Category Brunswick Street Depot   Show all

  • Project Updates - March 2024

    Share Project Updates - March 2024 on Facebook Share Project Updates - March 2024 on Twitter Share Project Updates - March 2024 on Linkedin Email Project Updates - March 2024 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)(External link)

    Arthur Park Archery Club

    Works commencing in April 2024.

    Brunswick Street Depot - Old Helicopter Building - Completed

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    External painting, club signage, changerooms and amenities were all completed.

    The canteen and Level 1 kitchen received finishing touches, with external stairs to be installed early April.

    Cedar Log Shed

    Costing and design for roof structure.

    CWA Building

    Ceiling work underway in the main hall and blockwork began on the extension. The concrete slab for wet areas is progressing, with tiling and services fit off to commence when sheeting is completed.

    Lismore Airport Terminal

    Early March saw the terminal floor finishes and Hearing Augmentation Loop installed and preparation for the generator lift underway.

    External works included pressure-cleaning and external conduit and trenching works progressing. By end of March, joinery and all service fit offs were nearing completion, and the generator was lifted to its new position. Aiming for completion of Stage 1 – early April.

    Lismore Basketball Association

    Subgrade earth works were underway to the gymnasium floor. The screw piles installation commenced, and was completed by the end of March.

    The waffle pod system (underfloor) was delivered and installed. The steel cages and the slab reinforcement also completed, underfloor finalised by completion of the concrete pours.

    Lismore Cattle Saleyards

    Works to commence mid-April. Focusing on the pedestrian walkway and replacement of damaged fencing.

    Lismore City Hall

    Design investigations relating to AV, Stage fit-out, Electrical, Mechanical and Hydraulics works progressing.

    Demolition continued, including external tile removal and internal brick wall removal and will continue in the coming weeks once the new design is approved. By the end of the month, investigation of a roof access system was being carried out and non-loadbearing wall removal was underway, and materials loaded out.

    Lismore Library

    Mid-March saw the establishment of the site and temporary power set up. The scaffold loading bay was installed and the rendering commenced on the ground floor.

    Lismore Municipal Building

    Strip out of all old services and rectification to the brickworks underway.

    Rendering to internal areas commenced and the parapet rectifications were in progress.

    Lismore Regional Gallery

    In early March, works on the ground floor consisted of lining of the wet areas and ceilings.

    Glazing installations in the Northern and Southern Walkways progressed. External cladding replacement was also underway.

    Level 1 works included wall and ceiling linings and skirting installation underway (set and sand). Plantroom deck works included waterproofing, and the replacement of a new Chiller and A/C condenser.

    Richards Oval Soccer Clubhouse (Workers FC)

    Tiling and painting underway and the rough-in almost complete. By the end of March, the epoxy flooring was complete, permanent power re-connected to the building and first floor tiling and fit off nearing completion.

    The Clubhouse is on track for completion in April, allowing for gates to be added to scope of works.

    Riverview Park

    Design of upcoming Accessible Toilet/Changeroom Block progressed.

    The Quad

    Temporary covered walkway constructed – ready for works to begin. Walkway access for pedestrians will remain, ensuring access between Harold Fredericks Carpark and Keen Street.

    Visitor Information Centre building

    Setting and timber trims nearing completion and the main switchboard fit off commenced.

    Towards the end of the month, painting was nearing completion with only Level 2 and one wall on Level 1 to go. The lighting fit-off was completed on both ground floor and Level 1. The spiral duct installation complete and skylights installed. Security and mechanical fit offs and joinery (reception desk/kitchenette) all well underway.

    Ground floor toilets re-opened, seeing the temporary toilets removed. Carpet and final joinery installation will mark the completion of this project in early April.


    Lease agreements are underway for the following buildings, ensuring the successful handover to community. The public notices will be available on the Your Say homepage for public comment.

