Keerrong Bridge Updates
Landing bridge beams have been installed yesterday at Keerrong Bridge.
Due to the February 28 disaster and March flooding events, the collapsed culvert structure located north of the intersection with Dudgeon Road is being replaced with a new 7.2m wide by 16.1m long InQuik bridge.
Works are expected to be finalised by the end of August 2022, pending weather and ground conditions.
***Update at August 4th 2022***
Unsuitable material has been found on the Lismore approach to the bridge, which will have to be removed and replaced. Schedule of works will now be delayed, expected opening remains at the end of August 2022.
Further details for Keerrong Road works can be found on: https://yoursay.lismore.nsw.gov.au/keerrong-road-works