Project Update - Sunday 5 March 2023
Keen Street Revitalisation works update:
Works next week:
- Replacement of barriers with temporary street furniture (progressive)
- Surface finish final clean and sealing
- Ongoing joint sealing (partial footpath closures to allow sufficient drying)
- Satay Hut Blister planting
Within the month:
- Linemarking (13th March – Nightshift)
- Signage finalisation (ongoing)
- Bollard Placement in Central Parking (intermittent closures over 2 days)
March-April:
- Bespoke Street Furniture will start to arrive. (Quatro Pots and seats 27th March)
- Planting of Seats, planter boxes (WS 27th March)
- Keen Magellan Corner rectification works (Mid-March)
- Wheel Stop installation Central Parking bays (intermittent closures over 1 days)
May-June
- Keen Magellan Corner revitalisation works.
- Electrical and communication cabling
- Finalisation of street furniture
We greatly appreciate the patience showed by all Keen St businesses during this project.
Share Project Update - Sunday 5 March 2023 on Facebook
Share Project Update - Sunday 5 March 2023 on Twitter
Share Project Update - Sunday 5 March 2023 on Linkedin
Email Project Update - Sunday 5 March 2023 link
This project has been completed. Minor additions will be completed, before ongoing maintenance.