buildings, Parks and Facilities on Twitter Share Flood Restoration - Buildings, Parks and Facilities on Linkedin Email Flood Restoration - Buildings, Parks and Facilities link

This page is dedicated to updating our community on the extensive damage to Council’s Buildings, Parks and Facilities since the February and March 2022 flood events.

Over 100 Council sites were affected by the February and March 2022 flooding events, including buildings, parks, public toilets and facilities.

The majority of this project is funded under the Community, Recreation and Cultural (CRC) Assets Restoration. The scope of this project covers the restoration of assets that have been flood affected. There are other Council owned assets that are not identified in the scope of this project, that will fall under different grant funding guidelines.

Council is currently working to an estimated completion of June 30, 2024 for the repair of all affected sites.



All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Name' at the bottom of this page. If on a desktop, 'Projects by Name' are to the right.

Council was able to complete Emergency and Immediate Restoration works under the Disaster Recovery Funding Arrangements for these assets until 31/12/22 (subsequent extension was granted to 31/01/23). Emergency works for larger built assets have focussed on the removable of flood debris, impacted building materials and electrical componentry, structural drying and providing emergency temporary facilities such as port-a-loo’s and electrical connections. Whilst less damaged assets such as Public Toilets and Parks have had immediate restorative work completed.

The demolition and removal of impacted materials from larger built assets has enabled the scoping and estimation works required to make submissions to Resilience NSW’s administering agencies to secure funding to return these assets to their pre-disaster condition. Community, Recreation and Cultural Asset Restoration works can be completed within 2 years after the end of the financial year in which the disaster occurred.

With many assets requiring restoration, Bennett Constructions has been appointed as the managing contractor.

The below table identifies all the different Council Buildings, Parks and Facilities that require restoration works following the February/March 2022 Natural Disaster event.

✔️ Restoration is completed 🚧 Restoration works underway 📋 Assessment completed and works scheduled to begin

For further specific updates, see 'Projects By Name' tab

Buildings, Parks or Facilities requiring restoration works
Airforce Road (20) Reserve Park 📋Lismore Regional Gallery 🚧
Albert Park Baseball Facility / Complex ✔️ Lismore SES Headquarters ✔️
Arthur Park 📋Lismore Transit Centre ✔️
Arthur Park Archery Club 🚧 Mackenzie Oval ✔️
Arthur Park Toilet Block ✔️ Marie Mackney Netball Clubhouse ✔️
Barnard Park ✔️ McKenzie Park Toilet Block/Kiosk ✔️
Blair Oval ✔️Meadow Drive Park 📋
Brunswick Street Depot 🚧 Memorial Park ✔️
Caniaba Street Reserve ✔️ Monaltrie Creek - Drainage from Footbridge Airforce Road Reserve 📋
Caniaba Street Reserve - Soccer Clubhouse 🚧 Mortimer Oval ✔️
Captain Rous Park 📋 Mortimer Oval amenities - Brick Building 🚧
Cattle Sale Yards 🚧 Mortimer Oval amenities - Container Building 🚧
Clyde Campbell Carpark ✔️ Neilson Park ✔️
Clyde Campbell Carpark Toilet ✔️ Nesbitt Park New Toilet Block ✔️
Coronation Park, The Channon ✔️ Nesbitt Park Old Toilet Block ✔️
Croquet Club - Spinks Park ✔️ Nesbitt Park 🚧
Crozier Field Canteen 🚧 Oakes Oval Facility (Gordan Pavilion) ✔️
CWA Building - Spinks 🚧 Old Helicopter Main Building ✔️
Davidson Oval ✔️ Municipal Building 🚧
Dungarubba Reserve Toilet Block and Shelter ✔️ Pritchard Park ✔️
Elaine Blanch Tennis Courts ✔️ Public Toilet - Dawson Street ✔️
ELGAS Office, Amenities and Store Room 🚧 Quad Park Lismore CBD 🚧
Family Support Network - Old Scout Hall South Lismore 📋 Radio Controlled Car Building -Nesbitt Park ✔️
Fawcetts Bridge Carpark 📋 Rhodes Street Park ✔️
Fredericks Carpark 📋 Richards Oval ✔️
Gundurimba Building ✔️ Richards Oval - Workers Soccer Clubhouse 🚧
Harold Fredricks Car Park Lights 📋 Riverside Park ✔️
Heaps Oval 🚧 Riverside Park Toilets ✔️
Hensley Carpark (Lower) 📋 Riverview Park 🚧
Hensley Carpark (Top) 📋 Riverview Park Amenities and Clubhouse ✔️
Heritage Park ✔️ Roder Oval ✔️
Humbley Oval Hockey Club Kiosk 🚧 Rowing Club Carpark
Joblin Park ✔️ Sam Trimble Oval ✔️
John Crowther Carpark 📋 Sam Trimble Oval Amenities ✔️
Jolley Field ✔️ Shearman Carpark 📋
Keen Street Carpark ✔️ Spinks Park 📋
Kirkland Riviera Carpark 📋 Spinks Park Carpark 📋
Laurie Allan Centre✔️ Stock Pot Kitchen - Old Art Gallery 🚧
Lions Park 📋 Stocks Park (Cedar Log Shed) 🚧
Lismore Airport Terminal 🚧 Terania Building 🚧
Lismore Basketball Stadium 🚧 Tucki Tucki Creek Reserve ✔️
Lismore Centra Tourist Park✔️ Victoria Street Carpark ✔️
Lismore City Hall 🚧 Visitor Information Centre 🚧
Lismore Lake 🚧 W Tresise Railway Park ✔️
Lismore Lake Precinct including Boat Ramp 📋 Wade Park ✔️
Lismore Library 🚧 Wade Park Toilet Block ✔️
Lismore Memorial Baths ✔️ Wilsons Walking Trail 📋
Lismore Pipe Band Building ✔️ Wyrallah Park ✔️
Lismore Railway Station Toilet Block (Union Street) ✔️ Wyrallah Park Amenities ✔️


