Category Lismore Municipal Building Show all
-
Project Updates - August 2024
Share Project Updates - August 2024 on Facebook Share Project Updates - August 2024 on Twitter Share Project Updates - August 2024 on Linkedin Email Project Updates - August 2024 linkThe Flood Restoration Portfolio is a crucial component of Lismore's strategy for community recovery. Across the city, numerous building and facility restoration projects are ongoing, each at different stages — from active work to completed enhancements. These projects are essential for revitalizing critical community assets, aiming not only to restore them to their former state but also to improve their resilience and sustainability against future adversities.
This update provides insights into the progress made on key projects during August. Lismore City Council, in partnership with its managing contractor, Bennett Construction, has achieved significant milestones: 33 projects have been completed, 10 are currently in progress, and 4 are set to commence shortly. Below, you will find updates on the major ongoing and recently completed projects.
For more specific details on any project, please refer to the Q+A section of the main article or contact the Council directly at council@lismore.nsw.gov.au
Ongoing Projects
Lismore Library
The Lismore Library has seen considerable advancements in August, with the erection of scaffolding along Magellan Street marking a significant phase of the project. Interior and exterior painting has been successfully completed, enhancing the aesthetic of the building. Concurrently, essential services such as plumbing and electrical mains are being fitted and fire safety improvements are progressing well towards completion. The library's entrance roofing and arch bar replacement works are actively underway, contributing to the overall structural enhancements of the facility.
The QUAD
The QUAD's development experienced a temporary slowdown due to inclement weather conditions in August. However, the return of favourable weather conditions allowed rapid progress, with the turfing successfully completed and concrete slabs honed to achieve a polished finish. Comprehensive concreting, tiling, and landscaping efforts in both the northern and southern areas of the QUAD were completed by the end of the month. The final steps involve top dressing and nurturing the newly laid grass to establish a robust ground cover.
Lismore Regional Gallery
The Lismore Regional Gallery underwent significant internal developments, with the construction of partition walls and ceilings. All service installations, including inground and rough-ins across various areas, were completed, laying the groundwork for operational functionalities. The reception and kitchen areas received wall sheeting, setting, and the application of a rock coat render finish at the reception entrance. By month's end, the café floor was sealed, and kitchen tiling along with epoxy flooring were fully completed, marking the readiness of these spaces for use. The Regional Gallery is on track for its reopening ceremony on 27 September 2024.
Lismore Regional Airport
At the Lismore Regional Airport, substantial structural developments were noted with the ongoing installation of the Porte Cochere's structural steel. Excavation activities for new grounds lighting progressed, alongside the removal of old carpark lights to a storage area, making way for modern infrastructure. Earthworks continued with trenching for lighting footings and silt fencing containment. The airport's carpark civil works were a focal point, culminating in the completion of new kerb and gutter installations and the addition of Porte Cochere roof flashings by the end of August.
Lismore Municipal Building
The Lismore Municipal Building saw significant progress with the completion of service rough-ins and the first concrete pour for the ground floor slab. Corbel repairs were well underway, enhancing the building's architectural integrity. Stair rectification efforts continued with notable progress, including the application of the first coat of stain. The framing around the main room's AC unit was finalized, ready for sheeting, as efforts to finish corbel detailing by Rofe Rendering were completed, ensuring the building's readiness for further interior development.Complete Works
Cattle Sale Yards
The Cattle Sale Yards project reached completion at the end of August, with all planned works finished. This completion marks a significant achievement in the project timeline, setting a benchmark for efficiency and project management within the overall portfolio.
Lismore City Hall – Stage 1
City Hall experienced a series of enabling works, but progress has been curtailed due to funding constraints. Despite the site's demobilization, detailed designs and a comprehensive cost plan for its restoration and improvement have been completed and received. Council is working with various State Government funding agencies to commence Stage 2 (construction and refurbishment) as soon as possible. -
Project Updates - July 2024
Share Project Updates - July 2024 on Facebook Share Project Updates - July 2024 on Twitter Share Project Updates - July 2024 on Linkedin Email Project Updates - July 2024 linkThe Flood Restoration Portfolio is central to Lismore's community recovery efforts. Across the city, numerous building and facility restoration projects are actively underway or have been completed, playing a crucial role in rejuvenating essential community assets. This ongoing work is focused not only on bringing facilities back to their original state but also on enhancing their resilience and sustainability to better face future challenges.
This July update details progress through June and July on several key projects. For more specific information on any project, feel free to use the Q+A feature of the main article or contact the Council directly at council@lismore.nsw.gov.au.
