Project Update Friday, 4th November 2022
This week the project team focused on progressing the channel drain and underground drainage and electrical networks.
Although it doesn’t appear as though the project advances much during these types of activities, it does allow us to progress into concrete and finishing works ensuring Keen Street is opened in the most timely manner possible.
A small number of footpath pours were also completed this week at the centre traffic blister.
Priorities for the project team over the next week are as follows:
- Lean mix (trench pours to protect the stormwater pipes)
- Larkin Lane Lean Mix and pavement works.
- Pour Channel drain encasement and kerb
- Continuation of lower section of the footpath.
There will be no further shop closures in relation to the Keen Street construction works. Once again we would like to thank the businesses for their understanding around these closures in order to accelerate the works.
Currently the project team are available onsite Mondays 3pm and Wednesdays 11am for discussions around construction staging and business interactions.
This project has been completed. Minor additions will be completed, before ongoing maintenance.