Category Leycester Road Show all
-
Flood Restoration - Roads & Bridges Update (Feb 2024)
Share on Facebook Share on Twitter Share on Linkedin Email this linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Geotechnical Investigations
During the last 5 months geotechnical investigations have taken place across the entire Lismore shire region. These works have involved using a drilling rig to understand subsurface conditions at the many landslip, bridge and culvert crossing locations. This information is vital in determining the most appropriate restoration design solution for these locations. All landslip, culvert and bridge geotechnical investigations have now been completed. We would like to thank residents for your patience and resilience during this time.
CURRENT WORKS
Dorroughby Road
The Dorroughby Road landslip restoration is well underway with embankment stabilisation completed last month. Wet weather has extended the closure slightly, however, drainage and road pavement works are scheduled to occur during March. See below progress photos, thank you to all the Dorroughby Road residents for your patience during this time.
Nimbin Road
Works are progressing on Nimbin Road at the site near Shipway Road. The retaining wall construction is now complete, and the road pavement works commenced end of February. Excitingly, traffic has temporarily moved onto the newly constructed northbound lane in preparation for an expected opening in April.
Guardrails Project
During the past month our guardrails project has been underway, replacing or installing new guardrails. This is multisite works to repair traffic barriers at road sections damaged during the 2022 natural disaster. Generally, the sites are at road sections over creek crossings. Each work site will require traffic control and the repair will generally be completed within 2 days. Recently, guardrails were completed on two sites at Nimbin Road, Rock Valley Road, Cawongla Road, Corndale Road and two sites at Boatharbour Road. Other road closures will be updated as scheduled work on Live Traffic.
Tuntable Creek Road
Works are currently underway on Tuntable Creek Road near Young Road. These involve reshaping of table drains, slashing and minor landslip remediation from Young Road heading back down the hill approximately 500m. The works are expected to be completed first week of March, pending weather conditions.
Terania Creek Road
The Terania Creek bridges project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings are completed for bridge 1. During early March, work crews will commence final concrete works and installation of lateral restrain brackets for bridge 3.
Newton Drive
Several minor upslope landslips and a single pipe culvert were scheduled to be repaired during February, these works have now been pushed into March due to weather delays. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Rosebank Road
Landslip restoration works were scheduled for completed during February; these works have now been pushed into March due to weather delays. The works involve reinstating the property access track and restoring the batter and table drain along the road edge. Works will be completed under traffic control and will have minimal impact on the residents.
Industry Drive
Works have commenced on Industry Drive to improve drainage works involving the construction of a gabion wall to prevent future erosion. The works will occur for approximately two weeks, from Thursday 29 February, pending weather conditions. For further information, please view the original notice at
https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/industry-drive
Rogerson Road
The team have been busy implementing appropriate protocols to ensure the safety of juvenile micro bats. Through successful collaboration with environmental professionals this protected species will be temporary relocated. This will allow the pups to complete their growth cycle during the breeding season and reduce their risk in maturing. We are unsure of the start date at this time. We will provide further update when available. Thank you to the community for your patience and understanding during these works. For further information, please view the original notice at: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/rogerson-road-culvert-replacement-feb-2024
FUTURE WORKS
Johnston Road
Works will commence to replace a damaged culvert headwall on Johnston Road for approximately two weeks, from 4 March to 18 March 2024, subject to weather conditions. The road will remain open under stop/go traffic control with slight delays expected. For further information, please view the original notice at
https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/johnston-road-culvert-works-feb-2023
Eureka Road, Graham Road & Haywood Lane
During the end of February, all three bridges were successfully delivered to Council storage yards. The designs for each site are in the final stages with works schedules being finalised. We apologise in advance for any disruptions you may experience while we carry out this essential work. These works will involve removing the existing infrastructure at each site and preparing the area for bridge construction. To minimise impact to residents and traffic flow during the construction work a temporary track will be established as a side road. The work duration at each site is expected to be approximately 6 weeks, subject to weather conditions.
