Project Updates - March 2024

There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.

If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)(External link)

Arthur Park Archery Club

Works commencing in April 2024.

Brunswick Street Depot - Old Helicopter Building - Completed

Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)

External painting, club signage, changerooms and amenities were all completed.

The canteen and Level 1 kitchen received finishing touches, with external stairs to be installed early April.

Cedar Log Shed

Costing and design for roof structure.

CWA Building

Ceiling work underway in the main hall and blockwork began on the extension. The concrete slab for wet areas is progressing, with tiling and services fit off to commence when sheeting is completed.

Lismore Airport Terminal

Early March saw the terminal floor finishes and Hearing Augmentation Loop installed and preparation for the generator lift underway.

External works included pressure-cleaning and external conduit and trenching works progressing. By end of March, joinery and all service fit offs were nearing completion, and the generator was lifted to its new position. Aiming for completion of Stage 1 – early April.

Lismore Basketball Association

Subgrade earth works were underway to the gymnasium floor. The screw piles installation commenced, and was completed by the end of March.

The waffle pod system (underfloor) was delivered and installed. The steel cages and the slab reinforcement also completed, underfloor finalised by completion of the concrete pours.

Lismore Cattle Saleyards

Works to commence mid-April. Focusing on the pedestrian walkway and replacement of damaged fencing.

Lismore City Hall

Design investigations relating to AV, Stage fit-out, Electrical, Mechanical and Hydraulics works progressing.

Demolition continued, including external tile removal and internal brick wall removal and will continue in the coming weeks once the new design is approved. By the end of the month, investigation of a roof access system was being carried out and non-loadbearing wall removal was underway, and materials loaded out.

Lismore Library

Mid-March saw the establishment of the site and temporary power set up. The scaffold loading bay was installed and the rendering commenced on the ground floor.

Lismore Municipal Building

Strip out of all old services and rectification to the brickworks underway.

Rendering to internal areas commenced and the parapet rectifications were in progress.

Lismore Regional Gallery

In early March, works on the ground floor consisted of lining of the wet areas and ceilings.

Glazing installations in the Northern and Southern Walkways progressed. External cladding replacement was also underway.

Level 1 works included wall and ceiling linings and skirting installation underway (set and sand). Plantroom deck works included waterproofing, and the replacement of a new Chiller and A/C condenser.

Richards Oval Soccer Clubhouse (Workers FC)

Tiling and painting underway and the rough-in almost complete. By the end of March, the epoxy flooring was complete, permanent power re-connected to the building and first floor tiling and fit off nearing completion.

The Clubhouse is on track for completion in April, allowing for gates to be added to scope of works.

Riverview Park

Design of upcoming Accessible Toilet/Changeroom Block progressed.

The Quad

Temporary covered walkway constructed – ready for works to begin. Walkway access for pedestrians will remain, ensuring access between Harold Fredericks Carpark and Keen Street.

Visitor Information Centre building

Setting and timber trims nearing completion and the main switchboard fit off commenced.

Towards the end of the month, painting was nearing completion with only Level 2 and one wall on Level 1 to go. The lighting fit-off was completed on both ground floor and Level 1. The spiral duct installation complete and skylights installed. Security and mechanical fit offs and joinery (reception desk/kitchenette) all well underway.

Ground floor toilets re-opened, seeing the temporary toilets removed. Carpet and final joinery installation will mark the completion of this project in early April.


Lease agreements are underway for the following buildings, ensuring the successful handover to community. The public notices will be available on the Your Say homepage for public comment.

CWA Building - 115 Molesworth Street

Lismore Park Elaine Blanch Tennis Courts (Lismore Tennis Courts) - 82 Ballina Road

Lismore RSL Sub-Branch - 179 Molesworth Street

Municipal Building - 165 Molesworth Street

The following are scheduled for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage. Dates listed below are estimated, pending project progress, available trades/services and favourable weather.
If you have any concerns or questions about the demolition of these buildings, please contact floodrestoration@lismore.nsw.gov.au

Family Support Network - Old Scout Hall

Demolition to proceed - June 2024

Lismore Lake Buildings

Demolition to proceed for toilet block and pumphouse - April 2024
New modular toilet to be constructed (separate future project)

Sam Trimble Oval Amenities

Demolition to proceed - weatherboard building - May 2024
Brick building to be refurbed
A new modular toilet is to be constructed (separate future project)

Humbley Oval Hockey Club Kiosk

Demolition to proceed - May 2024

Old Essential Energy Building

Corner Ballina Road and Conway St - April 2024
Demolition to proceed

Neilson Park Canteen Building, East Lismore

Demolition to proceed - May 2024
A new modular toilet is to be constructed (separate future project)

McKenzie Park Amenities, North Lismore

Demolition to proceed - May 2024
A new modular toilet is to be constructed (separate future project)

Wade Park, East Lismore

A new modular toilet is to be constructed, or temporary facilities established, before demolition will proceed. - June 2024

Categories: Arthur Park Archery Club, Brunswick Street Depot, Caniaba Street Reserve - Soccer Clubhouse, Cedar Log Shed, Lismore CWA Building, Lismore Airport Terminal, Lismore Basketball Association, Lismore Cattle Sale Yards, Lismore City Hall, Lismore Library, Municipal Building, Lismore Regional Gallery, Richards Oval - Workers Soccer Clubhouse, Richards Oval Clubhouse (Lismore Workers Clubhouse), Richards Oval Soccer Clubhouse (Workers FC), Riverview Park Clubhouse, The Quad, Visitor Information Centre
Share Project Updates - March 2024 on Facebook Share Project Updates - March 2024 on Twitter Share Project Updates - March 2024 on Linkedin Email Project Updates - March 2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>