Category Caniaba Road Show all
-
Caniaba Road - Pavement Rehabilitation Works (Feb 2023)
Share Caniaba Road - Pavement Rehabilitation Works (Feb 2023) on Facebook Share Caniaba Road - Pavement Rehabilitation Works (Feb 2023) on Twitter Share Caniaba Road - Pavement Rehabilitation Works (Feb 2023) on Linkedin Email Caniaba Road - Pavement Rehabilitation Works (Feb 2023) linkCouncil will be commencing pavement rehabilitation works to a section on Caniaba Road 1.7km to 2.1km West of Fredericks Road, to be completed throughout three months starting early February 2023 subject to weather, contractor, and material availability.
Funding has been secured through the Safer Roads Program to complete these works, which will improve road conditions and associated safety for road users. Additional works for Caniaba Road will continue to be assessed and reviewed.
Map outlining approximate location of the Caniaba Road pavement worksWhat are the works?
- Road surface: Improve the surface of the road in places. Road to be raised approximately 100mm.
- Guardrail installation: Installation of a safety barrier.
- Signs and line marking: Line marking and guideposts.
- Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
- Drainage maintenance: Re-excavate open drains and remove flood sediment as required
What are the traffic adjustments?
Road users are advised to follow signage and expect delays as these works are completed.
We apologise in advance for disruptions you may experience while we carry out these essential works. We would appreciate your cooperation with all traffic control and workplace protection measures to help keep everyone safe
Who should I contact with questions/concerns?
If you have any questions or concerns, please phone 6625 0500 (24-hour service) or email council@lismore.nsw.gov.au and include the title ‘Caniaba Road – Pavement Rehabilitation Works.’
-
Current Project Updates Tuesday, 11 October 2022
Share Current Project Updates Tuesday, 11 October 2022 on Facebook Share Current Project Updates Tuesday, 11 October 2022 on Twitter Share Current Project Updates Tuesday, 11 October 2022 on Linkedin Email Current Project Updates Tuesday, 11 October 2022 linkPlease note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.
Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
Caniaba Road - Shoulder widening and kerb and gutter installation completed, awaiting pavement backfill against kerb.
Caniaba Road
Blue Knob Road - Drainage and preparation work started this week, with further stabilisation works scheduled on various sections for next week - subject to weather, contractor and material availability. The landslip is being monitored as scope of works is determined.
Gravel road repairs - Young Road, Noble Road, Robb Road, Milgate Road, Beardow Road, Browning Road, Fairfull Road, Gibson Lane have all undergone maintenance. Upcoming maintenance is scheduled for Webber Road, Cook Road, Tulk Road, Fraser Road, Rose Road, Wybelena Road and Gray Road.
Gundurimba Road - Drainage works are scheduled for completion on various sections.
Gungas Road - Emergency culvert repair on Gungas Road, following damage sustained after recent heavy rainfall.
Gungas Road - emergency repairs
James Gibson Road - Temporary patching is scheduled, while scope of works for remediation is finalised.
Jiggi Road - First section has been completed, with an additional five to be completed. There have some delays due to weather, with scope of works reviewed to ensure damages due to heavy rainfall are remediated. Proposed works include pavement rehabilitation and drainage works.
Keerrong Road - Final stages of works, with a tidy up to be completed. Additional sections are scheduled for maintenance in December.
Nimbin Road - Drainage and Stabilisation are being completed on Nimbin Road with four patches completed out for the six scoped for repair. Guide posting and line marking works still to be completed. Stabilisation works are also scheduled for Nimbin Road (near Shipway Drive and Swift Road) in the coming weeks - subject to weather, contractor and material availability.
Pinchin Road - Final stages of completion on the sections of heavy patching works.
Pinchin Road - heavy patching completed
Sexton Bridge - Bridge deck pour and earthworks are currently being completed.