    CWA Building - 115 Molesworth Street

    Lismore Park Elaine Blanch Tennis Courts (Lismore Tennis Courts) - 82 Ballina Road

    Lismore RSL Sub-Branch - 179 Molesworth Street

    Municipal Building - 165 Molesworth Street

    The following are scheduled for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage. Dates listed below are estimated, pending project progress, available trades/services and favourable weather.
    If you have any concerns or questions about the demolition of these buildings, please contact floodrestoration@lismore.nsw.gov.au

    Family Support Network - Old Scout Hall

    Demolition to proceed - June 2024

    Lismore Lake Buildings

    Demolition to proceed for toilet block and pumphouse - April 2024
    New modular toilet to be constructed (separate future project)

    Sam Trimble Oval Amenities

    Demolition to proceed - weatherboard building - May 2024
    Brick building to be refurbed
    A new modular toilet is to be constructed (separate future project)

    Humbley Oval Hockey Club Kiosk

    Demolition to proceed - May 2024

    Old Essential Energy Building

    Corner Ballina Road and Conway St - April 2024
    Demolition to proceed

    Neilson Park Canteen Building, East Lismore

    Demolition to proceed - May 2024
    A new modular toilet is to be constructed (separate future project)

    McKenzie Park Amenities, North Lismore

    Demolition to proceed - May 2024
    A new modular toilet is to be constructed (separate future project)

    Wade Park, East Lismore

    A new modular toilet is to be constructed, or temporary facilities established, before demolition will proceed. - June 2024

  • Project Updates - December 2023/January 2024

    Share Project Updates - December 2023/January 2024 on Facebook Share Project Updates - December 2023/January 2024 on Twitter Share Project Updates - December 2023/January 2024 on Linkedin Email Project Updates - December 2023/January 2024 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)

    Completed by the end of 2023

    Albert Park Baseball

    Croquet Clubhouse

    Brunswick Street Depot

    Elaine Blanche Tennis Courts Clubhouse

    Lismore Memorial Baths

    Marie Mackney Netball Clubhouse

    Mortimer Oval Container Building

    Mortimer Oval Brick Building

    Oakes/Crozier Amenities

    Radio Controlled Car Building - Nesbitt Park

    Brunswick Street Depot - Old Helicopter Building

    Internal stairs have been built, and floor coverings installed.

    In the workshop, painting has been completed and AC equipment installed. External cladding is in progress.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.

    Lismore Airport Terminal

    All services rough ins completed during December. The mechanical condenser was replaced, the outdoor PAC unit and 3 x fan coil units installed. Geotech testing of the external generator location was conducted. Linings and insulation of internal walls has commenced.

    Lismore Basketball Association

    Site set up ready for works to replace the subfloor commence in January.

    Lismore Cattle Saleyards

    List of restoration priorities being determined with stakeholders. Scheduling of works to be determined in line with sale activities.

    Lismore City Hall

    Site set up complete, ready for works to commence in January.

    Lismore CWA Building

    Site set up and works to commence in January.

    Lismore Municipal Building

    Onsite meeting with stakeholders to inform accessibility in the design of the ground floor.

    Lismore Regional Gallery

    At the beginning of December, the solar panels were removed from the roof and the NBN fibre was installed. The laying of CFC flooring to L1 was completed and scaffolding erected to the North, East and West sides of external elevations. Roof sheets were delivered in early January which will be installed late January due to weather conditions. Internal cement rendering and repair of ground floor walls underway and the demolition strip-out of internal load bearing walls and kitchen benches are complete.

    Mortimer Oval Amenities

    Internal and external works now complete. Landscaping to be completed, which will finalise restoration for the end of January.

    Richards Oval Soccer Clubhouse (Workers FC)

    Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.

    Riverview Park

    Stage 1 – Completed 20/12/23 and the building handed back to the user group.

    Stage 2 – Field lighting and PA installation - nearing completion

    The Quad

    To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.

    Visitor Information Centre building

    Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.


  • Project Updates - November 2023

    Share Project Updates - November 2023 on Facebook Share Project Updates - November 2023 on Twitter Share Project Updates - November 2023 on Linkedin Email Project Updates - November 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Brunswick Street Depot - Old Helicopter Building

    Service rough ins, ceiling lining and floor preparation for vinyl covering have commenced. Handrail posts were installed and the main frame to the second level also in place.