Ongoing ProjectsLismore Library
During June, significant progress was made on the Lismore Library. Construction activities included the installation of wall sheeting in wet areas and progress in electrical, plumbing, air conditioning, and other rough-ins. Floor tiles were removed, and new timber flooring began installation, with the laying of battens and ply towards month's end. Window repairs and internal painting commenced, and air conditioning units were installed on the roof. Installation of timber floors and painting are currently underway. Progress is also being made on various service trades.
Lismore Regional Airport
At the Lismore Regional Airport, work is progressing on several fronts. The Porte Cochere roof soffit has been removed, and abrasive blasting of the structural steel is underway. Additionally, the old structural steel is being replaced with new roof purlins. Power systems have been updated, and the plans and approvals for Stage 2 are almost complete. Excavation and electrical work for upgrading the car park lighting are also ongoing.
The Quad
At The Quad, there was significant focus on concrete work, involving extensive excavation and removal of spoil from both The Quad and the Northern Terrace. Sub-soil systems were installed, and by the end of the month, preparations for new concrete slabs were complete. Paving and the installation of new storm water trunk lines in The Quad area were finished. Concrete was poured in both the western and northern areas, preparing them for final touches with sand and topsoil. Further enhancements included the delivery of bulk topsoil and the start of landscaping and furniture setups. Concrete pouring continued on the Northern Terrace and in the Southern Quad, with tiling also progressing on the Northern Terrace.Cattle Sale Yards
Recent developments have included the removal of fencing and the completion of landscaping.Municipal Building
Work on the Municipal Building advanced with continued external parapet works. Flooring demolition began to make way for the new concrete floor. Render on architraves advanced, and concrete pours for bathroom and foyer areas were completed. Doorways were resized with new concrete lintels installed.
Completed ProjectsStock’s Park (Cedar Log)
All planned works for this site have been finalised early in the month.
Lismore City Hall - Stage 1
Early works at the Lismore City Hall site included completing Stage 1 footings and blockwork, which were core-filled. The setup of stage 2 footings, columns, and block walls, along with the installation of structural beams, progressed. Adjustments to props allowed for the next stages of work, with blockwork and column installations completed by late June. Stage 1 has been successfully completed, with preparations underway for the initiation of Stage 2.
Netball - Stage 2
All scheduled works for Stage 2 have been completed, marking the project as finished for this phase.
Lismore Basketball Association
The project was completed with a handover meeting officially conducted on June 9th.
CWA Building
In June, the CWA Building saw the completion of finishing touches, culminating in a final walkthrough and handover. This update highlights the significant progress and completion of various restoration projects, showcasing the ongoing recovery efforts in the Lismore community.
Demolition Projects in June:- Sam Trimble Oval
- Humbley Oval
- Family Support Network – Old Scout Hall
-
Project Updates - April 2024
Share Project Updates - April 2024 on Facebook Share Project Updates - April 2024 on Twitter Share Project Updates - April 2024 on Linkedin Email Project Updates - April 2024 linkThere are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)
Arthur Park Archery Club - Completed, and handed over to stakeholder user group.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics) - Completed, and handed over to stakeholder user group.
Cedar Log Shed
Scope of works being reviewed, due to commence works in May.
CWA Building
Extension was framed, ready for roof works. External painting, tiling and trade services has commenced. Joinery underway, with rendering of internal walls almost complete.
Lismore Airport Terminal
Stage 1 of the Terminal works was completed early April. Planning and pricing for Stage 2 is underway and Stage 3 comprising of the airside works are in planning.
Lismore Basketball Association
The concrete slab was completed, with the moisture barrier applied to the slab and water stop installed around the perimeter of the building. The subfloor was completed by the end of the month, with timber floor laid aid for acclimatisation. Padded walls have been built ready for installation, and the new grandstand is being manufactured. The driveway and footpath have also been installed.
Lismore Cattle Saleyards
Sub-contractors confirmed, works to commence at the end of May.
Lismore City Hall
Non-load bearing wall removal has been completed. Props have been installed for the next phase of load bearing wall removal. Site clean-up conducted with removal of demolition rubble and other waste materials.
Final design discussed with stakeholders, to return the building to a thriving multi-purpose arts and culture precinct.
Lismore Library
Fire rating to ground floor beams and rendering of the walls is underway.
The ground floor concreting received a smooth finish through a process called 'white setting', ready for floor topping to be completed.
All services trades are now ready to commence.