Blue Knob Road
Remediation works are planned to commence in April 2024 on several landslips on Blue Knob Road, the two sites currently under temporary traffic control measures. Our primary focus is to ensure the well-being of our community and to efficiently manage the project to minimise disruption. We will notify residents of the exact date and provide further information on the works closer to commencement. The expected duration of the works will be approximately nine months, this estimated period includes the remediation of the total of four landslips.
Leycester Road
Leycester Road design is currently underway with expected completion in May 2024. Works are expected to start on site in August 2024 and will take approximately two months to complete. Funding for these works has been approved.
Oakey Creek Road
Currently there are five major landslips on Oakey Creek Road. Due to the complex nature of these sites, which involves multiple design iterations and reviews from civil, structural, and geotechnical engineers, the designs are expected to be completed by September 2024, with works to commence early in 2025 pending funding approvals.
Stony Chute Road
There are multiple landslips along Stoney Chute Road, seven of these being complex and two being non-complex. Works will commence on the noncomplex sites during April with the expected completion of June 2024. The more complex sites are currently under design with this process anticipated to be completed by August 2024 and works estimated to start towards the end of 2024 pending funding approvals.
Terania Creek Road
Terania Creek Road has multiple landslip sites currently under design with expected completion in September 2024 with works estimated to commence in early 2025 pending funding approval. Currently works are underway on multiple bridges with works anticipated to be completed mid-2024.
Wallace Road
Wallace Road has two major landslips currently under design with this process expected to be completed by the end of June 2024. It is estimated the works will commence towards the end of 2024 pending funding approvals. Please note, we are unable to schedule works until we receive funding approval.
Woodlawn Road
Woodlawn Road design is currently underway with expected completion in May 2024. Works are estimated to start on site in August 2024 and will take approximately three months to complete. Funding for these works has been approved. -
Flood Restoration - Roads & Bridges Update (Jan 2024)
Share on Facebook Share on Twitter Share on Linkedin Email this linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Geotechnical Investigations
During the month our contractors closed single lanes for works on Orion Street, Skyline Road South, Tuntable Creek Road, and Zouch Road to perform geotechnical investigations. This involved using a drilling rig to understand subsurface conditions. We would like to thank residents for your patience and resilience during this time. All landslip geotechnical investigations have now been completed with the bridge investigations underway and expected to also be completed by the middle of February.
Eltham Road
Recently, funding was secured to install guardrail on Eltham Road. These works were completed late January with a road closure in place around the site. There was a road closure between Houghlahans and Humpty Back roads and we thank the community for their patience during the road closure.Quilty Road
Works were recently completed on Quilty Road to repair pavement damage and replace a culvert to return the road to pre-existing conditions. Thank you to the residents for their patience and support during the works.
Tuntable Creek Road
As the safety threshold had been exceeded, a road closure was triggered for Tuntable Creek Road on Wednesday 17 January 2024 at the landslip site, between Rose Road and Beardow Road. The shut down was to ensure the safety of motorists and to allow for further monitoring. Geotechnical experts were on site the next day to inspect the site and determined it could be reopened. The road reopened Thursday morning 18 January 2024. The new signs installed in October 2023 assisted to reduce detour times allowing Council to notify residents of the closure before reaching the closed site.
CURRENT WORKSNimbin Road
Works are continuing for Site 4km on Nimbin Road, after the successful completion and opening of Site 1Km. Recently work crews completed implementation and maintenance of the erosion control following the heavy rainfall. Placement of approximately 70% of the GWS (No Fines Concrete Blocks) on top of the pile cap and approximately 60m of drainage layer and selected fill behind the retaining wall were also recently completed.