    Doors were installed, tiling underway and balustrades arrived late November. By the end of November, 90% of the plastering had been completed. Laying of the vinyl flooring and internal painting is now well underway.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Mood board and 90% plans have been approved by stakeholders. Container moved onsite for storage ahead of works commencing in January.

    Crozier and Oakes Oval Amenities (Dawson Street and Magellan Street Toilets)

    Restoration and handover has been completed for all amenities blocks. Works on the ticket booth at Oakes will now progress.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts)

    Restoration completed, with final inspection scheduled for Wednesday 29 November. Celebration of the key handover and completion of works is scheduled for December 14.

    Laurie Allan Centre

    Immediate restoration works including deep cleaning, lighting and hot water were completed. Handover to Far North Coast Canoe has been finalised. Additional longer term works are still being scoped and reviewed.

    Lismore Airport Terminal

    Site establishment was completed early November. Mechanical and electrical preliminary make safe had commenced. Hydraulics investigation was conducted and a clean out and rough in was completed. Procurement for mechanical, electrical and hydraulics was completed.

    Towards the end of November, mechanical pipework rough ins had commenced, and the electrical and data security rough ins had commenced.

    Lismore Basketball Association

    Meeting held with stakeholders to discuss site set up ahead of January 2024 start to replace the flooring.

    Lismore City Hall

    Storage containers onsite in preparation for early works to commence in December.

    Lismore CWA Building

    Scope of works increased, to incorporate additional roofing requirements. Works scheduled to commence in January. Estimated completion date is March 2024.

    Lismore Lake Buildings

    Meeting held with stakeholders to discuss scope of works.

    Lismore Library

    Estimated start February 2024. Slight schedule changes to accommodate Lismore Regional Gallery, The Quad and Lismore Library being completed concurrently.

    Lismore Memorial Baths

    The Pools were filled and filter system activated. With power restored, tiling, painting and cleaning including the cleaning of the 50m pool commenced.

    Installation of the mod wood slat seating in the Grandstand and landscaping also commenced. Preparing for a December 2023 opening.

    Lismore Municipal Building

    Estimated start February 2024.

    Lismore Regional Gallery

    During November, site was established. Temporary power had been installed and isolation of the solar panels carried out. Early strip out and make safe was completed, by the end of the month the ceiling in Level 1 was stripped out and removed. Design was completed with procurement of trades well underway.

    Mortimer Oval Amenities

    Restoration and handover complete on the Container Building. User groups have been notified, ready to prepare for next season.

    Site establishment was completed for the Brick Building. Demolition complete and rendering well underway. Plumbing including roofing works commenced at the end of November.

    Marie Mackney Netball Courts (Lismore Netball)

    Flooring, painting (internal and external) and electrical fit off were all completed in November.

    Towards the end of November, the stainless-steel benches and roller doors were installed and all fit offs by service trades (electrical, plumbing and security) were well underway. Final inspection has been completed, awaiting handover with user group.

    Radio Controlled Car Building - Nesbitt Park

    Completed, finalising handover to user group.

    Richards Oval Soccer Clubhouse (Workers FC)

    Meeting held with stakeholders to discuss 90% design and colour options. Mood board and 90% plans have been approved by stakeholders. Container moved onsite for storage ahead of works commencing in January.

    Riverview Park

    Works have begun with site establishment complete, and the redundant shower block demolished.

    The Quad

    To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.

    Visitor Information Centre building

    Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.

  • Project Updates - September 2023

    Share Project Updates - September 2023 on Facebook Share Project Updates - September 2023 on Twitter Share Project Updates - September 2023 on Linkedin Email Project Updates - September 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Brunswick Street Depot - Old Helicopter Building

    Construction set to commence shortly, with estimated completion date of January 2024.

    Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

    Onsite meeting with South Lismore Celtics representatives, to inform the design of the future rebuild suited to needs of the club.