The availability of contractors and materials may cause delays in the progress of the restoration projects. Some restoration works are also subject to weather conditions which may cause delays.

If there is a damaged building, park or facility missing from this list, please use the Q&A function below to assist Council in locating further flood damaged assets.


This page is dedicated to updating our community on the extensive damage to Council’s Buildings, Parks and Facilities since the February and March 2022 flood events.

Over 100 Council sites were affected by the February and March 2022 flooding events, including buildings, parks, public toilets and facilities.

The majority of this project is funded under the Community, Recreation and Cultural (CRC) Assets Restoration. The scope of this project covers the restoration of assets that have been flood affected. There are other Council owned assets that are not identified in the scope of this project, that will fall under different grant funding guidelines.

Council is currently working to an estimated completion of June 30, 2024 for the repair of all affected sites.



All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Name' at the bottom of this page. If on a desktop, 'Projects by Name' are to the right.

Council was able to complete Emergency and Immediate Restoration works under the Disaster Recovery Funding Arrangements for these assets until 31/12/22 (subsequent extension was granted to 31/01/23). Emergency works for larger built assets have focussed on the removable of flood debris, impacted building materials and electrical componentry, structural drying and providing emergency temporary facilities such as port-a-loo’s and electrical connections. Whilst less damaged assets such as Public Toilets and Parks have had immediate restorative work completed.

The demolition and removal of impacted materials from larger built assets has enabled the scoping and estimation works required to make submissions to Resilience NSW’s administering agencies to secure funding to return these assets to their pre-disaster condition. Community, Recreation and Cultural Asset Restoration works can be completed within 2 years after the end of the financial year in which the disaster occurred.

With many assets requiring restoration, Bennett Constructions has been appointed as the managing contractor.

The below table identifies all the different Council Buildings, Parks and Facilities that require restoration works following the February/March 2022 Natural Disaster event.

✔️ Restoration is completed 🚧 Restoration works underway 📋 Assessment completed and works scheduled to begin

For further specific updates, see 'Projects By Name' tab

Buildings, Parks or Facilities requiring restoration works
Airforce Road (20) Reserve Park 📋Lismore Regional Gallery 🚧
Albert Park Baseball Facility / Complex ✔️ Lismore SES Headquarters ✔️
Arthur Park 📋Lismore Transit Centre ✔️
Arthur Park Archery Club 🚧 Mackenzie Oval ✔️
Arthur Park Toilet Block ✔️ Marie Mackney Netball Clubhouse ✔️
Barnard Park ✔️ McKenzie Park Toilet Block/Kiosk ✔️
Blair Oval ✔️Meadow Drive Park 📋
Brunswick Street Depot 🚧 Memorial Park ✔️
Caniaba Street Reserve ✔️ Monaltrie Creek - Drainage from Footbridge Airforce Road Reserve 📋
Caniaba Street Reserve - Soccer Clubhouse 🚧 Mortimer Oval ✔️
Captain Rous Park 📋 Mortimer Oval amenities - Brick Building 🚧
Cattle Sale Yards 🚧 Mortimer Oval amenities - Container Building 🚧
Clyde Campbell Carpark ✔️ Neilson Park ✔️
Clyde Campbell Carpark Toilet ✔️ Nesbitt Park New Toilet Block ✔️
Coronation Park, The Channon ✔️ Nesbitt Park Old Toilet Block ✔️
Croquet Club - Spinks Park ✔️ Nesbitt Park 🚧
Crozier Field Canteen 🚧 Oakes Oval Facility (Gordan Pavilion) ✔️
CWA Building - Spinks 🚧 Old Helicopter Main Building ✔️
Davidson Oval ✔️ Municipal Building 🚧
Dungarubba Reserve Toilet Block and Shelter ✔️ Pritchard Park ✔️
Elaine Blanch Tennis Courts ✔️ Public Toilet - Dawson Street ✔️
ELGAS Office, Amenities and Store Room 🚧 Quad Park Lismore CBD 🚧
Family Support Network - Old Scout Hall South Lismore 📋 Radio Controlled Car Building -Nesbitt Park ✔️
Fawcetts Bridge Carpark 📋 Rhodes Street Park ✔️
Fredericks Carpark 📋 Richards Oval ✔️
Gundurimba Building ✔️ Richards Oval - Workers Soccer Clubhouse 🚧
Harold Fredricks Car Park Lights 📋 Riverside Park ✔️
Heaps Oval 🚧 Riverside Park Toilets ✔️
Hensley Carpark (Lower) 📋 Riverview Park 🚧
Hensley Carpark (Top) 📋 Riverview Park Amenities and Clubhouse ✔️
Heritage Park ✔️ Roder Oval ✔️
Humbley Oval Hockey Club Kiosk 🚧 Rowing Club Carpark
Joblin Park ✔️ Sam Trimble Oval ✔️
John Crowther Carpark 📋 Sam Trimble Oval Amenities ✔️
Jolley Field ✔️ Shearman Carpark 📋
Keen Street Carpark ✔️ Spinks Park 📋
Kirkland Riviera Carpark 📋 Spinks Park Carpark 📋
Laurie Allan Centre✔️ Stock Pot Kitchen - Old Art Gallery 🚧
Lions Park 📋 Stocks Park (Cedar Log Shed) 🚧
Lismore Airport Terminal 🚧 Terania Building 🚧
Lismore Basketball Stadium 🚧 Tucki Tucki Creek Reserve ✔️
Lismore Centra Tourist Park✔️ Victoria Street Carpark ✔️
Lismore City Hall 🚧 Visitor Information Centre 🚧
Lismore Lake 🚧 W Tresise Railway Park ✔️
Lismore Lake Precinct including Boat Ramp 📋 Wade Park ✔️
Lismore Library 🚧 Wade Park Toilet Block ✔️
Lismore Memorial Baths ✔️ Wilsons Walking Trail 📋
Lismore Pipe Band Building ✔️ Wyrallah Park ✔️
Lismore Railway Station Toilet Block (Union Street) ✔️ Wyrallah Park Amenities ✔️


