Project Update - Friday 17 February 2023

Please see the below project update for activities.

Keen Street Revitalisation works update:

Works next week:

  • Replacement of barriers with temporary street furniture
  • Concrete removal (Satay hut – 1 day)
  • Surface finish final clean and sealing
    • Noise work to be conducted late afternoons/weekends
    • Ongoing joint sealing (partial footpath closures to allow sufficient drying)

Within the month:

  • Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Milling Sunday 26th February, Placement Monday 27thFebruary (Road Closed during placement – traffic Control on Keen/Woodlark Roundabout)
    • Linemarking (tentative 2-MAR
    • Signage finalisation (ongoing)
  • Bollard Placement in Central Parking (intermittent closures over 2 days)

March-April:

  • Bespoke Street Furniture will start to arrive. (Quatro Pots and seats)
  • Planting of Seats, planter boxes
  • Keen Magellan Corner rectification works.
  • Wheel Stop installation Central Parking bays (intermittent closures over 1 days)

May-June

  • Keen Magellan Corner revitalisation works.
  • Electrical and communication cabling
  • Finalisation of street furniture

We greatly appreciate the patience showed by all keen St businesses during this project.

Share Project Update - Friday 17 February 2023 on Facebook Share Project Update - Friday 17 February 2023 on Twitter Share Project Update - Friday 17 February 2023 on Linkedin Email Project Update - Friday 17 February 2023 link

This project has been completed. Minor additions will be completed, before ongoing maintenance.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>