Category Mortimer Oval (Container Building)   Show all

  • Project Updates - September 2023

    Share Project Updates - September 2023 on Facebook Share Project Updates - September 2023 on Twitter Share Project Updates - September 2023 on Linkedin Email Project Updates - September 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Brunswick Street Depot - Old Helicopter Building

    Construction set to commence shortly, with estimated completion date of January 2024.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Onsite meeting with South Lismore Celtics representatives, to inform the design of the future rebuild suited to needs of the club.

    Crozier and Oakes Oval Amenities (Dawson Street and Magellan Street Toilets)

    The roof structure on both the Dawson and Magellan Street blocks commenced in September. Scyon flooring sheeting was laid and the plumbing rough-in completed. The structural steel roof framing to three buildings is now complete and the new Colorbond roof sheeting installed. Translucent roof sheeting was added to increase natural lighting within the building. Painting commenced at the Dawson Street block.

    Perimeter scaffolding will be removed shortly.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts)

    The existing training wall was demolished this month, requiring a rebuild due to extensive damage to the brickwork. By the end of the month, blockwork for the new wall was complete.

    Preliminary drainage works were also started and by mid-month, drainage was completed for the ground floor wet areas. Prep-work for the ground floor slab reinstatement has also commenced. Service rough-ins for security, electrical and plumbing are now complete.

    Lismore Airport Terminal

    Construction on the Terminal building set to commence shortly, with estimated completion date of January 2024.

    Lismore Library

    Onsite meeting with Library stakeholders to inform the design of future rebuild. Decisions on colour and fit out materials are now being made.

    Additionally, the Library received funding to continue offering pop-up spaces.

    Lismore Memorial Baths

    It was busy at the Baths in September. The last of the shade sails on the pool deck were pressure cleaned.

    All redundant solar tube systems and heat pumps were removed from the Amenities Block, lifeguard tower and the pump room roof in preparation for the new roof installation. Old roof and insulation was removed from the Amenities Block, before the new roof and insulation is installed.

    The Canteen fitout is underway, with a new grease arrest and hydraulic pipework installed. Plumbing, gas and electrical rough-ins has also commenced in all buildings. Work is also underway in the Amenities room including fixtures and plumbing rough-in of showers.

    The Baths also hosted the Mates in Construction Fly The Flag Breaky BBQ, which was a great success!

    The Pavilion was rendered and painting will continue through October.

    Laurie Allan Centre

    Onsite meeting with the Far North Coast Canoe Club representatives, to discuss future plans for the building, and their immediate needs in relation to the space.

    Lismore Municipal Building

    Onsite meeting with Richmond River Historical Society representatives, to inform the design of the future rebuild suited to needs of the user group.

    Lismore Regional Gallery

    Review of scope and grant funding with Project Team. Restoration for The Quad will now be completed in conjunction with Gallery works.

    Mortimer Oval Amenities

    In early September the roof structure was started with roof post footings being poured, roof sheeting and flashing installed. The roof structure was finished just in time for month end. Flooring was laid and power restored to the entire building. Resilient finishes were ordered and awaiting delivery.

    Marie Mackney Netball Courts (Lismore Netball)

    Drainage works, termite treatments and ground prep for the slab reinstatement had commenced and the Scyon flooring installed to the first floor.

    The external soffit was also completed and by the end of the month the service rough-ins underway and the internal wall framing complete.

    The goal was to have the clubhouse ready for September. However a number of challenges were faced and now aiming for completion at the end of October.

    Radio Controlled Car Building - Nesbitt Park

    Construction set to commence shortly, with estimated completion date of January 2024.

    Riverview Park

    Discus nets have been completed. Construction on clubhouse set to commence shortly, with estimated completion date of January 2024.

    Visitor Information Centre building

    Construction set to commence shortly, with estimated completion date of January 2024.

  • Project Updates - August 2023

    Share Project Updates - August 2023 on Facebook Share Project Updates - August 2023 on Twitter Share Project Updates - August 2023 on Linkedin Email Project Updates - August 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Crozier/Oakes Oval: The site fencing from Dawson Street to Magellan Street blocks is up. Showcasing that works are commencing with managing contractor Bennett Constructions.


    Dawson Street Toilet Block: The roof structure has commenced. The temporary toilet blocks have been delivered and ready for use, near the Dawson Street block.


    Elaine Blanch Tennis Courts Clubhouse: Demolition works were completed in the Tennis Club including slab and internal wall removal. Demolition is underway on the training wall. Preliminary works for drainage have been completed, with exploratory dig and camera survey of the sewer lines to ensure the new drainage is configured correctly.


