Project Update - Friday 24 February 2023

Keen Street Revitalisation works update:

Works next week:

  • Replacement of barriers with temporary street furniture (ongoing)
  • Concrete removal Satay Hut (Sunday 28th – cutting)
  • Surface finish final clean and sealing
    • Cutting (Noise work to be conducted Sunday 26th)
    • Ongoing joint sealing (partial footpath closures to allow sufficient drying)
  • Removal and replacement of partial central crossing
    • Cutting Sunday 26th Feb
    • Remove and repour Tuesday 28th Feb.

Within next month:

  • Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Milling Sunday 26th February, Placement Monday 27thFebruary (Road Closed during placement – traffic Control on Keen/Woodlark Roundabout)
    • Linemarking (13th March – Nightshift)
    • Signage finalisation (ongoing)
  • Bollard Placement in Central Parking (intermittent closures over 2 days)

March-April:

  • Bespoke Street Furniture will start to arrive. (Quatro Pots and seats 27th March)
  • Planting of Seats, planter boxes (WS 27th March)
  • Keen Magellan Corner rectification works (Mid-March)
  • Wheel Stop installation Central Parking bays (intermittent closures over 1 days)

May-June

  • Keen Magellan Corner revitalisation works.
  • Electrical and communication cabling
  • Finalisation of street furniture

We greatly appreciate the patience showed by all Keen St businesses during this project.

Share Project Update - Friday 24 February 2023 on Facebook Share Project Update - Friday 24 February 2023 on Twitter Share Project Update - Friday 24 February 2023 on Linkedin Email Project Update - Friday 24 February 2023 link

This project has been completed. Minor additions will be completed, before ongoing maintenance.