Lismore Municipal Building
Corbel (type of structural and decorative wall bracket) demolition, cement rendering and provisions for light cabling are all underway. Timber and subfloor works are in design and bricklaying is progressing. External works to parapet are ongoing.
Heritage of the Municipal Building being maintained is a high priority, and contractors are taking care with works to suit.
Lismore Regional Gallery
Gallery floors have been resurfaced and sealed. Tiling to wet areas is well underway and internal painting has progressed.
Vinyl to Level 1 and Bathrooms were also finished by the end of the month.
Richards Oval Soccer Clubhouse (Workers FC) - Completed, and handed over to stakeholder user group.
Riverview Park
Design of upcoming Accessible Toilet/Changeroom Block has been confirmed. Works to commence in May.
The Quad
Works progressing. Design was discussed with various stakeholders to include additional infrastructure to improve amenity and use of the restored space.
Visitor Information Centre building
Carpet and vinyl coverings were installed. Final painting and service fit offs were also completed.
These were the final works, ready for completion and handover.
The following are scheduled for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage. Dates listed below are estimated, pending project progress, available trades/services and favourable weather.
If you have any concerns or questions about the demolition of these buildings, please contact floodrestoration@lismore.nsw.gov.au(External link)Family Support Network - Old Scout Hall
Demolition to proceed - June 2024
Lismore Lake Buildings
Demolition to proceed for toilet block and pumphouse - May 2024
New modular toilet to be constructed (separate future project)Sam Trimble Oval Amenities
Demolition to proceed - weatherboard building - June 2024
Brick building to be refurbed
A new modular toilet is to be constructed (separate future project)Humbley Oval Hockey Club Kiosk
Demolition to proceed - May 2024
Old Essential Energy Building
Demolition complete. Works to clean up and close out the site will be completed in May.
Neilson Park Canteen Building, East Lismore
Demolition to proceed - May 2024
A new modular toilet is to be constructed (separate future project)McKenzie Park Amenities, North Lismore
Demolition to proceed - May 2024
A new modular toilet is to be constructed (separate future project)Wade Park, East Lismore
A new modular toilet is to be constructed, or temporary facilities established, before demolition will proceed. - June 2024
-
Project Updates - February 2024
Share Project Updates - February 2024 on Facebook Share Project Updates - February 2024 on Twitter Share Project Updates - February 2024 on Linkedin Email Project Updates - February 2024 linkThere are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)(External link)
Arthur Park Archery Club
Finalising costing to progress works. Currently scheduled to be completed in April 2024.
Brunswick Street Depot - Old Helicopter Building
Nearing completion, with painting of first floor offices and additional drainage added.
Site pack down commenced, as final defects and stakeholder requirements are addressed, costed and completed.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)
Demolition and tile removal was completed, ready for waterproofing and retiling to commence.
Level 1 linings and carpentry was completed, ready for internal and external painting which was completed by the end of the month.
Changerooms, amenities and kitchen nearing completion, ready for fit out.
Cedar Log Shed
In design review to address extensive damage to the roof structure, with a focus on future flood resilience.
CWA Building
Onsite meeting with stakeholders to discuss kitchen fit out, scope of works, final designs and construction underway.
Lismore Airport Terminal
Slab and fitting of the generator was completed.
Inside the Terminal, walls were set and internal painting commenced. Finishes such as skirting, tiling, toilet partitions and high access cleaning were carried out. Automatic doors, flooring and bathroom fit off were completed also.
The Terminal is on track to be completed by the end of March 2024.
Lismore Basketball Association
Entry point in the side brick wall has been established, for easy equipment and machinery access.
Padded walls removed and safely stored, ready for floor demolition to commence.Lismore Cattle Saleyards
Onsite meeting with stakeholders to discuss working collaboratively and utilising local contractors to complete confirmed scope of works, including walkway, ramps and some fencing.
Lismore City Hall
Demolition works are well underway, including tile and slab removal through the kitchen and wet areas.
Level 3 old cabling was removed, ready for installation of temporary switchboards and lighting. The southern walkway floor reinstatement was also completed, lights reinstated and concrete beams propped ready for brickwork removal on Level 1.
Lismore Municipal Building
Scaffolding and site set up complete.
Onsite meeting with existing stakeholders earlier in the month to confirm scope of works, and gather additional insight to progress with a proposal to make the ground floor all accessibility friendly.
Lismore Regional Gallery
The roof replacement and solar panel installation have been completed. External wall cladding, service rough ins and walls and ceilings are underway.
Southern walkways were a focus with removal of glazing and frames, with window frame installation also commencing.