    Crozier and Oakes Oval Amenities (Dawson Street and Magellan Street Toilets)

    The roof structure on both the Dawson and Magellan Street blocks commenced in September. Scyon flooring sheeting was laid and the plumbing rough-in completed. The structural steel roof framing to three buildings is now complete and the new Colorbond roof sheeting installed. Translucent roof sheeting was added to increase natural lighting within the building. Painting commenced at the Dawson Street block.

    Perimeter scaffolding will be removed shortly.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts)

    The existing training wall was demolished this month, requiring a rebuild due to extensive damage to the brickwork. By the end of the month, blockwork for the new wall was complete.

    Preliminary drainage works were also started and by mid-month, drainage was completed for the ground floor wet areas. Prep-work for the ground floor slab reinstatement has also commenced. Service rough-ins for security, electrical and plumbing are now complete.

    Lismore Airport Terminal

    Construction on the Terminal building set to commence shortly, with estimated completion date of January 2024.

    Lismore Library

    Onsite meeting with Library stakeholders to inform the design of future rebuild. Decisions on colour and fit out materials are now being made.

    Additionally, the Library received funding to continue offering pop-up spaces.

    Lismore Memorial Baths

    It was busy at the Baths in September. The last of the shade sails on the pool deck were pressure cleaned.

    All redundant solar tube systems and heat pumps were removed from the Amenities Block, lifeguard tower and the pump room roof in preparation for the new roof installation. Old roof and insulation was removed from the Amenities Block, before the new roof and insulation is installed.

    The Canteen fitout is underway, with a new grease arrest and hydraulic pipework installed. Plumbing, gas and electrical rough-ins has also commenced in all buildings. Work is also underway in the Amenities room including fixtures and plumbing rough-in of showers.

    The Baths also hosted the Mates in Construction Fly The Flag Breaky BBQ, which was a great success!

    The Pavilion was rendered and painting will continue through October.

    Laurie Allan Centre

    Onsite meeting with the Far North Coast Canoe Club representatives, to discuss future plans for the building, and their immediate needs in relation to the space.

    Lismore Municipal Building

    Onsite meeting with Richmond River Historical Society representatives, to inform the design of the future rebuild suited to needs of the user group.

    Lismore Regional Gallery

    Review of scope and grant funding with Project Team. Restoration for The Quad will now be completed in conjunction with Gallery works.

    Mortimer Oval Amenities

    In early September the roof structure was started with roof post footings being poured, roof sheeting and flashing installed. The roof structure was finished just in time for month end. Flooring was laid and power restored to the entire building. Resilient finishes were ordered and awaiting delivery.

    Marie Mackney Netball Courts (Lismore Netball)

    Drainage works, termite treatments and ground prep for the slab reinstatement had commenced and the Scyon flooring installed to the first floor.

    The external soffit was also completed and by the end of the month the service rough-ins underway and the internal wall framing complete.

    The goal was to have the clubhouse ready for September. However a number of challenges were faced and now aiming for completion at the end of October.

    Radio Controlled Car Building - Nesbitt Park

    Construction set to commence shortly, with estimated completion date of January 2024.

    Riverview Park

    Discus nets have been completed. Construction on clubhouse set to commence shortly, with estimated completion date of January 2024.

    Visitor Information Centre building

    Construction set to commence shortly, with estimated completion date of January 2024.

  • Project Updates - August 2023

    Share Project Updates - August 2023 on Facebook Share Project Updates - August 2023 on Twitter Share Project Updates - August 2023 on Linkedin Email Project Updates - August 2023 link

    There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month.

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au

    Crozier/Oakes Oval: The site fencing from Dawson Street to Magellan Street blocks is up. Showcasing that works are commencing with managing contractor Bennett Constructions.


    Dawson Street Toilet Block: The roof structure has commenced. The temporary toilet blocks have been delivered and ready for use, near the Dawson Street block.


    Elaine Blanch Tennis Courts Clubhouse: Demolition works were completed in the Tennis Club including slab and internal wall removal. Demolition is underway on the training wall. Preliminary works for drainage have been completed, with exploratory dig and camera survey of the sewer lines to ensure the new drainage is configured correctly.


