Category Keerrong Bridge   Show all

  • Keerrong Bridge - Open from Tuesday, 30 August 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Works are drawing to a close on the Keerrong Bridge project.

    Due to the February and March 2022 events, the collapsed culvert structure, located north of the intersection with Dudgeon Road was replaced with a new bridge. Measuring 7.2m wide, and 16.1m long the new InQuik concrete bridge will restore much needed access via Keerrong Road.

    Construction started back in May of 2022, and the bridge will now undergo a soft opening from Tuesday, 30 August 2022. Temporary traffic control will remain in place until approach guard rail has been installed. An official open date will be advertised as these works are finalised.

    Following the bridge opening, Keerrong Road will be open to through traffic from the Nimbin Road intersection through to the Keerrong Bridge Road intersection.

    As part of the construction, the approaches to the bridge were also replaced with more suitable material and sealed for the safety of motorists.

    There are still traffic control measures in place on Keerrong Road further north of this intersection whilst flood remediation works continue.

  • Current Road Project Updates 25 August 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    There are a number of road projects currently being completed. The below are updates for some of the projects which are progressing this week.

    If the road or project of interest isn't included below, please click the road name to the right (for desktop) of this page, or by scrolling to the bottom of the page (for mobile) for updates.

    Additionally, please utilise the Q+A function of this page to request specific updates.


    Black Road - Design is underway for a replacement structure. A temporary crossing is in place.

    Caniaba Road - Drainage works complete, shoulder widening works including a rock foundation is ongoing.

    Cowlong Road - Works are progressing near Lavis Road. Construction works planned for completion late September.

    Cawongla Road - Community consultation is underway in preparation for the road closure to replace four damaged culverts.

    Gravel Roads Program - Flood repair works are progressing. Approximately 60% of the LGA has now been complete with four road grading crews working full time on these works. Grading of gravel roads in Precinct 11 (including The Channon and surrounds) is due to commence in September. Please take care around the mobile plant. View the Precinct map and completion dates HERE

    Gungas Road - Pavement works well underway. Works expected to be complete by October.

    Hensen Bridge - Concrete abutments have been poured. Concrete bridge beams to be placed September in preparation of the deck pour.

    Johnston Road, Clunes - Geotechnical investigations finalised this week, with instruments installed to monitor the slip. Road reopened Monday 29th August under stop go traffic control until investigation works are complete.

    Keerrong Bridge - Concrete bridge complete including bridge approaches. Bridge will be opened under traffic control early September.

    Keerrong Road - Repairs to a 1.8km section on Keerrong Road is progressing well which will be complete by early September.

    Oakey Creek Road - Community consultation is underway in preparation for geotechnical investigations to determine the scope of work required for landslip remediation.

    Pinchin Road - Pavement stabilisation repair on several sections of Pinchin Road will commence August 29th. Single lane traffic control in place for the duration of works (5 weeks, weather permitting). Works on Keerrong Road will be postponed from September 1st, to allow additional traffic flow while Pinchin Road works are completed.

    Sexton Bridge, Gundurimba Road – Piling works commenced with abutment works planned for the next 3 weeks.

    Terania Creek Road - Segments have been identified to be included in the Flood Recovery Heavy Patching Program, which will provide improvements to the structural integrity of the road and driving conditions for road users. Geotechnical monitoring of the slip site is underway, as is procurement of specialist contractors and designers. Once works are complete at the slip, bridge approaches will be repaired and the road graded.

    Town Road - Bridge structure has been procured and works are expected to commence in late 2022.

    Tuntable Creek Road - Drilling has been undertaken on the slips, with geotechnical instrumentation installed to monitor movement to best inform the required structural design. Unfortunately, there is a shortage of suitably qualified geotechnical engineers at present. Council has started the procurement process to engage a designer and contractor to undertake restoration works. Additionally, funding has been received to undertake pavement repairs on damaged sealed-sections of Tuntable Creek Road, which is scheduled for October.

     Keerrong Road - repairs to a 1.8km sectionKeerrong Road - repairs to a 1.8km section

    Sexton Bridge piling works commenced

    Cowlong Road, near Lavis Road


  • Current Road Project Updates 5 August 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Gravel Roads (Flood Repair Works) – approximately 50% of LCC Gravel Roads have been repaired now since the Feb/March 2022 events.

    Caniaba Road – Drainage and shoulder widening works progressing well. Project is currently running to plan with minimal delays.

    Richmond Hill Road – the landslip has been repaired and pavement rehabilitation works are progressing.

    Nimbin Road near Goolmangar School – urgent maintenance works were carried out last week, the damaged sealed pavement was returned to gravel. This section of road will be overlaid with new gravel and stabilised this month

    Keerrong Road Bridge – the new concrete bridge is now complete and earthworks progressing on the approaches

    Henson Bridge – Piling is now complete, works progressing well on preparing the bridge abutments (form/reo/poor)

    Keerong Road – Landslip and drainage remediation works are commencing, leading to a road closure from August 10th - adjacent to 1265 Kerrong Road. Motorists are advised via roadside signage. Pavement strengthening works are also progressing on approximately a 1km section. Further pavement works are scheduled.

    Bruxner Highway at Northcott Road – pavement rehabilitation works are progressing which have included stabilisation of the existing material and overlay with new gravel.

    Gungas Road – shoulder widening and pavement works are progressing.

    Cowlong Road – pavement strengthening works are progressing south of McKenzie Road.

    Jiggi Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    Pinchin Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    One section of Jiggi Road, preconstruction on 04/08/22

    Wyrallah Road - Geotechnical drilling to determine scope of works.

    Drilling at Wyrallah Road 27/07/22

    Dunoon Road (near the Macadamia Factory) - Temporary patching on a section of road adjacent Macadamia factory on Dunoon Road. This section of road is due for full pavement reconstruction in October this year.

    a section of Dunoon Road before temporary patching 02/08/22

  • Keerrong Bridge Updates

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Landing bridge beams have been installed yesterday at Keerrong Bridge.

    Due to the February 28 disaster and March flooding events, the collapsed culvert structure located north of the intersection with Dudgeon Road is being replaced with a new 7.2m wide by 16.1m long InQuik bridge.

    Works are expected to be finalised by the end of August 2022, pending weather and ground conditions.

    ***Update at August 4th 2022***

    Unsuitable material has been found on the Lismore approach to the bridge, which will have to be removed and replaced. Schedule of works will now be delayed, expected opening remains at the end of August 2022.

    Further details for Keerrong Road works can be found on: https://yoursay.lismore.nsw.gov.au/keerrong-road-works