New electrical mains cable rough ins, soffits and fan coil units for Level 1 will be completed shortly, ready to finalise wall linings, ceilings and insulation.
Mortimer Oval Amenities
Completed and ready for community handover.
Richards Oval Soccer Clubhouse (Workers FC)
First floor demolition completed, with demolition of the ground floor to commence.
Sheeting, rough ins, pipework replacement, plastering, door jams and trims were all underway by the end of the month.
Riverview Park
Onsite meeting with stakeholder to address defects and requirements, ensuring space is fit for purpose.
Confirmed design of upcoming Accessible Toilet/Changeroom Block to be based next to the undercover area.
The Quad
Site set up and fencing commenced. Walkway access for pedestrians will remain, ensuring access between Harold Fredericks Carpark and Keen Street.
Visitor Information Centre building
Wall linings and sheeting completed, with door hangings and timber trims all underway.
External works include gutter replacement and gutter guard installation. Site clean up has begun, with the removal of scaffolding. Estimated completion in March 2024.
Lease agreements are underway for the following buildings, ensuring the successful handover to community. The public notices will be available on the Your Say homepage for public comment.
Caniaba Street Reserve - Soccer Clubhouse (Celtics FC) - 2 Caniaba Street
CWA Building - 115 Molesworth Street
Lismore Park Elaine Blanch Tennis Courts (Lismore Tennis Courts) - 82 Ballina Road
Lismore RSL Sub-Branch - 179 Molesworth Street
Municipal Building - 165 Molesworth Street
Richards Oval Soccer Clubhouse (Workers FC) - 48B & 48I Brewster Street
The following are being proposed for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage.
Family Support Network - Old Scout Hall - 41 Wilson Street, South Lismore
Humbley Oval Hockey Club Kiosk - Cnr of Brewster and Uralba Street, Lismore
Laurie Allen Centre, The Rowing Club - Molesworth Street. Top two levels only, basement building currently in use.
Lismore Lake Buildings - the old pumphouse and toilet block next to the pool site. Proposal for the toilet block to be demolished and replaced, pending available funding.
Sam Trimble Oval Amenities - Proposal for the toilet block to be demolished and replaced, pending available funding.
-
Project Updates - December 2023/January 2024
Share Project Updates - December 2023/January 2024 on Facebook Share Project Updates - December 2023/January 2024 on Twitter Share Project Updates - December 2023/January 2024 on Linkedin Email Project Updates - December 2023/January 2024 linkThere are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)
Completed by the end of 2023
Albert Park Baseball
Croquet Clubhouse
Brunswick Street Depot
Elaine Blanche Tennis Courts Clubhouse
Lismore Memorial Baths
Marie Mackney Netball Clubhouse
Mortimer Oval Container Building
Mortimer Oval Brick Building
Oakes/Crozier Amenities
Radio Controlled Car Building - Nesbitt Park
Brunswick Street Depot - Old Helicopter Building
Internal stairs have been built, and floor coverings installed.
In the workshop, painting has been completed and AC equipment installed. External cladding is in progress.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)
Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.
Lismore Airport Terminal
All services rough ins completed during December. The mechanical condenser was replaced, the outdoor PAC unit and 3 x fan coil units installed. Geotech testing of the external generator location was conducted. Linings and insulation of internal walls has commenced.
Lismore Basketball Association
Site set up ready for works to replace the subfloor commence in January.
Lismore Cattle Saleyards
List of restoration priorities being determined with stakeholders. Scheduling of works to be determined in line with sale activities.
Lismore City Hall
Site set up complete, ready for works to commence in January.
Lismore CWA Building
Site set up and works to commence in January.
Lismore Municipal Building
Onsite meeting with stakeholders to inform accessibility in the design of the ground floor.
Lismore Regional Gallery
At the beginning of December, the solar panels were removed from the roof and the NBN fibre was installed. The laying of CFC flooring to L1 was completed and scaffolding erected to the North, East and West sides of external elevations. Roof sheets were delivered in early January which will be installed late January due to weather conditions. Internal cement rendering and repair of ground floor walls underway and the demolition strip-out of internal load bearing walls and kitchen benches are complete.
Mortimer Oval Amenities
Internal and external works now complete. Landscaping to be completed, which will finalise restoration for the end of January.
Richards Oval Soccer Clubhouse (Workers FC)
Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.
Riverview Park
Stage 1 – Completed 20/12/23 and the building handed back to the user group.
Stage 2 – Field lighting and PA installation - nearing completion
The Quad
To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.
Visitor Information Centre building
Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.