Project Update - Friday 18th November 2022
This week the project team focused on finishing all stormwater and drainage works as well as the new road pavement layers at Larkin Lane.
We also progressed with lean mix (1st layer of footpath) and exposed aggregate finish (top layer of footpath) for the bottom section of the footpath.
With a big week next week focusing on footpath pours, the project team is looking forward to finishing the bulk of construction and reopening the road at the end of the month.
Priorities for the project team over the next week are as follows:
- Continuing lean mix (subbase) pours early in the week
- Continuation of lower section of the footpath.
- Continuation of Gollan Traffic Blister pits and drainage.
Share Project Update - Friday 18th November 2022 on Facebook
Share Project Update - Friday 18th November 2022 on Twitter
Share Project Update - Friday 18th November 2022 on Linkedin
Email Project Update - Friday 18th November 2022 link
This project has been completed. Minor additions will be completed, before ongoing maintenance.
![<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>](https://d569gmo85shlr.cloudfront.net/assets/ajax-loader-transparent-aebc793d0064383ee6b1625bf3bb32532ec30a5c12bf9117066107d412119123.gif)