    Lismore Memorial Baths: Another step forward for the Lismore Memorial Baths, as the old solar heating tubes were removed from the facilities roof.
    A crane delicately removed these damaged tubes, making way for the upcoming roof replacement set to take place over the coming weeks.


    Lismore Basketball Association: Onsite meeting with stakeholders to discuss choice of flooring, and future works.

    Marie Mackney Netball Clubhouse: Preliminary works for drainage works. Exploratory dig and camera survey of the sewer lines to make sure we are connecting the new drainage correctly. Drainage to the Ground Floor wet areas has been completed awaiting council inspection. The Level 1 ply flooring is being removed and progressively being replaced with Scyon flooring. And structural repairs to the framing are underway.


    Mortimer Oval Container Building: Roof post footings have been poured, and scaffolding has been erected to commence the roof structure.

  • Buildings and Facilities Update - November 2022

    Share Buildings and Facilities Update - November 2022 on Facebook Share Buildings and Facilities Update - November 2022 on Twitter Share Buildings and Facilities Update - November 2022 on Linkedin Email Buildings and Facilities Update - November 2022 link

    Albert Park Baseball Restoration works continue across the baseball fields and clubhouse & amenities. Validation report identified further areas of detailed cleaning required within the clubhouse which is being actioned to obtain certificate of validation. Batting cage replacement is currently being quoted.

    Arthur Park Archery ClubScope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Brunswick Street DepotSign shop, Fab shop and Workshop are operational. Temporary offices are in place until restoration works are complete. Contractor has been engaged for demountable office restoration. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Caniaba Street Reserve - Soccer Clubhouse Hygienist certificate of validation received. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Clyde Campbell CarparkPatching across the carpark has been completed. A scope of works and estimation of costs for severely damaged area behind Mary G’s has been submitted to Public Works Advisory for approval.

    Croquet Club, Spinks Park - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    CWA Building, Spinks ParkDecontamination works continuing – planned to be completed Mid-November. Repairs to damaged heritage tile roof are scheduled. A scope of works is developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Family Support Network (Old Scout Hall – 41 Wilston St, South Lismore)Structural assessment complete. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Harold Fredricks Carpark LightsReplacement solar lights for this carpark have been procured. Awaiting arrival for installation.

    Humbley Oval Hockey Club KioskSite isolated via temporary fencing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    John Crowther CarparkAfter being utilised as a temporary waste transfer station this carpark has now had resurfacing works and is available again for public use.

    Laurie Allen CentreGeotechnical Drilling contractor engaged to get samples to assist in the structural assessment of this building.

    Lismore Airport Terminal - Hygienist certificate of validation received. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Basketball Association Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Centra Tourist ParkPark is operational. Final restoration works on new office building is being complete.

    Lismore Cattle Sale YardsReplacement sales office designed and Development Application submitted. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore City Hall - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Library - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation. Structural Drying still on-going to maintain moisture levels. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore Memorial BathsAquatic Engineer site visit complete and awaiting on final report on water treatment system. Scope of works developed and estimation of costs of restoration works has been developed. Following outcome of Aquatic engineers assessment of water treatment system a submission for Community Recreation & Cultural Asset works required will be submitted to Public Works Advisory for approval.

    Lismore Park Elaine Blanche Tennis Courts (Lismore Tennis Courts) ClubhouseHygienist validation sampling complete, awaiting results of reporting. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Lismore Regional Gallery - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Lismore SES HeadquartersCouncil has been working closely with SES to minimise any disruption during the replacement of floor coverings that were inundated in the February 2022 flood. This work is ongoing and is scheduled to be finished by end of November.

    Lismore Transit Centre The Transit Centre re-opened to the public on Monday 17/10/22 as a Recovery Centre and Assistance point. Minor restoration works continue throughout November as materials/supplies become available.

    Marie Mackney Netball Clubhouse (Lismore Netball Courts) Hazardous building materials have been removed. Structural drying is ongoing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Mortimer Oval (Brick Building) - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Mortimer Oval (Container Building) Tender for the replacement of the roof structure has closed with successful tenderer selected. Scope of works developed for remaining works and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Municipal Building - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset approval.

