Project Update - 29th May 2023
Works next week:
- Installation of communication conduits and pits at Keen – Magellan Corner – work ongoing
- Keen Magellan Corner rectification
- Concrete works will be commencing
- New bin enclosures installed.
- All remaining plantings completed.
Within the month:
- Delivery of seating
- Replacing the old bollards in Keen street – Mid to late May (delayed due to change in contractors)
- Installation of the Multi Pole - Mid to late May
- Wheel Stop Placement (delayed due to change in contractors and delivery)
- Continuation of Keen - Magellan Corner rectification
June:
- Delayed shipment of the Seats. Expected late May, with installation now planned for mid-June
- Meet Pat Water Fountain Installation early June. Awaiting plumbing contractor availability
- Electrical and communication cabling
- Finalisation of street furniture
- Installation of seating in mid-June
- Meet Pat Water Fountain Installation early June. Awaiting plumbing contractor availability
Share Project Update - 29th May 2023 on Facebook
Share Project Update - 29th May 2023 on Twitter
Share Project Update - 29th May 2023 on Linkedin
Email Project Update - 29th May 2023 link
This project has been completed. Minor additions will be completed, before ongoing maintenance.