The availability of contractors and materials may cause delays in the progress of the restoration projects. Some restoration works are also subject to weather conditions which may cause delays.

If there is a damaged building, park or facility missing from this list, please use the Q&A function below to assist Council in locating further flood damaged assets.

  • Project Updates - March 2024

    Share Project Updates - March 2024 on Facebook Share Project Updates - March 2024 on Twitter Share Project Updates - March 2024 on Linkedin Email Project Updates - March 2024 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)(External link)

    Arthur Park Archery Club

    Works commencing in April 2024.

    Brunswick Street Depot - Old Helicopter Building - Completed

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    External painting, club signage, changerooms and amenities were all completed.

    The canteen and Level 1 kitchen received finishing touches, with external stairs to be installed early April.

    Cedar Log Shed

    Costing and design for roof structure.

    CWA Building

    Ceiling work underway in the main hall and blockwork began on the extension. The concrete slab for wet areas is progressing, with tiling and services fit off to commence when sheeting is completed.

    Lismore Airport Terminal

    Early March saw the terminal floor finishes and Hearing Augmentation Loop installed and preparation for the generator lift underway.

    External works included pressure-cleaning and external conduit and trenching works progressing. By end of March, joinery and all service fit offs were nearing completion, and the generator was lifted to its new position. Aiming for completion of Stage 1 – early April.

    Lismore Basketball Association

    Subgrade earth works were underway to the gymnasium floor. The screw piles installation commenced, and was completed by the end of March.

    The waffle pod system (underfloor) was delivered and installed. The steel cages and the slab reinforcement also completed, underfloor finalised by completion of the concrete pours.

    Lismore Cattle Saleyards

    Works to commence mid-April. Focusing on the pedestrian walkway and replacement of damaged fencing.

    Lismore City Hall

    Design investigations relating to AV, Stage fit-out, Electrical, Mechanical and Hydraulics works progressing.

    Demolition continued, including external tile removal and internal brick wall removal and will continue in the coming weeks once the new design is approved. By the end of the month, investigation of a roof access system was being carried out and non-loadbearing wall removal was underway, and materials loaded out.

    Lismore Library

    Mid-March saw the establishment of the site and temporary power set up. The scaffold loading bay was installed and the rendering commenced on the ground floor.

    Lismore Municipal Building

    Strip out of all old services and rectification to the brickworks underway.

    Rendering to internal areas commenced and the parapet rectifications were in progress.

    Lismore Regional Gallery

    In early March, works on the ground floor consisted of lining of the wet areas and ceilings.

    Glazing installations in the Northern and Southern Walkways progressed. External cladding replacement was also underway.

    Level 1 works included wall and ceiling linings and skirting installation underway (set and sand). Plantroom deck works included waterproofing, and the replacement of a new Chiller and A/C condenser.

    Richards Oval Soccer Clubhouse (Workers FC)

    Tiling and painting underway and the rough-in almost complete. By the end of March, the epoxy flooring was complete, permanent power re-connected to the building and first floor tiling and fit off nearing completion.

    The Clubhouse is on track for completion in April, allowing for gates to be added to scope of works.

    Riverview Park

    Design of upcoming Accessible Toilet/Changeroom Block progressed.

    The Quad

    Temporary covered walkway constructed – ready for works to begin. Walkway access for pedestrians will remain, ensuring access between Harold Fredericks Carpark and Keen Street.

    Visitor Information Centre building

    Setting and timber trims nearing completion and the main switchboard fit off commenced.

    Towards the end of the month, painting was nearing completion with only Level 2 and one wall on Level 1 to go. The lighting fit-off was completed on both ground floor and Level 1. The spiral duct installation complete and skylights installed. Security and mechanical fit offs and joinery (reception desk/kitchenette) all well underway.

    Ground floor toilets re-opened, seeing the temporary toilets removed. Carpet and final joinery installation will mark the completion of this project in early April.