Guardrails Project
During the past month our guardrails project has been underway, replacing or installing new guardrails. This is multisite works to repair traffic barriers at road sections damaged during the 2022 natural disaster. Generally, the sites are at road sections over creek crossings. Each work site will require traffic control and the repair will generally be completed within 2 days. Recently, the work crew worked on Eltham and Boatharbour Road. Other road closures will be updated as scheduled work on Live Traffic.
Terania Creek – Bridge Updates
The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings completed for bridge 3. Commencement on bridge 2 is scheduled for early February.
FUTURE WORKSDorroughby Road
The road closure for Dorroughby Road was unfortunately delayed until 12 February with expected competition approximately 26 February, subject to change pending weather conditions. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing conditions. Road closure will be required around the works zone with the section located approximately 500 meters from the Dorroughby Road/Corndale Road intersection, between 791 Corndale Road and 65 Dorroughby Road. Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated. Please adhere to all road closed signs and directions from any traffic controllers.
Rogerson Road
A culvert replacement is planned for late February 2024. These works will require a road closure for up to 10 weeks subject to weather and resources availability. The existing culvert was damaged in the February 2022 natural disaster and has funding approved for a replacement structure with concrete pipes.
Newton Drive
A number of minor up slope landslips and a single pipe culvert are scheduled to be repaired during February. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Rosebank Road
Rosebank road slip will have restoration works completed during February. The works involve reinstating the property access track and restoring the batter and table drain along the road edge. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Johnston Road
Minor works on a damaged drainage culvert along Johnston Road will be completed in February. This will involve reinstating a rock blanket that was washed away in the February 22 Flood Event. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Leycester Road
Council wishes to advise funding has now been secured to reinstate the road to a suitable standard to ensure the community are able to travel safely along this road. The works are schedule to occur July 2024, notwithstanding another disaster event and subject to weather conditions, resources, and contractor availability. During works traffic will be impacted as the works will be carried out under Traffic Control stop/go arrangement and a reduced speed limit. At times traffic users may experience long delays to allow construction of the new pavement. Access to property driveways may be impacted or restricted at times however will ensure property owners are notified prior to this occurring. Motorists will be notified of the upcoming roadworks with VMS boards and updated through www.livetraffic.com closer to construction commencement. Emergency services vehicles will be accommodated if required. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.
Eureka Road, Graham Road & Haywood Lane
The design plans have changed for Eureka Road, Graham Road, and Haywood Lane. These sites were originally scheduled for culvert replacement; however, funding has been successfully acquired to upgrade these locations from box culverts to bridges. Currently, design for the project works is in final stages with the bridges due to be delivered to Council late February. The works are to be scheduled after delivery, this is subject to change pending weather conditions, resources, and contractor availability. We apologise in advance for any disruptions you may experience while we carry out this essential work. These works will involve removing the existing infrastructure at each site and preparing the area for bridge construction. To minimise impact to residents and traffic flow during the construction work a temporary track will be established as a side road. The works will take approximately 6 weeks at each site. -
Leycester Road - Funding Approval (Jan 2024)
Share on Facebook Share on Twitter Share on Linkedin Email this linkCouncil wishes to advise funding has been approved Leycester Road on 18 January 2024. The works are schedule to occur July 2024, notwithstanding another disaster event and subject to weather conditions, resources, and contractor availability. During works traffic will be impacted as the works will be carried out under Traffic Control stop/go arrangement and a reduced speed limit. At times traffic users may experience long delays to allow construction of the new pavement.
Motorists will be notified of the upcoming roadworks with VMS boards and updated through www.livetraffic.com closer to construction commencement. Emergency services vehicles will be accommodated if required. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.
Council also advises access to property driveways may be impacted or restricted at times however will ensure property owners are notified prior to this occurring.
What are the works?
Following the February 2022 natural disaster, Leycester Road suffered extensive damage. Funding has now been secured to reinstate the road to a suitable standard to ensure the community are able to travel safely along this road.
Project Timeline
The following timeline outlines the current expected times for the works.