    Richmond River Historical Society contents safely relocated to a flood free location whilst restoration works on the municipal building are complete.

    Oakes Oval (Gordan Pavilion) - Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Old Helicopter Building Electrical, Data and Fire systems restoration has commenced. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Richards Oval Clubhouse (Lismore Workers Clubhouse) - Hazardous building materials have been removed. Structural drying is ongoing. Scope of works developed and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Stock Pot Kitchen (Old Art Gallery) Stock Pot Kitchen is open to the public. Please see their social media for details on opening hours. The Old Art Gallery’s site restoration is ongoing. A scope of works is developed, and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

    Visitor Information Centre - Hygienist validation sampling complete, awaiting results of reporting for certificate of validation and/or detailed areas of cleaning required. Scope of works is developed, and estimation of costs submitted to Public Works Advisory for Community Recreation & Cultural Asset Works approval.

  • Buildings and Facilities Update - September 2022

    Share Buildings and Facilities Update - September 2022 on Facebook Share Buildings and Facilities Update - September 2022 on Twitter Share Buildings and Facilities Update - September 2022 on Linkedin Email Buildings and Facilities Update - September 2022 link

    It's been a busy month as restoration works continue across Council’s buildings, parks and facilities. Below you will find updates on the progress being made at Council’s Buildings, as well as some quick updates on Parks and Public toilets that required restorative works.

    Albert Park Baseball - Strip out and clean of clubhouse and amenities has been completed. Electricity due to be reconnected during September.

    Arthur Park Archery Club - Assessment report has been completed, with scope of works currently under review.

    Gundurimba Building – Carpentry work is underway to restore this building. Heritage Consultants were engaged prior to the commencement of restoration works.

    Brunswick Street Depot – Electrical restoration works to be completed throughout September.

    Caniaba Street Reserve - Soccer Clubhouse – Awaiting final assessment report from hygienist before restoration works commence.

    Cedar Log Shed - Scope of works is currently being assessed for this building.

    Central Tourist Park – Construction of new office building to replace existing flood damaged building commenced. Minor concreting works complete.

    City Hall - First floor strip out of flood damaged building materials and electrical components is underway. Followed by cleaning and assessment for scope of works. Grand piano is currently undergoing mould remediation and storage with local specialised contractor.

    Croquet Club – Electrical restoration works have commenced. Heritage Consultants have been engaged to contribute to the scope of works required to this building.

    CWA Building - Decontamination contractor (to prevent mould) will commence mid-September. Heritage Consultants have been engaged to contribute to the scope of works required to this building.

    ELGAS - ELGAS Station still operational. Offices and stores buildings are being replaced, with design for new buildings determined in collaboration with the tenant. Fencing has been repaired and/or replaced.

    Gordon Pavilion (Oakes Oval) – Oakes/Crozier Sports Hub upgrades are progressing. Gordon Pavilion cleaning and decontamination works have been finalised. The grounds of Oakes/Crozier Oval are open.

    Laurie Allen Centre - Building is currently closed to the public. Removal of flood damaged building material and electrical components has been completed. Building requires specialist structural assessment before commencing restoration works.

    Lismore Basketball Association - Design works are currently underway in collaboration with Lismore Basketball Association for replacement of flooring.

    Lismore Airport Terminal – BOM weather station has been restored. Aeronautical instrumentation replacement is progressing. Specialist contractor has removed flood damaged airport security screening equipment. Restoration works on terminal to progress once Scope of Works required is finalised.

    Lismore Cattle Sale Yards – Structural assessment has been completed. Final design of office building being reviewed in collaboration with tenants.

    Lismore Lake Buildings - Restoration works have commenced with the removal of flood damaged structures.

    Lismore Library – Structural drying is currently underway. Components to repair elevator have been ordered. Heritage Consultants have been engaged to contribute to the scope of works required to this building.

