This project has now concluded.
Lismore City Council is undertaking roadworks on Caniaba Road, Loftville, from 28 January 2020.
The works include reconstructing and upgrading the pavement on Caniaba Road, commencing at Muldoon Road for approximately 500m.
Works are expected to take approximately 9-10 weeks subject to weather. Daily work hours will mostly be between 7am and 4pm weekdays, although there may be some weekend work.
Traffic will be reduced to one lane during the works. Traffic control will include mobile traffic lights and a traffic control operator during working hours. Council will try to reopen the road at the end of each working day where possible.
Please commute through the job site at low speed, obey lane closures, and drive carefully.
If you have any questions or concerns, ask us a question using our Q&A tab below or phone our project engineer William Lee on 0427 674 008. For enquiries outside normal working hours, please phone 1300 87 83 87 (24-hour service).
Lismore City Council is undertaking roadworks on Caniaba Road, Loftville, from 28 January 2020.
The works include reconstructing and upgrading the pavement on Caniaba Road, commencing at Muldoon Road for approximately 500m.
Works are expected to take approximately 9-10 weeks subject to weather. Daily work hours will mostly be between 7am and 4pm weekdays, although there may be some weekend work.
Traffic will be reduced to one lane during the works. Traffic control will include mobile traffic lights and a traffic control operator during working hours. Council will try to reopen the road at the end of each working day where possible.
Please commute through the job site at low speed, obey lane closures, and drive carefully.
If you have any questions or concerns, ask us a question using our Q&A tab below or phone our project engineer William Lee on 0427 674 008. For enquiries outside normal working hours, please phone 1300 87 83 87 (24-hour service).
Share Community Update: 10 March 2020 on FacebookShare Community Update: 10 March 2020 on TwitterShare Community Update: 10 March 2020 on LinkedinEmail Community Update: 10 March 2020 link
Crews have now finished sub-soil drainage work at this site. Road reconstruction will now begin and traffic control will be in place with one lane of traffic closed to the end of April.
We hope to have the road resealed and two lanes of traffic reopened by the end of April.
Share Community Update: January 2020 on FacebookShare Community Update: January 2020 on TwitterShare Community Update: January 2020 on LinkedinEmail Community Update: January 2020 link
What works are going to
occur?
Improve
the section of road.
Reshape roadside drains and modify
culverts.
Adjoining driveway adjustments.
Re-install guide posts and traffic
signage.
How will I be impacted?
Traffic flow will be disrupted
on Caniaba Road and at the intersection to Muldoon Road. Access to adjoining driveways
will be maintained.
There may be periods of dust,
noise and water supply
disruptions.
Garbage
bin collection will continue as usual.
Who is funding this project? Lismore
City Council
Signup Banner
Life Cycle
Works commence
Caniaba Road, Loftville has finished this stage
28 January 2020
Ongoing updates
Caniaba Road, Loftville is currently at this stage
See our Community Updates for ongoing information
Works Completed
this is an upcoming stage for Caniaba Road, Loftville