    Lismore Memorial Baths: Another step forward for the Lismore Memorial Baths, as the old solar heating tubes were removed from the facilities roof.
    A crane delicately removed these damaged tubes, making way for the upcoming roof replacement set to take place over the coming weeks.


    Lismore Basketball Association: Onsite meeting with stakeholders to discuss choice of flooring, and future works.

    Marie Mackney Netball Clubhouse: Preliminary works for drainage works. Exploratory dig and camera survey of the sewer lines to make sure we are connecting the new drainage correctly. Drainage to the Ground Floor wet areas has been completed awaiting council inspection. The Level 1 ply flooring is being removed and progressively being replaced with Scyon flooring. And structural repairs to the framing are underway.


    Mortimer Oval Container Building: Roof post footings have been poured, and scaffolding has been erected to commence the roof structure.

  • Buildings and Facilities Update - November 2022

    Share Buildings and Facilities Update - November 2022 on Facebook Share Buildings and Facilities Update - November 2022 on Twitter Share Buildings and Facilities Update - November 2022 on Linkedin Email Buildings and Facilities Update - November 2022 link

    Albert Park Baseball Restoration works continue across the baseball fields and clubhouse & amenities. Validation report identified further areas of detailed cleaning required within the clubhouse which is being actioned to obtain certificate of validation. Batting cage replacement is currently being quoted.

    Arthur Park Archery ClubScope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Brunswick Street DepotSign shop, Fab shop and Workshop are operational. Temporary offices are in place until restoration works are complete. Contractor has been engaged for demountable office restoration. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Caniaba Street Reserve - Soccer Clubhouse Hygienist certificate of validation received. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Clyde Campbell CarparkPatching across the carpark has been completed. A scope of works and estimation of costs for severely damaged area behind Mary G’s has been submitted to Public Works Advisory for approval.

    Croquet Club, Spinks Park - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    CWA Building, Spinks ParkDecontamination works continuing – planned to be completed Mid-November. Repairs to damaged heritage tile roof are scheduled. A scope of works is developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Family Support Network (Old Scout Hall – 41 Wilston St, South Lismore)Structural assessment complete. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Harold Fredricks Carpark LightsReplacement solar lights for this carpark have been procured. Awaiting arrival for installation.

    Humbley Oval Hockey Club KioskSite isolated via temporary fencing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    John Crowther CarparkAfter being utilised as a temporary waste transfer station this carpark has now had resurfacing works and is available again for public use.

    Laurie Allen CentreGeotechnical Drilling contractor engaged to get samples to assist in the structural assessment of this building.

    Lismore Airport Terminal - Hygienist certificate of validation received. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Basketball Association Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Centra Tourist ParkPark is operational. Final restoration works on new office building is being complete.

    Lismore Cattle Sale YardsReplacement sales office designed and Development Application submitted. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore City Hall - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Library - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation. Structural Drying still on-going to maintain moisture levels. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Memorial BathsAquatic Engineer site visit complete and awaiting on final report on water treatment system. Scope of works developed and estimation of costs of restoration works has been developed. Following outcome of Aquatic engineers assessment of water treatment system a submission for Community Recreation & Cultural Asset works required will be submitted to Public Works Advisory for approval.

    Lismore Park Elaine Blanche Tennis Courts (Lismore Tennis Courts) ClubhouseHygienist validation sampling complete, awaiting results of reporting. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Lismore Regional Gallery - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore SES HeadquartersCouncil has been working closely with SES to minimise any disruption during the replacement of floor coverings that were inundated in the February 2022 flood. This work is ongoing and is scheduled to be finished by end of November.

    Lismore Transit Centre The Transit Centre re-opened to the public on Monday 17/10/22 as a Recovery Centre and Assistance point. Minor restoration works continue throughout November as materials/supplies become available.

    Marie Mackney Netball Clubhouse (Lismore Netball Courts) Hazardous building materials have been removed. Structural drying is ongoing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Mortimer Oval (Brick Building) - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Mortimer Oval (Container Building) Tender for the replacement of the roof structure has closed with successful tenderer selected. Scope of works developed for remaining works and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Municipal Building - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Richmond River Historical Society contents safely relocated to a flood free location whilst restoration works on the municipal building are complete.

    Oakes Oval (Gordan Pavilion) - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Old Helicopter Building Electrical, Data and Fire systems restoration has commenced. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Richards Oval Clubhouse (Lismore Workers Clubhouse) - Hazardous building materials have been removed. Structural drying is ongoing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Stock Pot Kitchen (Old Art Gallery) Stock Pot Kitchen is open to the public. Please see their social media for details on opening hours. The Old Art Gallery’s site restoration is ongoing. A scope of works is developed, and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Visitor Information Centre - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works is developed, and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.