Project Update - Sunday 5 March 2023

Keen Street Revitalisation works update:

Works next week:

  • Replacement of barriers with temporary street furniture (progressive)
  • Surface finish final clean and sealing
    • Ongoing joint sealing (partial footpath closures to allow sufficient drying)
  • Satay Hut Blister planting

Within the month:

  • Linemarking (13th March – Nightshift)
  • Signage finalisation (ongoing)
  • Bollard Placement in Central Parking (intermittent closures over 2 days)

March-April:

  • Bespoke Street Furniture will start to arrive. (Quatro Pots and seats 27th March)
  • Planting of Seats, planter boxes (WS 27th March)
  • Keen Magellan Corner rectification works (Mid-March)
  • Wheel Stop installation Central Parking bays (intermittent closures over 1 days)

May-June

  • Keen Magellan Corner revitalisation works.
  • Electrical and communication cabling
  • Finalisation of street furniture

We greatly appreciate the patience showed by all Keen St businesses during this project.

Share Project Update - Sunday 5 March 2023 on Facebook Share Project Update - Sunday 5 March 2023 on Twitter Share Project Update - Sunday 5 March 2023 on Linkedin Email Project Update - Sunday 5 March 2023 link

This project has been completed. Minor additions will be completed, before ongoing maintenance.