Flood Restoration - Roads & Bridges Update (5th Dec 2022)
ROAD PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.
Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
Sealed Pavements
Nimbin Road
Pavement works have been completed at Nimbin Road near the intersection of Shipway Road.
Riverbank Road
Works have started at Riverbank Road to complete permanent pavement stabilisation works consisting of overlaying 150mm of DGB20 then mixing a conforming road pavement.
Jiggi Road
The team are continuing to undertake pavement repairs on various sections of Jiggi Road.
Drainage Work
Riverbank Road
The following photos outline the completed drainage work for Riverbank Road.
Emergency Temporary Pavement Repair
Rock Valley Road / Cawongla Road
Sections of temporary road pavement which have been identified and planned for return early next year.
Tatham Road
Sections of road pavement which have been temporarily with a planned return early next yearUnsealed Pavements
The team have completed unsealed pavement works at Gordon Road, Parmenter Road, Savins Road, Houlden Road, Nightcap Range Road and Whian Whian Road.
Culverts
Cawongla Road
Multiple culvert works are now complete along Cawongla Road. These include culverts near Larnook School with 1 x 900mm and 1 x 600mm culvert successfully replaced and material being stockpiled for replacement of a twin cell 1350mm culvert (culvert with deep depression within the roadway). These works will continue until Christmas, after which the road closure and replacement works can be undertaken. Additionally, material is being stockpiled for replacement of Twin cell 1800mm culvert at 169 Cawongla Road, these works will continue until Christmas, after which the road closure and replacement works can be undertaken. It is anticipated that the tree lopping within this area will be completed prior to Christmas.
Quilty Road detour route works
Currently works are being undertaken to upgrade Quilty Road to ensure adequate width of the gravel pavement for two lane traffic and to improve road pavement surface.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends