Project Updates - April 2024
Share Project Updates - April 2024 on Facebook Share Project Updates - April 2024 on Twitter Share Project Updates - April 2024 on Linkedin Email Project Updates - April 2024 linkThere are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)
Arthur Park Archery Club - Completed, and handed over to stakeholder user group.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics) - Completed, and handed over to stakeholder user group.
Cedar Log Shed
Scope of works being reviewed, due to commence works in May.
CWA Building
Extension was framed, ready for roof works. External painting, tiling and trade services has commenced. Joinery underway, with rendering of internal walls almost complete.
Lismore Airport Terminal
Stage 1 of the Terminal works was completed early April. Planning and pricing for Stage 2 is underway and Stage 3 comprising of the airside works are in planning.
Lismore Basketball Association
The concrete slab was completed, with the moisture barrier applied to the slab and water stop installed around the perimeter of the building. The subfloor was completed by the end of the month, with timber floor laid aid for acclimatisation. Padded walls have been built ready for installation, and the new grandstand is being manufactured. The driveway and footpath have also been installed.
Lismore Cattle Saleyards
Sub-contractors confirmed, works to commence at the end of May.
Lismore City Hall
Non-load bearing wall removal has been completed. Props have been installed for the next phase of load bearing wall removal. Site clean-up conducted with removal of demolition rubble and other waste materials.
Final design discussed with stakeholders, to return the building to a thriving multi-purpose arts and culture precinct.
Lismore Library
Fire rating to ground floor beams and rendering of the walls is underway.
The ground floor concreting received a smooth finish through a process called 'white setting', ready for floor topping to be completed.
All services trades are now ready to commence.
Lismore Municipal Building
Corbel (type of structural and decorative wall bracket) demolition, cement rendering and provisions for light cabling are all underway. Timber and subfloor works are in design and bricklaying is progressing. External works to parapet are ongoing.
Heritage of the Municipal Building being maintained is a high priority, and contractors are taking care with works to suit.
Lismore Regional Gallery
Gallery floors have been resurfaced and sealed. Tiling to wet areas is well underway and internal painting has progressed.
Vinyl to Level 1 and Bathrooms were also finished by the end of the month.
Richards Oval Soccer Clubhouse (Workers FC) - Completed, and handed over to stakeholder user group.
Riverview Park
Design of upcoming Accessible Toilet/Changeroom Block has been confirmed. Works to commence in May.
The Quad
Works progressing. Design was discussed with various stakeholders to include additional infrastructure to improve amenity and use of the restored space.
Visitor Information Centre building
Carpet and vinyl coverings were installed. Final painting and service fit offs were also completed.
These were the final works, ready for completion and handover.
The following are scheduled for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage. Dates listed below are estimated, pending project progress, available trades/services and favourable weather.
If you have any concerns or questions about the demolition of these buildings, please contact floodrestoration@lismore.nsw.gov.au(External link)Family Support Network - Old Scout Hall
Demolition to proceed - June 2024
Lismore Lake Buildings
Demolition to proceed for toilet block and pumphouse - May 2024
New modular toilet to be constructed (separate future project)Sam Trimble Oval Amenities
Demolition to proceed - weatherboard building - June 2024
Brick building to be refurbed
A new modular toilet is to be constructed (separate future project)Humbley Oval Hockey Club Kiosk
Demolition to proceed - May 2024
Old Essential Energy Building
Demolition complete. Works to clean up and close out the site will be completed in May.
Neilson Park Canteen Building, East Lismore
Demolition to proceed - May 2024
A new modular toilet is to be constructed (separate future project)McKenzie Park Amenities, North Lismore
Demolition to proceed - May 2024
A new modular toilet is to be constructed (separate future project)Wade Park, East Lismore
A new modular toilet is to be constructed, or temporary facilities established, before demolition will proceed. - June 2024
-
Project Updates - February 2024
Share Project Updates - February 2024 on Facebook Share Project Updates - February 2024 on Twitter Share Project Updates - February 2024 on Linkedin Email Project Updates - February 2024 linkThere are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)(External link)
Arthur Park Archery Club
Finalising costing to progress works. Currently scheduled to be completed in April 2024.
