Project Update - Saturday 26th November
Despite some slight issues this week with concrete supply the project team have progressed the footpath pours to the final traffic blister at the Northern end of the street. (Woodlark end)
These pours will allow the asphalt subcontractor to mobilise to site from Monday to Wednesday next week to pave the new parking and driving lanes.
These final works are weather sensitive however we are still looking confident for vehicle access to shops at the end of the month.
This week the project team also installed the new underground power and communications conduit from the Gallery via underbore drilling.
Priorities for the project team over the next week are as follows:
- Kerb pours at the Woodlark end Roundabout crossing
- Asphalt profiling (milling) and paving of the parking and traffic lanes.
- Existing Pit repairs under Woodlark Street
- Footpath pours at the Woodlark end Roundabout crossing
This project has been completed. Minor additions will be completed, before ongoing maintenance.