    Lismore Memorial Baths – Clean and decontamination works have been finalised. Heritage Consultants have been engaged to contribute to the scope of works required to this facility and assessment of the pool’s pumps for restoration, replacement or elevating for future flood proofing is being considered to form part of the works required at this facility.

    Lismore Park Elaine Blanche Tennis Courts (Lismore Tennis Courts) – Tennis courts are open. Clubhouse is awaiting final validation of moisture levels before restoration works can commence. Temporary toilets are available at this facility for users.

    Lismore Pipe Band Building – Flood damage assessment has been completed. Clean and decontamination contractors to be engaged for this building.

    Lismore Preschool – Lismore Preschool is completing restoration works directly. Please refer to their social media for further updates.

    Lismore Regional Gallery -. Final detailed clean is underway, with reporting for validation of building to be done once complete. Scope of works required for the building restoration is being developed.

    Lismore SES Headquarters - Open and operational.

    Lismore Transit Centre – Restoration of the roof structure has been completed, with solar hot water system to be installed shortly. Full restoration works are currently underway for replacement of kitchen, public toilets, and amenities including disabled toilets and showers.

    Marie Mackney Netball Clubhouse (Lismore Netball Courts) - Specialist subcontractor has been engaged to assist with removal of hazardous building materials from this building. Temporary toilets are available at this facility for users.

    Mortimer Oval New Building - Validation sampling of building complete with report forthcoming. The design of a new roof structure is being finalised.

    Mortimer Oval Old Building – Building currently structurally drying. Restoration works to follow.

    Municipal Building, Old Council Chambers – Heritage Consultants have been engaged to contribute to the scope of works required to this building. Clean and decontamination works for prevention of mould is ongoing.

    Old Helicopter Building - Electrical, data and fire system contractors have commenced restoration works.

    Radio Controlled Car Building - Nesbitt Park - Works to remove flood damaged building materials and cleaning is underway. Replacement of RC Tracks boundary fencing is progressing with procurement process started.

    Riverview Park Clubhouse and Canteen – Restoration of the boundary fencing of Riverview Park underway. Clubhouse and Canteen are completing drying before validation can be obtained.

    Richards Oval - Workers Soccer Clubhouse – Removal of flood damaged building and electoral components complete. Structural drying underway to be followed by validation report.

    Terania Building – Restoration works for electrical and plumbing have commenced, with electricity being reconnected. ACE Community Colleges are re-locating from the Terania building on Magellan St to Suite 4, Level 1 29 Molesworth Street from October 2022. Please follow their social media for further updates on exact opening dates.

    Visitor Information Centre - Closed to public until restoration works are complete, structural drying has been completed. Toilets are operational and open to the public. May require intermittent closure to complete necessary works, temporary services will be available.

  • Buildings and Facilities Update - August 2022

    Share Buildings and Facilities Update - August 2022 on Facebook Share Buildings and Facilities Update - August 2022 on Twitter Share Buildings and Facilities Update - August 2022 on Linkedin Email Buildings and Facilities Update - August 2022 link

    There are a number of Flood Restoration works being completed. Please see below updates on some of the projects shared for this month. Council asks members of the community to exercise caution around any of these sites and abide by temporary exclusion fences/barriers.

    Updates on specific projects can be found by selecting 'Projects By Name' as found on the right side of the main article (Desktop) or scrolling to the bottom of the article page (Mobile).

    If there is a project you would like particular updates on, please utilise the Q+A function of the main article.

    Terania Building - Structural drying to be completed, followed by restoration works.

    Albert Park Baseball - Strip out and clean of Clubhouse and Amenities commenced mid-July, expected to take two weeks. Pathway cleaning, plus removal of flood damaged storage sheds has been completed. The fencing has been removed and stored for re-use.

    Arthur Park Archery Club - Scope of works to be determined, pending Assessment Report.

    Gundurimba Building - Cleaning and structural drying completed. Painting has commenced, carpentry work expected to commence mid-August.

    Brunswick Street Depot - Workshop and Fabrication shop are operational. Temporary offices are in place until restoration works are completed.

    Caniaba Street Reserve - Soccer Clubhouse - Strip out, removal of flood damaged building material and electrical components, plus cleaning and structural drying have been completed. Restoration works to following pending validation report.