Brunswick Street Depot - Old Helicopter Building
Nearing completion, with painting of first floor offices and additional drainage added.
Site pack down commenced, as final defects and stakeholder requirements are addressed, costed and completed.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)
Demolition and tile removal was completed, ready for waterproofing and retiling to commence.
Level 1 linings and carpentry was completed, ready for internal and external painting which was completed by the end of the month.
Changerooms, amenities and kitchen nearing completion, ready for fit out.
Cedar Log Shed
In design review to address extensive damage to the roof structure, with a focus on future flood resilience.
CWA Building
Onsite meeting with stakeholders to discuss kitchen fit out, scope of works, final designs and construction underway.
Lismore Airport Terminal
Slab and fitting of the generator was completed.
Inside the Terminal, walls were set and internal painting commenced. Finishes such as skirting, tiling, toilet partitions and high access cleaning were carried out. Automatic doors, flooring and bathroom fit off were completed also.
The Terminal is on track to be completed by the end of March 2024.
Lismore Basketball Association
Entry point in the side brick wall has been established, for easy equipment and machinery access.
Padded walls removed and safely stored, ready for floor demolition to commence.Lismore Cattle Saleyards
Onsite meeting with stakeholders to discuss working collaboratively and utilising local contractors to complete confirmed scope of works, including walkway, ramps and some fencing.
Lismore City Hall
Demolition works are well underway, including tile and slab removal through the kitchen and wet areas.
Level 3 old cabling was removed, ready for installation of temporary switchboards and lighting. The southern walkway floor reinstatement was also completed, lights reinstated and concrete beams propped ready for brickwork removal on Level 1.
Lismore Municipal Building
Scaffolding and site set up complete.
Onsite meeting with existing stakeholders earlier in the month to confirm scope of works, and gather additional insight to progress with a proposal to make the ground floor all accessibility friendly.
Lismore Regional Gallery
The roof replacement and solar panel installation have been completed. External wall cladding, service rough ins and walls and ceilings are underway.
Southern walkways were a focus with removal of glazing and frames, with window frame installation also commencing.
New electrical mains cable rough ins, soffits and fan coil units for Level 1 will be completed shortly, ready to finalise wall linings, ceilings and insulation.
Mortimer Oval Amenities
Completed and ready for community handover.
Richards Oval Soccer Clubhouse (Workers FC)
First floor demolition completed, with demolition of the ground floor to commence.
Sheeting, rough ins, pipework replacement, plastering, door jams and trims were all underway by the end of the month.
Riverview Park
Onsite meeting with stakeholder to address defects and requirements, ensuring space is fit for purpose.
Confirmed design of upcoming Accessible Toilet/Changeroom Block to be based next to the undercover area.
The Quad
Site set up and fencing commenced. Walkway access for pedestrians will remain, ensuring access between Harold Fredericks Carpark and Keen Street.
Visitor Information Centre building
Wall linings and sheeting completed, with door hangings and timber trims all underway.
External works include gutter replacement and gutter guard installation. Site clean up has begun, with the removal of scaffolding. Estimated completion in March 2024.
Lease agreements are underway for the following buildings, ensuring the successful handover to community. The public notices will be available on the Your Say homepage for public comment.
Caniaba Street Reserve - Soccer Clubhouse (Celtics FC) - 2 Caniaba Street
CWA Building - 115 Molesworth Street
Lismore Park Elaine Blanch Tennis Courts (Lismore Tennis Courts) - 82 Ballina Road
Lismore RSL Sub-Branch - 179 Molesworth Street
Municipal Building - 165 Molesworth Street
Richards Oval Soccer Clubhouse (Workers FC) - 48B & 48I Brewster Street
The following are being proposed for demolition, due to a number of considerations including structural damage, potential hazards and safety risk to the public, cost of repair and community usage.
