CBD Watermain Replacement Program

Share CBD Watermain Replacement Program on Facebook Share CBD Watermain Replacement Program on Twitter Share CBD Watermain Replacement Program on Linkedin Email CBD Watermain Replacement Program link

Consultation has concluded

Consultation for this project has been finalised. We'd like to extend thanks to the businesses, residents and stakeholders involved.

Works to complete the CBD Watermain Replacement Program are nearing completion, and expected to be finalised by December 2024.


As water mains age, they are replaced to ensure businesses and residents continue to have a reliable water supply. From February 2024 to September 2024, Council will be replacing watermains at five locations across the CBD, as part of the CBD Watermain Replacement Program 2023/24.


Project Details:

Circa $3million

  • Installation of new water mains
  • Transfer of service connections
  • Decommission the original mains

The construction methodology preference is to employ horizontal directional drilling where possible and practicable to minimise disruption. This method of installation allows the pipe to be drilled into the ground in sections, with small receive and launch holes. Excavation and backfilling for this process will be completed using a small excavator.

If this method is found to be impractical at any of the below locations, residents and businesses will be notified to minimise impacts.

Location of Works:

Dawson Street (Conway Street to McLennan Lane) 96m - Scheduled start 28/02/24: Notification

Dawson Street (Conway Street to Orion Street)  937m - Scheduled start 01/03/24: Notification

Keen & Orion Streets (Zadoc Street to Orion Street) 330m - Scheduled start 13/03/24: Notification

Woodlark Street (Dawson Street to Keen Street)  206m - Scheduled start 21/03/24: Notification

Zadoc Street (Molesworth Street to Keen Street)  200m - Scheduled start 01/04/24: Notification

A laydown area for the delivery of pipes will be setup in the Harold Fredericks carpark opposite Oaks Oval, and utilised until the end of June 2024.

Notification of works will be delivered to businesses and residents 14 days before works commence at each location. Additionally, will be shared online throughout the works to provide updates on project completion and any disruptions where necessary.

Potential Impacts:

  • Increased levels of noise and dust
  • Changed traffic conditions including reduced speed limits and temporary lane closures. Traffic controllers will be available during construction working hours to assist motorists.
  • Where works will cause large interference with traffic movements, temporary road closures may be incorporated and/or works may be scheduled for nightworks. In this case, significant notice will be provided. The preferred methodology is not to close roads; however, this is not possible on all occasions.
  • Temporary water supply interruptions. Businesses and residents will be notified of these interruptions in writing at least 48 hours in advance.
  • A slight reduction in water pressure during the use of the temporary water supply pipe.
  • Temporary driveway access restrictions at times. Affected businesses and residents will be notified in advance so alternative arrangements can be made if needed.
  • Temporary footpath closures. Alternative pedestrian access will be clearly signed, and site representatives will be available during construction working hours to assist pedestrians as needed.

These works are being completed through the Capital Works Water Pipelines projects to provide a safe and reliable water supply.

Please visit the FAQs, Related Information and Project Updates tabs for more information.

Consultation for this project has been finalised. We'd like to extend thanks to the businesses, residents and stakeholders involved.

Works to complete the CBD Watermain Replacement Program are nearing completion, and expected to be finalised by December 2024.


As water mains age, they are replaced to ensure businesses and residents continue to have a reliable water supply. From February 2024 to September 2024, Council will be replacing watermains at five locations across the CBD, as part of the CBD Watermain Replacement Program 2023/24.


Project Details:

Circa $3million

  • Installation of new water mains
  • Transfer of service connections
  • Decommission the original mains

The construction methodology preference is to employ horizontal directional drilling where possible and practicable to minimise disruption. This method of installation allows the pipe to be drilled into the ground in sections, with small receive and launch holes. Excavation and backfilling for this process will be completed using a small excavator.

If this method is found to be impractical at any of the below locations, residents and businesses will be notified to minimise impacts.

Location of Works:

Dawson Street (Conway Street to McLennan Lane) 96m - Scheduled start 28/02/24: Notification

Dawson Street (Conway Street to Orion Street)  937m - Scheduled start 01/03/24: Notification

Keen & Orion Streets (Zadoc Street to Orion Street) 330m - Scheduled start 13/03/24: Notification

Woodlark Street (Dawson Street to Keen Street)  206m - Scheduled start 21/03/24: Notification

Zadoc Street (Molesworth Street to Keen Street)  200m - Scheduled start 01/04/24: Notification

A laydown area for the delivery of pipes will be setup in the Harold Fredericks carpark opposite Oaks Oval, and utilised until the end of June 2024.

Notification of works will be delivered to businesses and residents 14 days before works commence at each location. Additionally, will be shared online throughout the works to provide updates on project completion and any disruptions where necessary.

Potential Impacts:

  • Increased levels of noise and dust
  • Changed traffic conditions including reduced speed limits and temporary lane closures. Traffic controllers will be available during construction working hours to assist motorists.
  • Where works will cause large interference with traffic movements, temporary road closures may be incorporated and/or works may be scheduled for nightworks. In this case, significant notice will be provided. The preferred methodology is not to close roads; however, this is not possible on all occasions.
  • Temporary water supply interruptions. Businesses and residents will be notified of these interruptions in writing at least 48 hours in advance.
  • A slight reduction in water pressure during the use of the temporary water supply pipe.
  • Temporary driveway access restrictions at times. Affected businesses and residents will be notified in advance so alternative arrangements can be made if needed.
  • Temporary footpath closures. Alternative pedestrian access will be clearly signed, and site representatives will be available during construction working hours to assist pedestrians as needed.

These works are being completed through the Capital Works Water Pipelines projects to provide a safe and reliable water supply.

Please visit the FAQs, Related Information and Project Updates tabs for more information.

Consultation has concluded
  • January 2024

    Share January 2024 on Facebook Share January 2024 on Twitter Share January 2024 on Linkedin Email January 2024 link

    An early notification of works was delivered to letterboxes of affected businesses and residents on Wednesday 17 January.

    READ THE NOTIFICATION

    The five sections will be completed one after the other as best practicable and as works are finalised. Notification will be delivered in advance prior to commencement of works.

    All works notifications will be available on this page. If you feel your letterbox was missed, copies will be available in the Related Information tab, or can be sent by request. Please call 6625 0500 and provide your best details to receive these notifications.

    Please consider the FAQs for any questions you may have. Updates about the project will be available on this page as works progress.