Further Information
We apologise in advance for any disruptions you may experience while we carry out this essential work. Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Leycester Road – Jan 2024 Update.’ -
Leycester Road - Gravel Road Maintenance (Oct 2023)
Share on Facebook Share on Twitter Share on Linkedin Email this linkFollowing the February 2022 natural disaster, Leycester Road suffered extensive damage. Council completed temporary patching works to improve the road surface condition during December 2022. These works involved removing damaged road sections and replacing with gravel road base, with an emulsion sacrificial seal. The temporary patching works were a temporary measure, until permanent pavement rehabilitation works were scheduled.
The funding submission for a permanent pavement rehabilitation was completed in June 2023, and Council is awaiting on funding approval to commence work. We have also asked for priority funding to accelerate these works. When approved, works will apply to multiple sections that have been identified as significantly impacted by the February 2022 natural disaster, based on pre and post disaster assessments.
Council would like to improve the impact on residents while waiting for funding approval and have scheduled further gravel road maintenance works for next week. We would like to thank the community for their continuing patience.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Leycester Road – October 2023 Update.’
-
Flood Restoration - Roads & Bridges Update (Dec 2023)
Share on Facebook Share on Twitter Share on Linkedin Email this linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
CURRENT WORKS – SEALED & UNSEALED ROADS
Jiggi Road
Works have been completed on Jiggi Road to address immediate issues caused from the February and March 2022 floods. This has involved DGB20 overlay, pavement stabilisation, trimming and sealing of the road surface to repair flood damages. Further assessment is required and works will continue in 2023-24.
Ashlin Road
Overlay and drainage works are now completed on Ashlin Road to repair damages caused from the February and March 2022 floods. Leeson Road
Overlay and drainage works are now completed on Leeson Road to repair damages caused from the February and March 2022 floods.
Upper Tuntable Falls Road
Repair work was recently carried out for Upper Tuntable Falls Road. Overlay and drainage works are now completed to restore damages caused from the February and March 2022 floods.
Wallace Road
Wallace Road has recently undergone repair work up to the landslip. Overlay and drainage works are now completed to restore damages caused from the February and March 2022 floods.
COMPLETED WORKS – EMERGENCY ROAD REPAIRS
Tatham Road
Works were completed on Tatham Road to remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Tucki Road
Tucki Road works have removed and replaced existing material from the road surface, graded and rolled the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
CURRENT WORKS – SEALED ROADS
Riverbank Road
Works are continuing for Riverbank Road to repair the issues caused from the February and March 2022 floods, restoration works have been performed on Riverbank Road. These involved overlay, stabilise, trim and seal road surface to repair flood damages.
CURRENT WORKS – UNSEALED ROADS
Corndale Road
Corndale Road continues to undergo works to replace existing road surface, stabilise, trim and seal of existing road surface height to repair damages from the February and March 2022 floods.
East Road
Overlay and drainage works are currently being carried out on East Road to restore damages caused from the February and March 2022 floods.
Terania Creek Road
Work is currently underway between The Channon and Lawler Road on Terania Creek Road due to a landslip after Lawler Road. Overlay and drainage work are underway to repair damages caused from the February and March 2022 floods.
CURRENT WORKS – EMERGENCY ROAD REPAIRS
Keerrong Road
Works are continuing along Keerrong Road to overlay, stabilise, trim and seal road surface to repair damages from the February and March, 2022 floods.
Tuntable Creek Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Leycester Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.
CURRENT WORKS – DRAINAGE WORKS
Keerrong Road
Drainage works are continuing for Keerrong Road these include desilt and reshape table drainage, while installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.
CURRENT WORKS – RESTORATION WORKS
Restoration works are continuing along Tuntable Creek Road. Landslip repairs are currently underway through stabilisation works to allow rehabilitation of landslip and reinstatement of road and guardrail barrier.Tuntable Creek Road
The photos below outline the restoration effort including works performed by a 16-tonne hydraulic crawler mounted drill rig. This remote operated machine is designed for geotechnical site investigations and is drilling around 8m into the embankment.
