Project Updates - December 2023/January 2024
There are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)
Completed by the end of 2023
Albert Park Baseball
Croquet Clubhouse
Brunswick Street Depot
Elaine Blanche Tennis Courts Clubhouse
Lismore Memorial Baths
Marie Mackney Netball Clubhouse
Mortimer Oval Container Building
Mortimer Oval Brick Building
Oakes/Crozier Amenities
Radio Controlled Car Building - Nesbitt Park
Brunswick Street Depot - Old Helicopter Building
Internal stairs have been built, and floor coverings installed.
In the workshop, painting has been completed and AC equipment installed. External cladding is in progress.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)
Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.
Lismore Airport Terminal
All services rough ins completed during December. The mechanical condenser was replaced, the outdoor PAC unit and 3 x fan coil units installed. Geotech testing of the external generator location was conducted. Linings and insulation of internal walls has commenced.
Lismore Basketball Association
Site set up ready for works to replace the subfloor commence in January.
Lismore Cattle Saleyards
List of restoration priorities being determined with stakeholders. Scheduling of works to be determined in line with sale activities.
Lismore City Hall
Site set up complete, ready for works to commence in January.
Lismore CWA Building
Site set up and works to commence in January.
Lismore Municipal Building
Onsite meeting with stakeholders to inform accessibility in the design of the ground floor.
Lismore Regional Gallery
At the beginning of December, the solar panels were removed from the roof and the NBN fibre was installed. The laying of CFC flooring to L1 was completed and scaffolding erected to the North, East and West sides of external elevations. Roof sheets were delivered in early January which will be installed late January due to weather conditions. Internal cement rendering and repair of ground floor walls underway and the demolition strip-out of internal load bearing walls and kitchen benches are complete.
Mortimer Oval Amenities
Internal and external works now complete. Landscaping to be completed, which will finalise restoration for the end of January.
Richards Oval Soccer Clubhouse (Workers FC)
Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.
Riverview Park
Stage 1 – Completed 20/12/23 and the building handed back to the user group.
Stage 2 – Field lighting and PA installation - nearing completion
The Quad
To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.
Visitor Information Centre building
Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.