Project Update - Friday 11 November 2022
This week the project team focused on kerb, channel drain and the civil works in preparation for the new road and footpath pavement.
The progression of this work allows large volume footpath pours next week.
Priorities for the project team over the next week are as follows:
- Continuing lean mix (subbase) pours early in the week
- Continuation of lower section of the footpath.
- Gollan Traffic Blister pits and drainage.
Share Project Update - Friday 11 November 2022 on Facebook
Share Project Update - Friday 11 November 2022 on Twitter
Share Project Update - Friday 11 November 2022 on Linkedin
Email Project Update - Friday 11 November 2022 link
This project has been completed. Minor additions will be completed, before ongoing maintenance.
![<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>](https://d569gmo85shlr.cloudfront.net/assets/ajax-loader-transparent-aebc793d0064383ee6b1625bf3bb32532ec30a5c12bf9117066107d412119123.gif)