    Lease agreements are underway for the following buildings, ensuring the successful handover to community. The public notices will be available on the Your Say homepage for public comment.

    CWA Building - 115 Molesworth Street

    Lismore Park Elaine Blanch Tennis Courts (Lismore Tennis Courts) - 82 Ballina Road

    Lismore RSL Sub-Branch - 179 Molesworth Street

    Municipal Building - 165 Molesworth Street

    The following are scheduled for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage. Dates listed below are estimated, pending project progress, available trades/services and favourable weather.
    If you have any concerns or questions about the demolition of these buildings, please contact floodrestoration@lismore.nsw.gov.au

    Family Support Network - Old Scout Hall

    Demolition to proceed - June 2024

    Lismore Lake Buildings

    Demolition to proceed for toilet block and pumphouse - April 2024
    New modular toilet to be constructed (separate future project)

    Sam Trimble Oval Amenities

    Demolition to proceed - weatherboard building - May 2024
    Brick building to be refurbed
    A new modular toilet is to be constructed (separate future project)

    Humbley Oval Hockey Club Kiosk

    Demolition to proceed - May 2024

    Old Essential Energy Building

    Corner Ballina Road and Conway St - April 2024
    Demolition to proceed

    Neilson Park Canteen Building, East Lismore

    Demolition to proceed - May 2024
    A new modular toilet is to be constructed (separate future project)

    McKenzie Park Amenities, North Lismore

    Demolition to proceed - May 2024
    A new modular toilet is to be constructed (separate future project)

    Wade Park, East Lismore

    A new modular toilet is to be constructed, or temporary facilities established, before demolition will proceed. - June 2024

  • Project Updates - February 2024

    Share Project Updates - February 2024 on Facebook Share Project Updates - February 2024 on Twitter Share Project Updates - February 2024 on Linkedin Email Project Updates - February 2024 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)(External link)

    Arthur Park Archery Club

    Finalising costing to progress works. Currently scheduled to be completed in April 2024.

    Brunswick Street Depot - Old Helicopter Building

    Nearing completion, with painting of first floor offices and additional drainage added.

    Site pack down commenced, as final defects and stakeholder requirements are addressed, costed and completed.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Demolition and tile removal was completed, ready for waterproofing and retiling to commence.

    Level 1 linings and carpentry was completed, ready for internal and external painting which was completed by the end of the month.

    Changerooms, amenities and kitchen nearing completion, ready for fit out.

    Cedar Log Shed

    In design review to address extensive damage to the roof structure, with a focus on future flood resilience.

    CWA Building

    Onsite meeting with stakeholders to discuss kitchen fit out, scope of works, final designs and construction underway.

    Lismore Airport Terminal

    Slab and fitting of the generator was completed.

    Inside the Terminal, walls were set and internal painting commenced. Finishes such as skirting, tiling, toilet partitions and high access cleaning were carried out. Automatic doors, flooring and bathroom fit off were completed also.

    The Terminal is on track to be completed by the end of March 2024.

    Lismore Basketball Association

    Entry point in the side brick wall has been established, for easy equipment and machinery access.
    Padded walls removed and safely stored, ready for floor demolition to commence.

    Lismore Cattle Saleyards

    Onsite meeting with stakeholders to discuss working collaboratively and utilising local contractors to complete confirmed scope of works, including walkway, ramps and some fencing.

    Lismore City Hall

    Demolition works are well underway, including tile and slab removal through the kitchen and wet areas.

    Level 3 old cabling was removed, ready for installation of temporary switchboards and lighting. The southern walkway floor reinstatement was also completed, lights reinstated and concrete beams propped ready for brickwork removal on Level 1.

    Lismore Municipal Building

    Scaffolding and site set up complete.

    Onsite meeting with existing stakeholders earlier in the month to confirm scope of works, and gather additional insight to progress with a proposal to make the ground floor all accessibility friendly.

    Lismore Regional Gallery

    The roof replacement and solar panel installation have been completed. External wall cladding, service rough ins and walls and ceilings are underway.

    Southern walkways were a focus with removal of glazing and frames, with window frame installation also commencing.

    New electrical mains cable rough ins, soffits and fan coil units for Level 1 will be completed shortly, ready to finalise wall linings, ceilings and insulation.

    Mortimer Oval Amenities

    Completed and ready for community handover.

    Richards Oval Soccer Clubhouse (Workers FC)

    First floor demolition completed, with demolition of the ground floor to commence.

    Sheeting, rough ins, pipework replacement, plastering, door jams and trims were all underway by the end of the month.

    Riverview Park

    Onsite meeting with stakeholder to address defects and requirements, ensuring space is fit for purpose.

    Confirmed design of upcoming Accessible Toilet/Changeroom Block to be based next to the undercover area.

    The Quad

    Site set up and fencing commenced. Walkway access for pedestrians will remain, ensuring access between Harold Fredericks Carpark and Keen Street.

    Visitor Information Centre building

    Wall linings and sheeting completed, with door hangings and timber trims all underway.

    External works include gutter replacement and gutter guard installation. Site clean up has begun, with the removal of scaffolding. Estimated completion in March 2024.

    Lease agreements are underway for the following buildings, ensuring the successful handover to community. The public notices will be available on the Your Say homepage for public comment.

