Flood Restoration - Roads & Bridges Update (Feb 2023)
Share Flood Restoration - Roads & Bridges Update (Feb 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Feb 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Feb 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Feb 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please email floodrestoration@lismore.nsw.gov.au with subject ‘Add Road Name - Notification list’ to register your contact details to receive updates.
COMPLETED WORKS
Tuntable Creek Road
Tuntable Creek Road experienced significant damage during the February 2022 natural disaster with 11 notable landslips recorded and a major landslip closing the road north of intersection with Rose Road. A temporary solution was designed to open the road and establish connectivity between Nimbin and The Channon while the permanent solution is designed. The temporary construction consists of stabilising the embankment below the road and excavating into the slope above the road to make a single trafficable lane. The stabilisation will use up to 160 8m long soil nails and over 400m2 of sprayed concrete. Additionally, crews are also reconstructing pavement through the slip zone and installing light traffic control. The works are expected to be complete in March with the road opened to local access only and restricted during weather events. For further details please visit the Tuntable Creek Road update:
https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/tuntable-creek-road-jan-2023
Cawongla Road
The Cawongla Road pipes’ replacement project was ahead of schedule and the road opened at the end of January before school started. The works consisted of replacing two culverts that suffered significant damage during the 2022 floods.
Gwynne Road
Temporary repair of damaged pavement was recently completed for Gwynne Road. During these works, the crews also performed scour repair and mulching vegetation along with cleaning drains and pipes to improve the roads condition.
Unsealed Roads
Overlay works to repair damages from the October flood event were recently completed for Lagoon Grass Road, Howards Grass Road, Cusack Road, Booerie Creek Road, Hewitt Road, Swan Bay Road, and Sheehan Road.
Johnston Road
Temporary patching works across slip single lane were recently completed for Johnston Road.
CURRENT WORKS
Crofton Road & Rock Valley Road
Drainage works are continuing for Crofton Road and Rock Valley Road these include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.Wyrallah Road
Pavement rehabilitation works started at the end of January to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. For further details please visit the Wyrallah Road update link below:
FUTURE WORKS
Town Road
Funding through the Fixing Country Bridges program has been awarded to replace the damaged structure with a new bridge. The bridge superstructure is currently being constructed in France with an innovative steel beam that will be launched into place in one piece. A unique type of structure, this bridge will be the first in the region. A general plan of the works is provided below. The Town Road bridge superstructure will be delivered at the end of May 2023. Civil works are scheduled to begin in April 2023 with a planned completion in late July 2023, subject to fine weather. Further updates will be provided towards the end of March 2023.
Mackie Road
Following the 2020 natural disaster the Mackie Road causeway at Johnston Creek suffered extensive damage. Funding has been awarded to replace the damaged structure with a bridge to reduce impediments to fish passage. The Mackie Road culvert to bridge replacement at Johnston Creek, works will begin on the 13th of March for approximately three months with a planned completion in late June 2023, subject to fine weather. Due to the nature of the works a full 24-hour hard road closure is required during the March – June 2023 works period around the location detailed on the map below. For further details please visit the Mackie Road bridge update link below:
-
Flood Recovery Heavy Patching Program
Share Flood Recovery Heavy Patching Program on Facebook Share Flood Recovery Heavy Patching Program on Twitter Share Flood Recovery Heavy Patching Program on Linkedin Email Flood Recovery Heavy Patching Program linkFlood Recovery Heavy Patching Program –
Restoration of road surface, possible change in road level.
Segments of the following have been identified for heavy patching works to repair flood damage to road surface.
Precinct 1
Graham Road
Gundarimba Road
River Bank Road
Rous Road
Skyline Road
Tregeagle Road
Tuckurimba Road
Tucki Road
Wybelena Road
Precinct 2
Bagotville Road
Broadwater Road
Kilgin Road
Mathieson Lane
Precinct 3
Tatham Road
Precinct 4
Nimoola Road
Pelican Creek Road
Precinct 6
Back Creek Road
Precinct 7
Axford Road
Martin Road
McGuinness Road
Rock Valley Road
Precinct 8
Boggumbil Road
Davis Road
Jacobson Road
Jiggi Road
Potessu Road
Rosehill Road
Precinct 9
Anderson Road
Basil Road
Cecil Street
Crofton Road
Gungas Road
Lillian Rock Road
Moffitt Road
Sibley Street
Symonds Road
Thorburn Street
Precinct 10
Booerie Creek Road
Boyle Road
Keerrong Road
Precinct 11
Koonorigan Road
Pinchin Road
Terania Creek Road
The Channon Road
Tuntable Creek Road
Precinct 12
Dorroughby Road
Duncan Road
James Street (Dunoon)
Middleton Way
Nightcap Range Road
Rocky Creek Dam Road
Precinct 13
Corndale Road
Hunters Hill Road
Grace Road
James Gibson Road
Precinct 14
Boatharbour Road
Eltham Road
Humpty Back Road
Regional Roads
Blue Knob Road
Coraki Road
Dunoon Road
Nimbin Road
Wyrallah Road
Bridge Street (Wyrallah)
Kyogle Road
These works are subject to change to due weather conditions, availability of contractors and funding. Updates will be posted on this article.
Shall you wish to be kept up to date directly, you can register your details via the Your Say ‘Submissions’ tab HERE. Alternately, please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details. Please reference ‘Flood Recovery Heavy Patching Program’.
How will the works affect traffic?
Roads will be open to residential access only during the time of works. Traffic controls will be in place, which will cause minor delays and disruptions. Please note roadside signage, updates on myroadinfo and updates in the online Your Say article for communication about temporary disruptions to your property access during this period.
What do the works involve?
These roads need to be fixed to improve the structural integrity and driving conditions for road users. Works include cleaning drains and culverts, cutting off high road shoulders, digging out and replacing soft spots with rock. The gravel overlay is placed where required, before stabilising with the addition of slag lime. This is then compacted, trimmed, and sealed. Followed by line marking edge line.
The road surface may receive a final wearing seal several months after the initial bitumen seal has cured.
This pavement overlay may potentially change road levels between 0mm to +150mm and resurfacing of the existing road width due to additional layers of new road base material.
All driveways that intersect the road will match any changes to the road profile. If there are any changes, you will be contacted should your driveway/access need modification. We will also do maintenance to roadside drainage as needed.
What happens now?
If you wish to make comment on the works, we ask that you do this by 4pm Monday, 15th August 2022 referring to ‘Flood Recovery Heavy Patching Program’. Feedback can be received via any of the following:
- Via the ‘Submissions’ tab of this article HERE.
- Email to council@lismore.nsw.gov.au
- Call to Council (02) 6625 0500
- In writing to Lismore City Council, PO Box 23A, Lismore 2480