    Cedar Log Shed - Scope of works is currently being assessed.

    Central Tourist Park - Essential services have been restored. Restoration works of specific buildings are ongoing.

    City Hall - Removal of flood damaged building material and electrical components completed on the Ground Floor. Clean, decontamination (to prevent mould) and structural drying has commenced. First Floor strip out has commenced.

    Croquet Club - Building assessed. Building restoration works to commence pending current contractor procurement.

    CWA Building - Decontamination (to prevent mould) expected to commence mid September, with restoration works to follow. Temporary structural bracing has been installed.

    ELGAS - ELGAS Station still operational. Removal of flood damaged building material and electrical components of the office and parts store have been completed. Restoration works are currently being scoped.

    Gordon Pavilion (Oakes Oval) - Facility upgrades have recommenced. Cleaning has been completed and restoration works are underway. The grounds of Oakes/Crozier Oval are open.

    Laurie Allen Centre - Building is currently closed to the public. Removal of flood damaged building material and electrical components has been completed. Building requires specialist structural assessment before commencing restoration works.

    Lismore Basketball Association - Design works are currently underway for replacement of flooring.

    Lismore Airport Terminal - Structural drying of the building has been completed, restoration works to follow.

    Lismore Cattle Sale Yards - Initial assessment completed on sale yards, further structural assessment required on octagonal sales ring and office. Restoration works to follow on finalisation of structural assessment.

    Lismore Lake Buildings - Removal of flood damaged building material and electrical components on the pump shed will begin in August. Restoration works to follow.

    Lismore Library - Following paint strip out, a final detailed clean will be completed by end of August. Once completed, structural drying will take place over a four week period.

    Lismore Memorial Baths - Removal of flood damaged building material and electrical components, plus cleaning of office buildings completed and change rooms are ongoing. Pool has been de-sludged, pool surrounds and equipment approaching completion. New security fence has been erected, with further restoration works to follow.

    Elaine Blanch Tennis Courts (Lismore Tennis Courts) - Cleaning of the courts is completed. Clubhouse undergoing structural drying, before commencing restoration works.

    Lismore Pipe Band Building - Damage assessment and repair scoping underway.

    Lismore Preschool - Damage assessment and repair scoping underway.

    Lismore Regional Gallery - Strip out, removal of flood damaged building material and electrical components is complete. A final detail and clean is underway. Up to 4 weeks structural drying required prior to restoration commencing.

    Lismore SES Headquarters - Open and operational. Minor restoration works and final cleaning to be completed.

    Lismore Transit Centre - Structural drying scheduled to be completed in August. Restoration works to follow to repair building for public use.

    Marie Mackney Netball Clubhouse (Lismore Netball Courts) - Removal of flood damaged building material and electrical components is ongoing. Specialist subcontractor has been engaged to assist with these works.

    Mortimer Oval New Building - Strip out of damaged flooring and detailed cleaning complete. Validation report and roof design underway.

    Mortimer Oval Old Building - Removal of flood damaged building material nearing completion. Restoration works to commence.

    Municipal Building, Old Council Chambers - Building closed to public, museum staff removing and cleaning artefacts with the assistance of the Contractor onsite. Ground Floor flood damaged material removal commenced by specialist subcontractor. Clean and decontamination (to prevent mould) of First Floor to be completed by September.

    Old Helicopter Building - Structural drying complete, with restoration to follow pending validation reporting. Electrical, data and fire system contractors have been engaged to commence restoration works.

    Radio Controlled Car Building - Nesbitt Park - Works to remove building materials and cleaning is underway.

    Riverview Park Clubhouse and Canteen - Initial cleaning has been completed. Structural drying is now underway.

    Richards Oval - Workers Soccer Clubhouse - Strip out, removal of flood damaged building material underway pending specialist contractor.

    Visitor Information Centre - Closed to public until restoration works are complete, structural drying has been completed. Toilets are operational and open to the public. May require intermittent closure to complete necessary works, temporary services will be available.