    Caniaba Street Reserve - Soccer Clubhouse (Celtics FC) - 2 Caniaba Street

    CWA Building - 115 Molesworth Street

    Lismore Park Elaine Blanch Tennis Courts (Lismore Tennis Courts) - 82 Ballina Road

    Lismore RSL Sub-Branch - 179 Molesworth Street

    Municipal Building - 165 Molesworth Street

    Richards Oval Soccer Clubhouse (Workers FC) - 48B & 48I Brewster Street

    The following are being proposed for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage.

    Family Support Network - Old Scout Hall - 41 Wilson Street, South Lismore

    Humbley Oval Hockey Club Kiosk - Cnr of Brewster and Uralba Street, Lismore

    Laurie Allen Centre, The Rowing Club - Molesworth Street. Top two levels only, basement building currently in use.

    Lismore Lake Buildings - the old pumphouse and toilet block next to the pool site. Proposal for the toilet block to be demolished and replaced, pending available funding.

    Sam Trimble Oval Amenities - Proposal for the toilet block to be demolished and replaced, pending available funding.

  • Project Updates - December 2023/January 2024

    Share Project Updates - December 2023/January 2024 on Facebook Share Project Updates - December 2023/January 2024 on Twitter Share Project Updates - December 2023/January 2024 on Linkedin Email Project Updates - December 2023/January 2024 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)

    Completed by the end of 2023

    Albert Park Baseball

    Croquet Clubhouse

    Brunswick Street Depot

    Elaine Blanche Tennis Courts Clubhouse

    Lismore Memorial Baths

    Marie Mackney Netball Clubhouse

    Mortimer Oval Container Building

    Mortimer Oval Brick Building

    Oakes/Crozier Amenities

    Radio Controlled Car Building - Nesbitt Park

    Brunswick Street Depot - Old Helicopter Building

    Internal stairs have been built, and floor coverings installed.

    In the workshop, painting has been completed and AC equipment installed. External cladding is in progress.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.

    Lismore Airport Terminal

    All services rough ins completed during December. The mechanical condenser was replaced, the outdoor PAC unit and 3 x fan coil units installed. Geotech testing of the external generator location was conducted. Linings and insulation of internal walls has commenced.

    Lismore Basketball Association

    Site set up ready for works to replace the subfloor commence in January.

    Lismore Cattle Saleyards

    List of restoration priorities being determined with stakeholders. Scheduling of works to be determined in line with sale activities.

    Lismore City Hall

    Site set up complete, ready for works to commence in January.

    Lismore CWA Building

    Site set up and works to commence in January.

    Lismore Municipal Building

    Onsite meeting with stakeholders to inform accessibility in the design of the ground floor.

    Lismore Regional Gallery

    At the beginning of December, the solar panels were removed from the roof and the NBN fibre was installed. The laying of CFC flooring to L1 was completed and scaffolding erected to the North, East and West sides of external elevations. Roof sheets were delivered in early January which will be installed late January due to weather conditions. Internal cement rendering and repair of ground floor walls underway and the demolition strip-out of internal load bearing walls and kitchen benches are complete.

    Mortimer Oval Amenities

    Internal and external works now complete. Landscaping to be completed, which will finalise restoration for the end of January.

    Richards Oval Soccer Clubhouse (Workers FC)

    Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.

    Riverview Park

    Stage 1 – Completed 20/12/23 and the building handed back to the user group.

    Stage 2 – Field lighting and PA installation - nearing completion

    The Quad

    To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.

    Visitor Information Centre building

    Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.


  • Project Updates - November 2023

    Share Project Updates - November 2023 on Facebook Share Project Updates - November 2023 on Twitter Share Project Updates - November 2023 on Linkedin Email Project Updates - November 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Brunswick Street Depot - Old Helicopter Building

    Service rough ins, ceiling lining and floor preparation for vinyl covering have commenced. Handrail posts were installed and the main frame to the second level also in place.

    Doors were installed, tiling underway and balustrades arrived late November. By the end of November, 90% of the plastering had been completed. Laying of the vinyl flooring and internal painting is now well underway.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Mood board and 90% plans have been approved by stakeholders. Container moved onsite for storage ahead of works commencing in January.

    Crozier and Oakes Oval Amenities (Dawson Street and Magellan Street Toilets)

    Restoration and handover has been completed for all amenities blocks. Works on the ticket booth at Oakes will now progress.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts)

    Restoration completed, with final inspection scheduled for Wednesday 29 November. Celebration of the key handover and completion of works is scheduled for December 14.

    Laurie Allan Centre

    Immediate restoration works including deep cleaning, lighting and hot water were completed. Handover to Far North Coast Canoe has been finalised. Additional longer term works are still being scoped and reviewed.

    Lismore Airport Terminal

    Site establishment was completed early November. Mechanical and electrical preliminary make safe had commenced. Hydraulics investigation was conducted and a clean out and rough in was completed. Procurement for mechanical, electrical and hydraulics was completed.

    Towards the end of November, mechanical pipework rough ins had commenced, and the electrical and data security rough ins had commenced.

    Lismore Basketball Association

    Meeting held with stakeholders to discuss site set up ahead of January 2024 start to replace the flooring.

    Lismore City Hall

    Storage containers onsite in preparation for early works to commence in December.

