Multiple Unsealed Gravel Roads - Grading Works (May 2024)
Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Facebook Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Twitter Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Linkedin Email Multiple Unsealed Gravel Roads - Grading Works (May 2024) linkCouncil wishes to advise of upcoming works on the listed roads below. The works involve grading over 120km of unsealed gravel roads which have been significantly damaged as a result of declared natural disaster events AGRN1101 (December 2023) and AGRN1119 (April 2024).
What are the works?Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first. Council is deploying six separate works crews and efforts have been made to cluster the works geographically to optimise efficiency and resource allocation.
The works will begin to commence this week, though will not all begin simultaneously due to contractor availability. These works will take approximately three months to complete, weather permitting.
We understand the importance of these roads to our daily commutes, emergency services, and local economy, and we are committed to restoring them to their optimal condition quickly. Motorists will be notified of road changes via roadside signage. We apologise in advance for any disruptions you may experience while we carry out this essential work.Crew 1
Crew 2
Priority
Road Name
Priority
Road Name
1
Davis Road
1
Gungas Road
2
Boggumbil Road
2
Shipway Road
3
Stead Road
3
Bishops Creek Road
4
Unnamed Lane West off Mountain Top (Georgica)
4
Parmenter Road
5
Clark Road
5
Keerrong Road
6
Unnamed Lane West off Clark
6
Quilty Road
7
Warby Road
7
Mulvena Road
8
Bertoli Road
9
Lodge Road
10
Stanger Road
11
Blade Road (West)
12
Cullen Road
13
Suffolk Road
14
Blade Road
Crew 3
Crew 4
Priority
Road Name
Priority
Road Name
1
Terania Creek Road
1
Upper Coopers Creek Road
2
Lawler Road
2
Minyon Falls Road
3
Rankin Road
3
Fox Road
4
Greengate Road
4
Nightcap Range Road
5
Unara Road
5
Lychee Drive
6
Walmsley Road
6
Armstrong Road
7
Virtue Road
8
Behan Access
9
Lavis Road
10
McKinnon Road
Crew 5
Crew 6
Priority
Road Name
Priority
Road Name
1
McInnes Road
1
Wallace Road
2
Monaltrie Road
2
Rose Road
3
Bice Road
3
Pinchin Road
4
Yeager Road
4
Izzard Road
5
Eastment Lane
5
Paterson Road
6
McMahon Road
6
Arkinstall Road
7
Muldoon Road
8
Norton Road
9
Lavis Road
10
McKinnon Road
We are in the process of assessing various additional roads to be included in the scope of these recovery works. Our goal is to ensure comprehensive restoration and long-term resilience of our unsealed gravel road network. The funding for this engagement is granted by Transport for NSW (TfNSW) under the Disaster Recovery Funding Arrangements (DRFA) guidelines to reconstruct eligible assets to pre-disaster function.
Works Criteria
The works have been carefully distributed and prioritised based on the following criteria:
- Scale of Damage: Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first.
- Contractor Availability: We have coordinated with available contractors to expedite the commencement of these essential repairs.
- Group Locality: Efforts have been made to cluster the works geographically to optimise efficiency and resource allocation.
Further Information
This notification will be posted on our Your Say dedicated Flood Recovery – Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges.
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Unsealed Gravel Roads – May 2024 Update.’ -
Flood Restoration - Roads & Bridges Update (5th Dec 2022)
Share Flood Restoration - Roads & Bridges Update (5th Dec 2022) on Facebook Share Flood Restoration - Roads & Bridges Update (5th Dec 2022) on Twitter Share Flood Restoration - Roads & Bridges Update (5th Dec 2022) on Linkedin Email Flood Restoration - Roads & Bridges Update (5th Dec 2022) linkROAD PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.
Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
Sealed Pavements
Nimbin Road
Pavement works have been completed at Nimbin Road near the intersection of Shipway Road.Riverbank Road
Works have started at Riverbank Road to complete permanent pavement stabilisation works consisting of overlaying 150mm of DGB20 then mixing a conforming road pavement.
Jiggi Road
The team are continuing to undertake pavement repairs on various sections of Jiggi Road.
Drainage Work
Riverbank Road
The following photos outline the completed drainage work for Riverbank Road.
Emergency Temporary Pavement Repair
Rock Valley Road / Cawongla Road
Sections of temporary road pavement which have been identified and planned for return early next year.
Tatham Road
Sections of road pavement which have been temporarily with a planned return early next yearUnsealed Pavements
The team have completed unsealed pavement works at Gordon Road, Parmenter Road, Savins Road, Houlden Road, Nightcap Range Road and Whian Whian Road.
Culverts
Cawongla Road
Multiple culvert works are now complete along Cawongla Road. These include culverts near Larnook School with 1 x 900mm and 1 x 600mm culvert successfully replaced and material being stockpiled for replacement of a twin cell 1350mm culvert (culvert with deep depression within the roadway). These works will continue until Christmas, after which the road closure and replacement works can be undertaken. Additionally, material is being stockpiled for replacement of Twin cell 1800mm culvert at 169 Cawongla Road, these works will continue until Christmas, after which the road closure and replacement works can be undertaken. It is anticipated that the tree lopping within this area will be completed prior to Christmas.
Quilty Road detour route works
Currently works are being undertaken to upgrade Quilty Road to ensure adequate width of the gravel pavement for two lane traffic and to improve road pavement surface.