FUTURE WORKS - SEALED ROADS
Cawongla Road / Quilty Road
All preliminary works on Cawongla Road are completed ready to commence works on the 3rd of January 2023. Quilty road has been graded and prepared for the detour route to commence on the 3rd of January 2023, vegetation trimming has been completed and drainage works have also been completed. These works have been completed with great cooperation for the public. For further information on the work, visit the Cawongla Road update -
Flood Restoration - Roads & Bridges Update (12th Dec 2022)
Share on Facebook Share on Twitter Share on Linkedin Email this linkROAD PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.
Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
CURRENT WORKS – SEALED ROADS
Riverbank Road
To repair the issues caused from the February and March 2022 floods, restoration works have been performed on Riverbank Road. These involved overlay, stablise, trim and seal road surface height to repair damages.
Jiggi Road
Likewise, Jiggi Road has undergone recent works to address issues caused from the February and March 2022 floods. This has involved overlay, stabilise, trim and seal road surface height to repair damages.
CURRENT WORKS – UNSEALED ROADS
Braidwood Road
Braidwood Road has recently had unsealed road works completed, the below image outlines the after result for the road.
Ashlin Road
Ashlin Road recently underwent repair works, these are now completed. The image below shows the before image of the roads condition.
Leeson Road
Unsealed road works were recently completed for Leeson Road. The below image outlines the before condition of the road.
Upper Tuntable Falls Road
Repair work was recently carried out and are now completed for Upper Tuntable Falls Road. The image below shows the before image of the roads condition.
CURRENT WORKS – EMERGENCY ROAD REPAIRS
Tatham Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Tucki Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
CURRENT WORKS – DRAINAGE WORKS
Keerrong Road
Desilt and reshape table drainage, while installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.
FUTURE WORKS – SEALED ROADS
Corndale Road
Replace existing road surface, stabilise, trim and seal of existing road surface height to repair damages from the February and March, 2022 floods.
Keerrong Road
Overlay, stabilise, trim and seal road surface height to repair damages from the February and March, 2022 floods.
FUTURE WORKS – UNSEALED ROADS
East Road, Mountain Top Road, East Road, Terania Creek Road & Wallace Road
Planning is in place to perform works shortly on the following unsealed roads: Terania Creek Road (Section before the landslip), Wallace Road, Mountain Top Road, and East Road.
FUTURE WORKS – EMERGENCY ROAD REPAIRS
Tuntable Creek Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Leycester Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.
Keerrong Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.
-
Leycester Road – Temporary patching works (Dec 2022)
Share on Facebook Share on Twitter Share on Linkedin Email this linkCouncil will be completing temporary patching works to improve road surface conditions for Leycester Road during December 2022. These works are a temporary measure, until permanent pavement rehabilitation works are scheduled.
Works will apply to multiple sections that have been identified as significantly impacted by the February 2022 natural disaster, based on pre and post disaster assessments. Funding has been secured through Transport for NSW. This funding is allocated to repair damage sustained during the February 2022 natural disaster only. Additional works required and subsequent funding for Leycester Road are being reviewed.
The temporary works are expected to occur throughout December 2022 subject to weather, contractor, and material availability. Single lane traffic control will be in place during the works period.
These temporary works will involve removing damaged road sections and replacing with gravel road base, with an emulsion sacrificial seal.
Future pavement repair works, expected to be carried out in mid-2023 will include:
- Road surface: Improve the surface of the road in places.
- Signs and line marking: Line marking and guideposts.
- Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
- Drainage maintenance: Re-excavate open drains and remove flood sediment as required. Minor drainage works will be completed prior to pavement works commencing.
- Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.
Road users are advised to follow signage and expect delays as these works are completed.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title ‘Leycester Road – Temporary Patching Works.’