    Lismore CWA Building

    Scope of works increased, to incorporate additional roofing requirements. Works scheduled to commence in January. Estimated completion date is March 2024.

    Lismore Lake Buildings

    Meeting held with stakeholders to discuss scope of works.

    Lismore Library

    Estimated start February 2024. Slight schedule changes to accommodate Lismore Regional Gallery, The Quad and Lismore Library being completed concurrently.

    Lismore Memorial Baths

    The Pools were filled and filter system activated. With power restored, tiling, painting and cleaning including the cleaning of the 50m pool commenced.

    Installation of the mod wood slat seating in the Grandstand and landscaping also commenced. Preparing for a December 2023 opening.

    Lismore Municipal Building

    Estimated start February 2024.

    Lismore Regional Gallery

    During November, site was established. Temporary power had been installed and isolation of the solar panels carried out. Early strip out and make safe was completed, by the end of the month the ceiling in Level 1 was stripped out and removed. Design was completed with procurement of trades well underway.

    Mortimer Oval Amenities

    Restoration and handover complete on the Container Building. User groups have been notified, ready to prepare for next season.

    Site establishment was completed for the Brick Building. Demolition complete and rendering well underway. Plumbing including roofing works commenced at the end of November.

    Marie Mackney Netball Courts (Lismore Netball)

    Flooring, painting (internal and external) and electrical fit off were all completed in November.

    Towards the end of November, the stainless-steel benches and roller doors were installed and all fit offs by service trades (electrical, plumbing and security) were well underway. Final inspection has been completed, awaiting handover with user group.

    Radio Controlled Car Building - Nesbitt Park

    Completed, finalising handover to user group.

    Richards Oval Soccer Clubhouse (Workers FC)

    Meeting held with stakeholders to discuss 90% design and colour options. Mood board and 90% plans have been approved by stakeholders. Container moved onsite for storage ahead of works commencing in January.

    Riverview Park

    Works have begun with site establishment complete, and the redundant shower block demolished.

    The Quad

    To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.

    Visitor Information Centre building

    Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.

  • Project Updates - October 2023

    Share Project Updates - October 2023 on Facebook Share Project Updates - October 2023 on Twitter Share Project Updates - October 2023 on Linkedin Email Project Updates - October 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Brunswick Street Depot - Old Helicopter Building

    Construction commenced, with the the electrical, data and security wiring started. Sheeting of the walls and ceilings in the workshop offices is also underway.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Design progressing with colour scheme selections made in conjunction with stakeholders. Schedule of works will be set following cost plan completion.

    Crozier and Oakes Oval Amenities (Dawson Street and Magellan Street Toilets)

    Dawson Street toilet block was reopened to the public in early October.

    Magellan Street ceiling sheeting, fit out and painting has been completed.

    Crozier Oval block linings and fitout is mostly complete, with painting to follow.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts)

    The wall and ceiling sheeting was completed at the beginning of October. Setting of the wet areas and the timber trim installation was also commenced. Internal linings and carpentry fit out were completed with new glazing installed. Internal painting was well underway.

    The training wall was finished and the shed repairs completed with both now being ready for painting. Repairs were also underway on the fencing. Joinery was well underway and the external painting started.

    By the end of the month, floor preparation for epoxy was underway, and the electrical fit off to ceilings started. Lighting and switchboard works had also commenced and external painting and window repair started.

    Delay of works has been attributed to trades and material availability. Handover to the Tennis Club is scheduled for November.

    Lismore Airport Terminal

    Site set up has been established and external fencing has been erected. Works have commenced, completing a basic strip out, ready for trades to start.

    Lismore Cattle Saleyards

    Onsite meeting with stakeholders to finalise scope of works required.

    Lismore CWA Building

    90% design completed, cost plan currently being reviewed. Schedule of works will be set following cost plan completion. Estimated completion date is February 2024.

    Lismore Library

    Design is progressing, pending completion of the cost plan. Construction dates will be determined following cost plan and design completion. Estimated January 2024 to commence.

    Lismore Memorial Baths

    The sheeting of the walls in the Pavilion commenced as well as electrical, hydraulic and security rough ins. The new hot water systems were installed in the pump room.

    Toward the end of the month, roofing on the lifeguard tower had been installed. All stud framing and villa board walls in the Pavilion were completed and painting commenced. Service trade rough ins were completed in the pool amenities building and ceiling framing and re-lining underway. Replacement of the existing roof and box gutters were completed. Works on the two pools had progressed and included a new filtration system.

    Scaffolding has been taken down from around the Lifeguard Tower and Pavilion.

    Laurie Allan Centre

    Offsite storage for boats is being explored to ensure disruptions to members and building users are minimised during works period.

    Lismore Municipal Building

    Colour scheme determined in conjunction with stakeholders. Design progressing for floor upgrades. Estimated start January 2024.

    Lismore Regional Gallery

    Remaining equipment and Gallery items have been stored ready for Stage 1 construction. Restoration for The Quad confirmed be completed in conjunction with Stage 2 of the Gallery works (commencing in 2024).

    Mortimer Oval Amenities

    All flooring, the external ceiling and an external clean was completed. Electrical fit out and all roofing was also completed. By the end of October, the internal fit out and flooring was completed as well as internal and external painting. Shower linings and toilet partitions to be installed in the coming weeks.