Family Support Network - Old Scout Hall - 41 Wilson Street, South Lismore
Humbley Oval Hockey Club Kiosk - Cnr of Brewster and Uralba Street, Lismore
Laurie Allen Centre, The Rowing Club - Molesworth Street. Top two levels only, basement building currently in use.
Lismore Lake Buildings - the old pumphouse and toilet block next to the pool site. Proposal for the toilet block to be demolished and replaced, pending available funding.
Sam Trimble Oval Amenities - Proposal for the toilet block to be demolished and replaced, pending available funding.
-
Project Updates - December 2023/January 2024
Share Project Updates - December 2023/January 2024 on Facebook Share Project Updates - December 2023/January 2024 on Twitter Share Project Updates - December 2023/January 2024 on Linkedin Email Project Updates - December 2023/January 2024 linkThere are a number of Flood Restoration Project works currently being completed, on the vast list of buildings and facilities requiring repair. This page aims to share milestone updates, that may benefit the wider community. Please see below updates on some of the projects shared for this month. Projects are listed in alphabetical order.
If there is a project you would like particular updates on, please utilise the Q+A function of the main article or contact Council on council@lismore.nsw.gov.au(External link)
Completed by the end of 2023
Albert Park Baseball
Croquet Clubhouse
Brunswick Street Depot
Elaine Blanche Tennis Courts Clubhouse
Lismore Memorial Baths
Marie Mackney Netball Clubhouse
Mortimer Oval Container Building
Mortimer Oval Brick Building
Oakes/Crozier Amenities
Radio Controlled Car Building - Nesbitt Park
Brunswick Street Depot - Old Helicopter Building
Internal stairs have been built, and floor coverings installed.
In the workshop, painting has been completed and AC equipment installed. External cladding is in progress.
Caniaba Street Reserve Soccer Clubhouse (South Lismore Celtics)
Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.
Lismore Airport Terminal
All services rough ins completed during December. The mechanical condenser was replaced, the outdoor PAC unit and 3 x fan coil units installed. Geotech testing of the external generator location was conducted. Linings and insulation of internal walls has commenced.
Lismore Basketball Association
Site set up ready for works to replace the subfloor commence in January.
Lismore Cattle Saleyards
List of restoration priorities being determined with stakeholders. Scheduling of works to be determined in line with sale activities.
Lismore City Hall
Site set up complete, ready for works to commence in January.
Lismore CWA Building
Site set up and works to commence in January.
Lismore Municipal Building
Onsite meeting with stakeholders to inform accessibility in the design of the ground floor.
Lismore Regional Gallery
At the beginning of December, the solar panels were removed from the roof and the NBN fibre was installed. The laying of CFC flooring to L1 was completed and scaffolding erected to the North, East and West sides of external elevations. Roof sheets were delivered in early January which will be installed late January due to weather conditions. Internal cement rendering and repair of ground floor walls underway and the demolition strip-out of internal load bearing walls and kitchen benches are complete.
Mortimer Oval Amenities
Internal and external works now complete. Landscaping to be completed, which will finalise restoration for the end of January.
Richards Oval Soccer Clubhouse (Workers FC)
Meeting held with stakeholders to discuss 90% designs, schedule of works and ongoing support. Site setup complete, works to commence end of January.
Riverview Park
Stage 1 – Completed 20/12/23 and the building handed back to the user group.
Stage 2 – Field lighting and PA installation - nearing completion
The Quad
To be completed in conjunction with the Lismore Regional Gallery. Scheduled to start in March 2024. Scope of works broadly include drainage, shade and landscape improvements.
Visitor Information Centre building
Temporary toilets were installed for public use, as works commenced and site setup finalised. Contract procurement, planning with subcontractors and stakeholder conversations also continued. New mechanical upgrades were underway and glazing upgrades in production.