September 2 2022

Over the past week, the project team have been undertaking the civil works to improve foundation conditions as well as installing new and updated services.

These services include electrical and communications networks for future uses as well as upgraded storm water and water main services.

Priorities for the project team over the next two weeks are as follows:

  • The project team are working this Sunday 04/09 for concrete cutting activities as an effort to minimise business disruption.
    • This will occur from Book Warehouse to Woodlark St. Public access will be restricted in this area on this day, however business owner, landlord and residential access will still be possible.
  • Early next week the project team will be completing earthworks activities between Suffolk Sports and Cut Lose Hair Salon.
  • The concreters will then be returning to site to pour the concrete footpath along the shopfront section between Suffolk Sports and Cut Loose Hair Salon.

            Access will not be possible for 4 days commencing Monday 05/09 for the businesses in this section. Contact will be made for any updates around restoring public access.

  • The following week (commencing 12/09) new concrete footpath will be poured from Scoops and Candy to the Book Warehouse.
  • The project team will be progressing into the 2nd half of the street with demolition activities beginning at the Northern end of the Book Warehouse on the 12th September. (please see dates below)

Ch 122 – 170 Book Warehouse to Blooms Chemist (between the 2 doors)

Footpath closed 12/9/22 to 15/9/22

Footpath to reopen 16/9/22

Ch 170 – 212 Blooms Chemist to Larkin Lane

Footpath closed 19/9/22 to 22/9/22

Footpath to reopen 23/9/22

Ch 212 – 250 Larkin Lane to Woodlark Street

Footpath closed 26/9/22 to 29/9/22

Footpath to reopen 30/9/22

Currently the project team are available onsite Mondays 3pm and Wednesdays 11am for discussions around construction staging and business interactions. If there is a better suited time, please reply to this email and we can make ourselves available.

Share September 2 2022 on Facebook Share September 2 2022 on Twitter Share September 2 2022 on Linkedin Email September 2 2022 link

This project has been completed. Minor additions will be completed, before ongoing maintenance.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>