    Marie Mackney Netball Courts (Lismore Netball)

    At the beginning of October, the insulation and wall sheeting were completed for both floors including the wet areas. Setting was underway to the wet areas. Internal linings were completed and internal fit off including doors was also underway.

    The switchboard installation and electrical requirements progressed well.

    By the end of October, preparation for painting had commenced, and the doors installed. External cladding was reinstated. Timber trims and doors were completed. Internal painting to Level 1 had begun and external painting to the south elevation was finished.

    Delay of works has been attributed to trades and material availability. Handover to the LDNA is scheduled for November.

    Radio Controlled Car Building - Nesbitt Park

    Site set-up has been established, and works are steadily progressing.

    Richards Oval Soccer Clubhouse (Workers FC)

    Onsite meeting with stakeholders to determine scope of works.

    Riverview Park

    Works have begun with site establishment complete, and the redundant shower block demolished.

    Visitor Information Centre building

    Construction has commenced.

  • Project Updates - September 2023

    Share Project Updates - September 2023 on Facebook Share Project Updates - September 2023 on Twitter Share Project Updates - September 2023 on Linkedin Email Project Updates - September 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Brunswick Street Depot - Old Helicopter Building

    Construction set to commence shortly, with estimated completion date of January 2024.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Onsite meeting with South Lismore Celtics representatives, to inform the design of the future rebuild suited to needs of the club.

    Crozier and Oakes Oval Amenities (Dawson Street and Magellan Street Toilets)

    The roof structure on both the Dawson and Magellan Street blocks commenced in September. Scyon flooring sheeting was laid and the plumbing rough-in completed. The structural steel roof framing to three buildings is now complete and the new Colorbond roof sheeting installed. Translucent roof sheeting was added to increase natural lighting within the building. Painting commenced at the Dawson Street block.

    Perimeter scaffolding will be removed shortly.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts)

    The existing training wall was demolished this month, requiring a rebuild due to extensive damage to the brickwork. By the end of the month, blockwork for the new wall was complete.

    Preliminary drainage works were also started and by mid-month, drainage was completed for the ground floor wet areas. Prep-work for the ground floor slab reinstatement has also commenced. Service rough-ins for security, electrical and plumbing are now complete.

    Lismore Airport Terminal

    Construction on the Terminal building set to commence shortly, with estimated completion date of January 2024.

    Lismore Library

    Onsite meeting with Library stakeholders to inform the design of future rebuild. Decisions on colour and fit out materials are now being made.

    Additionally, the Library received funding to continue offering pop-up spaces.

    Lismore Memorial Baths

    It was busy at the Baths in September. The last of the shade sails on the pool deck were pressure cleaned.

    All redundant solar tube systems and heat pumps were removed from the Amenities Block, lifeguard tower and the pump room roof in preparation for the new roof installation. Old roof and insulation was removed from the Amenities Block, before the new roof and insulation is installed.

    The Canteen fitout is underway, with a new grease arrest and hydraulic pipework installed. Plumbing, gas and electrical rough-ins has also commenced in all buildings. Work is also underway in the Amenities room including fixtures and plumbing rough-in of showers.

    The Baths also hosted the Mates in Construction Fly The Flag Breaky BBQ, which was a great success!

    The Pavilion was rendered and painting will continue through October.

    Laurie Allan Centre

    Onsite meeting with the Far North Coast Canoe Club representatives, to discuss future plans for the building, and their immediate needs in relation to the space.

    Lismore Municipal Building

    Onsite meeting with Richmond River Historical Society representatives, to inform the design of the future rebuild suited to needs of the user group.

    Lismore Regional Gallery

    Review of scope and grant funding with Project Team. Restoration for The Quad will now be completed in conjunction with Gallery works.

    Mortimer Oval Amenities

    In early September the roof structure was started with roof post footings being poured, roof sheeting and flashing installed. The roof structure was finished just in time for month end. Flooring was laid and power restored to the entire building. Resilient finishes were ordered and awaiting delivery.

    Marie Mackney Netball Courts (Lismore Netball)

    Drainage works, termite treatments and ground prep for the slab reinstatement had commenced and the Scyon flooring installed to the first floor.

    The external soffit was also completed and by the end of the month the service rough-ins underway and the internal wall framing complete.

    The goal was to have the clubhouse ready for September. However a number of challenges were faced and now aiming for completion at the end of October.

    Radio Controlled Car Building - Nesbitt Park

    Construction set to commence shortly, with estimated completion date of January 2024.

    Riverview Park

    Discus nets have been completed. Construction on clubhouse set to commence shortly, with estimated completion date of January 2024.

    Visitor Information Centre building

    Construction set to commence shortly, with estimated completion date of January 2024.

  • Building Bonds and Breaking Stigma

    Share Building Bonds and Breaking Stigma on Facebook Share Building Bonds and Breaking Stigma on Twitter Share Building Bonds and Breaking Stigma on Linkedin Email Building Bonds and Breaking Stigma link
    The Lismore Memorial Baths became more than just a construction site this week as Bennett Constructions with assistance from Konnect Fastening Systems hosted a special barbecue to commemorate two vital causes – R U OK?Day and MATES in Construction.


    The Baths transformed into a hub of unity, support and camaraderie as Council staff, local contractors and construction workers gathered for the event.
    R U OK Day is a reminder that a simple question can make a world of difference. While Mates in Construction addresses the high level of suicide within the Australian construction industry.


