Project Update - Friday 17 February 2023
Please see the below project update for activities.
Keen Street Revitalisation works update:
Works next week:
- Replacement of barriers with temporary street furniture
- Concrete removal (Satay hut – 1 day)
- Surface finish final clean and sealing
- Noise work to be conducted late afternoons/weekends
- Ongoing joint sealing (partial footpath closures to allow sufficient drying)
Within the month:
- Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Milling Sunday 26th February, Placement Monday 27thFebruary (Road Closed during placement – traffic Control on Keen/Woodlark Roundabout)
- Linemarking (tentative 2-MAR
- Signage finalisation (ongoing)
- Bollard Placement in Central Parking (intermittent closures over 2 days)
March-April:
- Bespoke Street Furniture will start to arrive. (Quatro Pots and seats)
- Planting of Seats, planter boxes
- Keen Magellan Corner rectification works.
- Wheel Stop installation Central Parking bays (intermittent closures over 1 days)
May-June
- Keen Magellan Corner revitalisation works.
- Electrical and communication cabling
- Finalisation of street furniture
We greatly appreciate the patience showed by all keen St businesses during this project.
Share Project Update - Friday 17 February 2023 on Facebook
Share Project Update - Friday 17 February 2023 on Twitter
Share Project Update - Friday 17 February 2023 on Linkedin
Email Project Update - Friday 17 February 2023 link
This project has been completed. Minor additions will be completed, before ongoing maintenance.
![<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>](https://d569gmo85shlr.cloudfront.net/assets/ajax-loader-transparent-aebc793d0064383ee6b1625bf3bb32532ec30a5c12bf9117066107d412119123.gif)