    The barbecue emphasised that it's okay not to be okay, and seeking help and support is a sign of strength, not weakness.


  • Council Welcomes $15 million grant funding announcement

    Share Council Welcomes $15 million grant funding announcement on Facebook Share Council Welcomes $15 million grant funding announcement on Twitter Share Council Welcomes $15 million grant funding announcement on Linkedin Email Council Welcomes $15 million grant funding announcement link

    Lismore City Council has welcomed the State and Federal Government’s announcement of grants totalling $15 million to assists Lismore’s City Hall and, arts and cultural sector as they continue to rebuild after the February 2022 natural disaster.

    Mayor Steve Krieg said the announcement was great news for the community and will allow popular services like the library and art gallery to continue to provide services while their buildings are being repaired, as well as delivering flood resilience and functionality enhancements to Lismore City Hall.

    “This is great news for the entire community, including library users and our arts community,” he said.

    “Our community has missed City Hall, the Lismore Library and the Regional Art Gallery since the natural disaster and these grants are a significant step in Lismore’s rebuild.

    “I would like to thank local State Member Janelle Saffin and Federal Member for Page Kevin Hogan for their assistance in getting these important grants.”

    About $8 million of the total package will go to community organisations within the local government area, with Council receiving almost $7 million, which comprises of:

    • $5.2 million for Lismore City Hall flood mitigation and sustainable improvements
    • $177,240 for the Lismore Library to create a meeting and workshop space at Lismore Central Shopping Centre, and
    • $1.3 million for the continuation of the Pop-Up Regional Art Gallery and office space in Magellan Street.

    Member for Lismore Janelle Saffin said the rebuilding is vitally important to help re-open arts, cultural and community spaces.

    “They are at the very heart of community life,” she said.

    “We rely on our galleries, museums and cultural hubs to revive our spirits and tell our stories and they are critical to the identity of our cities and towns.

    “Investing in these spaces is about investing in the future of our communities so they can flourish.”

    Member for Page Kevin Hogan said the grants will play a role in our recovery.

    “The restoration of our civic buildings after the floods is an important stage of the recovery and the creation of cultural facilities and activities is essential to restoring our community wellbeing,” he said.

    “I look forward to the work commencing.”

    The projects were successful through the second round of the Community Local Infrastructure Recovery Package – Arts and Cultural Assets Program, designed to support medium to long-term recovery under the Commonwealth-State Disaster Recovery Funding Arrangements.

  • Project Updates - August 2023

    Share Project Updates - August 2023 on Facebook Share Project Updates - August 2023 on Twitter Share Project Updates - August 2023 on Linkedin Email Project Updates - August 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Crozier/Oakes Oval: The site fencing from Dawson Street to Magellan Street blocks is up. Showcasing that works are commencing with managing contractor Bennett Constructions.


    Dawson Street Toilet Block: The roof structure has commenced. The temporary toilet blocks have been delivered and ready for use, near the Dawson Street block.


    Elaine Blanch Tennis Courts Clubhouse: Demolition works were completed in the Tennis Club including slab and internal wall removal. Demolition is underway on the training wall. Preliminary works for drainage have been completed, with exploratory dig and camera survey of the sewer lines to ensure the new drainage is configured correctly.


    Lismore Memorial Baths: Another step forward for the Lismore Memorial Baths, as the old solar heating tubes were removed from the facilities roof.
    A crane delicately removed these damaged tubes, making way for the upcoming roof replacement set to take place over the coming weeks.


    Lismore Basketball Association: Onsite meeting with stakeholders to discuss choice of flooring, and future works.

    Marie Mackney Netball Clubhouse: Preliminary works for drainage works. Exploratory dig and camera survey of the sewer lines to make sure we are connecting the new drainage correctly. Drainage to the Ground Floor wet areas has been completed awaiting council inspection. The Level 1 ply flooring is being removed and progressively being replaced with Scyon flooring. And structural repairs to the framing are underway.


    Mortimer Oval Container Building: Roof post footings have been poured, and scaffolding has been erected to commence the roof structure.

  • Lismore Memorial Baths - July 2023

    Share Lismore Memorial Baths - July 2023 on Facebook Share Lismore Memorial Baths - July 2023 on Twitter Share Lismore Memorial Baths - July 2023 on Linkedin Email Lismore Memorial Baths - July 2023 link

    Planning is underway to restore the Memorial Baths ready for Summer. While there are still challenges to reach this goal, early dewatering of the pool to enable hydraulic investigations has commenced. In addition, orders for long lead time mechanical equipment have been placed.

    Draining the pool of water is a complex operation that if not done correctly could lead to the pool lifting out of position. Our team spent considerable effort in the planning phase to ensure this didn’t happen, including rolling out a number of contingency plans.
    Council’s Water and Wastewater team successfully repaired the downstream sewer connection to allow draining to occur. As water levels fell, Bennett Constructions was able to clean the sides of the pool.

    Swimplex Aquatics have been contracted to partner with Bennett Constructions to complete the works.

    The fences surrounding the site will also be receiving a creative and colourful update, displaying artworks from 10 local artists as part of The Creative Fencing Project. To read more on this project, take a look at Lismore Regional Gallery's post.

Page last updated: 21 Apr 2024, 07:57 PM